SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $1,000 | $500 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Submit draft annual report to NOAA Fisheries | 10/1/2005 | 11/1/2005 | Concluded | Christopher (UAF) Binckley (Inactive) | 2/7/2006 8:34:56 AM | |
Description: Submit a draft annual report for the previous performance period (October 1, 2004 through September 30, 2005) | |||||||
B | Receive comments from NOAA Fisheries | 11/1/2005 | 11/15/2005 | Concluded | Christopher (UAF) Binckley (Inactive) | 2/7/2006 8:34:59 AM | |
Description: BPA COTR should provide comments within 15 days of receiving a draft annual report. | |||||||
C | Submit final report to NOAA for approval | 11/15/2005 | 12/1/2005 | Concluded | Christopher (UAF) Binckley (Inactive) | 2/7/2006 8:35:01 AM | |
Description: Within 15 days of receiving draft annual report comments from the COTR, the contractor shall submit a revised FINAL version to BPA. | |||||||
D | DELIV | Final Approved Annual Report submitted to NOAA and a copy sent to BPA COTR | 11/30/2005 | Concluded | Gerald McClintock (Inactive) | 2/13/2006 2:31:32 PM | |
Description: An annual report will be prepared as outlined in1-6 below: 1. Brief abstract (limit 600 words). 2. Introduction based on project purpose and rationale. 3. Concise description of project area. 4. Description of methods and materials used to perform tasks. 5. Summary of results (effectiveness of task completion; presentation of summarized field data in tabular or GIS format) and brief discussion of results by task. 6. If necessary, supplemental electronic copies of summarized field data in spreadsheet or GIS format." Annual Report: The Contractor must submit a draft Annual Report due no later than 30 days after the end of the prior annual performance period. The report shall be submitted to the Principal Investigator, Chris Jordan, at the Northwest Fisheries Science Center, as well as to the BPA Project Manager / COTR. |