2008-105-00 EXP SELECTIVE GEAR DEPLOYMENT
Contract Start Date:
6/1/2011
Contract End Date:
5/31/2012
Title:
A: 165 - Determine which ESA, and waterway permits, and NEPA compliance are needed and obtain.
Description:
It is anticipated that no additional environmental compliance documentation will be required in this phase of work, because of existing ESA, JARPA, and HPA. However, investigation will continue determining level of NEPA / ESA required for a weir, working closely with BPA Environmental Compliance staff.

JARPA has been submitted for scaffolds to be constructed in the Chief Joseph Dam tailrace for hoop and dip net fishing.
WE Agreement Type:
Contracted
Deliverable Specification:
Work with BPA Environmental Compliance lead and Live Capture project subcontractors to determine level of EC needed for the 2011 & 2012 contract years
WSE Effective Budget:
$81,000
% of Total WSE Effective Budget:
10.53%
WSE Start:
06/01/2011
WSE End:
05/31/2012
WSE Completion:
05/01/2012
WSE Progress:
Concluded
WSE ID Continued From:
n/a
WSE ID Continued To:
n/a
Finite or Recurring:
Recurring

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $20,000 $81,000 Securing State HPA for weir work has blown contractor budget for permit line item

5 Milestones
Sort Type Title Start End Status Modified By Modified Date
A Suggested Obtain/Renew applicable local, state, federal and tribal environmental permits 6/1/2011 5/31/2012 Concluded Michael Rayton (Inactive) 2/16/2011 9:34:05 AM
Description: Obtain and renew permits where applicable. ESA Section 10, State or Tribal HPA, Shoreline, Cultural Resource, Submit annual reports to issuing agencies when required.
B Suggested Assist BPA's EC Lead to meet necessary environmental compliance requirements 6/1/2011 5/31/2012 Concluded Michael Rayton (Inactive) 2/16/2011 9:34:06 AM
Description: Involves coordinating with the EC Lead to move forward with projects within the program, such as the Okanogan Weir.
C Suggested Participate in ESA Consultation (may include drafting BA, completing HIP BO Consistency Form, etc.) 6/1/2011 5/31/2012 Concluded Michael Rayton (Inactive) 2/16/2011 9:34:06 AM
Description: Includes participation in the crafting of a Tribal Resource Management Plan (TRMP) for blanket coverage of fish harvest and monitoring activities under the ESA
D Suggested Inspect water craft and equipment to be used in or near water for aquatic invasive species 7/1/2011 11/1/2011 Concluded Michael Rayton (Inactive) 2/16/2011 9:34:07 AM
Description: Take preventative measures to prevent the spread of Eurasian Watermilfoil
E DELIV Determine which ESA, and waterway permits, and NEPA 5/31/2012 Concluded Michael Rayton (Inactive) 2/16/2011 8:41:46 AM
Description: Work with BPA Environmental Compliance lead and Live Capture project subcontractors to determine level of EC needed for the 2011 & 2012 contract years

This work element does not require Focal Species
This work element does not require Environmental Compliance
This work element does not require RM&E metadata