This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 60059 (01/02/2013 - 01/31/2014) | $43,597 | $94,871 | ||
2. Amendment 001 (01/02/2013 - 08/31/2013) | $63,940 | $94,871 | ||
Work Element Budget (Current Performance Period) | $94,871 | $94,871 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Attend kick-off/orientation meeting with BPA | 1/8/2013 | 1/8/2013 | Concluded | Jay Marcotte (Inactive) | 6/7/2013 11:45:15 AM | |
Description: Meet with key BPA staff to develop a shared understanding of the goals, objectives, strategies and schedule for this contract (teleconference acceptable). | |||||||
B | Review existing information | 1/2/2013 | 1/16/2013 | Concluded | Jay Marcotte (Inactive) | 6/7/2013 11:45:15 AM | |
Description: Existing information to be reviewed is attached in Pisces at the project level (2000-038-00) and includes: ISRP 2007-2009 Proposal Review Comments for Project, 2008 CTUIR HMP (including appendices), 2008 ISRP Comments, 2010 CTUIR Comment Responses, 2010 ISRP Comments on CTUIR Responses, 2012 Draft HGMP as submitted to NOAA 2012 Co-Manager MOA (CTUIR-WDFW-ODFW) | |||||||
C | Develop HMP strategy/schedule for BPA approval | 1/16/2013 | 1/23/2013 | Concluded | Jay Marcotte (Inactive) | 6/7/2013 11:45:15 AM | |
Description: See deliverable specs | |||||||
D | Draft Hatchery Management Plan for submittal for ISRP review | 1/23/2013 | 4/1/2013 | Concluded | Jay Marcotte (Inactive) | 6/7/2013 11:45:15 AM | |
Description: see deliverable specs | |||||||
E | Assist BPA in responding to any ISRP comments on HMP | 7/15/2013 | 10/31/2013 | Concluded | Jay Marcotte (Inactive) | 7/10/2013 11:42:23 AM | |
Description: Review and provide responses to ISRP on revised HMP | |||||||
F | Assist BPA in presentation of HMP package to NPCC | 9/1/2013 | 10/31/2013 | Concluded | Jay Marcotte (Inactive) | 7/10/2013 11:42:23 AM | |
Description: Support BPA in presentation of Revised Step 1 HMP to ISRP and NPCC. Due to delays in processing the draft HMP, the date for this MS is uncertain, but expected to occur by September/October, 2013. | |||||||
G | Assist BPA in presentation of HMP package to F&W Committee | 8/1/2013 | 10/31/2013 | Concluded | Jay Marcotte (Inactive) | 7/10/2013 11:42:23 AM | |
Description: Support BPA in presentation of Revised Step 1 HMP to F&W committee. Due to delays in processing the draft HMP, the date for this MS is uncertain, but expected to occur by August/September, 2013. | |||||||
H | DELIV | Produce a comprehensive new HMP addressing all outstanding NPCC/ISRP issues | 10/31/2013 | Concluded | Jay Marcotte (Inactive) | 6/7/2013 11:45:15 AM | |
Description: The new HMP will include the following at a minimum: •Incorporate any updated M&E and passage/habitat info completed since 2010. This might include spawning survey results, scale sample analysis, etc as needed to update conclusions about population status, habitat carrying capacity, etc.. Clarify and expand on CTUIR’s M&E approach as needed. •Assess and resolve technical issues related to PNI, PNOS vs PHOS, SARs, AARs etc. •Assess the validity/applicability of the EDT model used in the HMP to assess habitat carrying capacity. Identify whether other models exist that could meet this accomplish this task. No additional modeling is expected to be required. •Clarify and expand upon CTUIR’s proposed approach to Adaptive Management as communicated in the 2008 HMP and the 2010 Comment Responses. •Clarify and expand on CTUIR’s “decision framework” (Appendix X – Fish Disposition Model). Provide narrative examples of how the model would inform management decisions across a representative range of key or likely scenarios involving adult return numbers and timing, water and habitat conditions, etc. |