SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 45993 (02/01/2010 - 01/31/2011) | $3,000 | $1,500 | ||
Work Element Budget (Current Performance Period) | $3,000 | $1,500 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | FPCIR | Funding Package - Conduct internal review (e.g., Supervisor or Interagency) | 10/1/2010 | 10/31/2010 | Concluded | David Byrnes (Inactive) | 4/16/2010 9:31:44 AM |
Description: If necessary, submit next year's SOW and Budget for internal contractor review before submitting to BPA. Assuming this review takes 30 days, start this milestone 120 days before the end of the current contract. | |||||||
B | ASSEB | Accrual - Submit September estimate to BPA | 8/25/2010 | 9/10/2010 | Concluded | David Byrnes (Inactive) | 4/16/2010 9:31:44 AM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Generally, this should be done by September 10. | |||||||
C | DELIV | All BPA Contract Documents | 1/30/2011 | Concluded | David Byrnes (Inactive) | 4/16/2010 9:31:44 AM | |
Description: FY11 Pisces SOW, Excel budget (with sub-contractor budgets if applicable), Property Inventory, and FY10September Accruals (work performed but not invoiced by 9/30/2010) |