This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $20,000 | $81,000 | Securing State HPA for weir work has blown contractor budget for permit line item |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Suggested | Obtain/Renew applicable local, state, federal and tribal environmental permits | 6/1/2011 | 5/31/2012 | Concluded | Michael Rayton (Inactive) | 2/16/2011 9:34:05 AM |
Description: Obtain and renew permits where applicable. ESA Section 10, State or Tribal HPA, Shoreline, Cultural Resource, Submit annual reports to issuing agencies when required. | |||||||
B | Suggested | Assist BPA's EC Lead to meet necessary environmental compliance requirements | 6/1/2011 | 5/31/2012 | Concluded | Michael Rayton (Inactive) | 2/16/2011 9:34:06 AM |
Description: Involves coordinating with the EC Lead to move forward with projects within the program, such as the Okanogan Weir. | |||||||
C | Suggested | Participate in ESA Consultation (may include drafting BA, completing HIP BO Consistency Form, etc.) | 6/1/2011 | 5/31/2012 | Concluded | Michael Rayton (Inactive) | 2/16/2011 9:34:06 AM |
Description: Includes participation in the crafting of a Tribal Resource Management Plan (TRMP) for blanket coverage of fish harvest and monitoring activities under the ESA | |||||||
D | Suggested | Inspect water craft and equipment to be used in or near water for aquatic invasive species | 7/1/2011 | 11/1/2011 | Concluded | Michael Rayton (Inactive) | 2/16/2011 9:34:07 AM |
Description: Take preventative measures to prevent the spread of Eurasian Watermilfoil | |||||||
E | DELIV | Determine which ESA, and waterway permits, and NEPA | 5/31/2012 | Concluded | Michael Rayton (Inactive) | 2/16/2011 8:41:46 AM | |
Description: Work with BPA Environmental Compliance lead and Live Capture project subcontractors to determine level of EC needed for the 2011 & 2012 contract years |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1479. Are herbicides used as part of work performed under this contract? | No | No | |||
1722. Will water craft, heavy equipment, waders, boots, or other equipment be used from outside the local watershed as part of work performed under this contract? | No | No |