SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 56441 (04/01/2012 - 03/31/2013) | $10,000 | $10,000 | ||
Work Element Budget (Current Performance Period) | $10,000 | $10,000 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | FPCIR | Funding Package - Conduct internal review (e.g., Supervisor or Interagency) | 12/3/2012 | 12/31/2012 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM |
Description: Warm Springs Habitat Program Manager and Restoration Ecologist provides oversight and work coordination for the Oxbow Conservation Area. The Habitat manager position is funded for a total of 4 weeks, and the Restoration Ecologist is for 1 month in this work element. Position provides coordination for fiscal tracking, contracts, time sheets, and purchasing throughout the contract period. If necessary, submit next year's SOW and Budget for internal contractor review before submitting to BPA. Assuming this review takes 30 days, start this milestone 120 days before the end of the current contract. | |||||||
B | Oversight and technical support | 4/1/2012 | 3/31/2013 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM | |
Description: Warm Springs Habitat Program Manager and Restoration Ecologist provides oversight and work coordination for the Oxbow Conservation Area. The Habitat manager position is funded for a total of 4 weeks, and the Restoration Ecologist is for 1 month in this work element. Position provides coordination for fiscal tracking, contracts, time sheets, and purchasing throughout the contract period. | |||||||
C | Administration Support | 4/1/2012 | 3/31/2013 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM | |
Description: John Day Basin Office Secretary and Warm Springs Administration | |||||||
D | Training/Symposiums | 4/1/2012 | 3/31/2013 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM | |
Description: Provide Project staff with funding to attend training for restoration symposiums and trainings, ARC View and local resource management workshops. | |||||||
E | Produce SOW package for BPA COTR Revew | 12/3/2012 | 12/31/2012 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM | |
Description: Provide draft SOW, budget, spending plan, and inventory for COTR in Pisces. Should be finished in Early December, pending various factors. | |||||||
F | Submit BPA 2011 Project income and expense report | 12/3/2012 | 1/18/2013 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM | |
Description: Provide statement to BPA COTR that details all income created by property management to date, to include all CREP payments, up through January 31st, and what expenses that are projected to be paid from the income. This will be used to consider offset of BPA funding. | |||||||
G | ASSEB | Accrual - Submit September estimate to BPA | 9/1/2012 | 9/14/2012 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Generally, this should be done by September 10. | |||||||
H | Provide GIS training and support to GIS staff as necessary for work performed on property maps | 4/1/2012 | 3/31/2013 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM | |
Description: Provide GIS training for staff involved in map making and provide necessary support to staff involved in all GIS related issues. | |||||||
I | DELIV | Project management | 3/31/2013 | Concluded | Jason Karnezis | 5/14/2012 1:32:12 PM | |
Description: Provide funding for training, symposiums, staff, and Tribal administrative support. Also provide BPA with work proposals, SOW for 2012, and BIOP/Metrics. Work with BPA on administrative duties that result over the course of the PP. |