Province | Subbasin | % |
---|---|---|
Mountain Snake | Clearwater | 100.00% |
Previous: | Next: |
---|---|
n/a |
|
* Expenditures data includes accruals and are based on data through 31-Mar-2025.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Brenda Aguirre | Bonneville Power Administration | No | Env. Compliance Lead | baguirre@bpa.gov | (503) 230-5928 |
Anne Connor | US Forest Service (USFS) | Yes | Contract Manager | aconnor@fs.fed.us | (208) 476-8235 |
Lois Geary | US Forest Service (USFS) | No | Administrative Contact | lgeary@fs.fed.us | (208) 983-7008 |
Mark Johnson | Nez Perce Tribe | Yes | Technical Contact | markj@nezperce.org | (208) 621-3561 |
David Kaplowe | Bonneville Power Administration | Yes | COR | djkaplowe@bpa.gov | (503) 230-5365 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Rebecca Lloyd | Nez Perce Tribe | No | Technical Contact | rebeccal@nezperce.org | (202) 621-3544 |
Heidi McRoberts | Nez Perce Tribe | Yes | Technical Contact | heidim@nezperce.org | (208) 621-3548 |
Khanida Mote | Bonneville Power Administration | Yes | Contracting Officer | kpmote@bpa.gov | (503) 230-4599 |
Tom Reilly | US Forest Service (USFS) | No | Supervisor | treilly@fs.fed.us | (208) 476-8273 |
A | 24639 | 165 | Produce Environmental Compliance Documentation | Provide environmental compliance information to BPA for projects on Forest Service Lands | All applicable NEPA, ESA and cultural resources consultation will be completed for all contract activities by the Clearwater National Forest. | $0 | 0.00% | 03/01/2007 | 05/31/2007 |
B | 24641 | 184 | Install Fish Passage Structure | Replace Rat Creek Culvert | A BPA funded culvert inventory and assessment was completed by the NPT for the entire Lolo Creek watershed in 2004. The Rat Creek culvert was identified as a high priority for replacement in the watershed as it is undersized and does not pass all life stages of fish. This work element will return fish passage to 4.3 miles of stream by removing and replacing the existing culvert that is a spring Chinook and steelhead migration barrier. The culvert is located at T33N/R6E/Sec.33. The CNF will offer and manage contract installations. Funding will come from BPA (to both NPT and CNF), as well as CNF in-kind and cost contributions. | $50,000 | 71.47% | 03/01/2007 | 09/30/2007 |
C | 24642 | 184 | Install Fish Passage Structure | Replace Snowshoe Creek Culvert | A BPA funded culvert inventory and assessment was completed by the NPT for the entire Lolo Creek watershed in 2004. The Snowshoe Creek culvert was identified as a high priority for replacement in the watershed as it is undersized and does not pass all life stages of fish. This work element will return fish passage to 0.9 miles of stream by removing and replacing the existing culvert that is a spring Chinook and steelhead migration barrier. The culvert is located at T34N/R6E/Sec.8. The CNF will offer and manage contract installations. Funding will come from BPA (to both NPT and CNF), as well as CNF in-kind and cost contributions. | $19,958 | 28.53% | 03/01/2007 | 09/30/2007 |
D | 24640 | 119 | Manage and Administer Projects | Management, Coordination and Communication | Project management includes coordinating project activities, attending meetings and workshops, seeking additional funding, prioritizing and scheduling of projects, employee supervision, preparing statements of work, managing budgets, and completing reports. The Nez Perce Tribe and the CNF (Clearwater National Forest) have been partners in watershed restoration since 1996, which includes sharing funds and resources to complete projects. Each year, project specifics are spelled out in an agreement that is signed by both parties. | $0 | 0.00% | 03/01/2007 | 02/29/2008 |
E | 24801 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables on a quarterly basis in Pisces. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR. | $0 | 0.00% | 07/01/2007 | 02/29/2008 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental compliance documentation submitted to BPA | A: 165. Provide environmental compliance information to BPA for projects on Forest Service Lands | 05/31/2007 | 07/16/2007 | |
Culvert replacement complete | B: 184. Replace Rat Creek Culvert | 09/30/2007 | 09/04/2007 | |
Culvert replacement complete | C: 184. Replace Snowshoe Creek Culvert | 09/30/2007 | 09/04/2007 | |
FY 08 SOW package and accrual estimate | D: 119. Management, Coordination and Communication | 01/31/2008 | 01/31/2008 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Cutthroat Trout, Westslope (O. c. lewisi) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Provide environmental compliance information to BPA for projects on Forest Service Lands | 02/09/2007 | ||||||
B | 184 | Replace Rat Creek Culvert | 05/26/2004 | ||||||
C | 184 | Replace Snowshoe Creek Culvert | 05/26/2004 | ||||||
D | 119 | Management, Coordination and Communication | 02/09/2007 | ||||||
E | 185 | Periodic Status Reports for BPA | 02/09/2007 |