This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $40,000 | $20,000 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 5/1/2014 | 5/2/2014 | Concluded | Nick Bean | 2/4/2014 1:00:18 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Suggested | Hold an initial meeting for kick off/scoping | 7/1/2014 | 10/31/2014 | Concluded | Nick Bean | 1/28/2014 3:46:39 PM |
Description: Meeting will be held with appropriate stakeholders and fisheries management agencies to review all relevant information regarding the Box Canyon Reservoir northern pike population and draft the framework for producing a plan for managing Pend Oreille River northern pike in the future, beginning in 2015. | |||||||
C | Suggested | Prepare draft plan | 7/1/2014 | 12/1/2014 | Active | Nick Bean | 1/28/2014 3:46:39 PM |
Description: Following the scoping/kickoff meeting, a draft plan will be produced for managing Pend Oreille River northern pike in the future. The plan will include background research on the population, suppression results (2012-2014), monitoring strategies, a management strategy with thresholds for action and alternatives, resource management agencies' responsibilities, and financial estimates and potential funding sources for management strategies. | |||||||
D | Suggested | Hold a meeting for final review | 12/1/2014 | 2/26/2015 | Active | Jason Olson | 2/5/2014 11:00:29 AM |
Description: Once the draft Pend Oreille River long-term northern pike management plan is available, a review meeting will take place with the original stakeholders to provide final comments and suggestions on the plan. The group will also determine what level of management to implement in 2015 (short-term) and approve the plan assuming comments/suggestions are considered. | |||||||
E | Produce final plan | 12/1/2014 | 2/26/2015 | Active | Jason Olson | 2/5/2014 11:00:29 AM | |
Description: Following the scoping/kickoff meeting, drafting and stakeholder review, the final long-term Pend Oreille River northern pike management plan will be edited and finalized. Once finalized, the plan will be active and short and long term management activities can commence. This plan will be reviewed annually and adapted as necessary with the production/analysis of new data and changes in the Pend Oreille River northern pike population. The final plan will be available to the public and included as an appendix to the FY2014-15 Kalispel Tribe Non-Native Fish Suppression BPA project (2007-149-00) annual report. | |||||||
F | DELIV | Produce a long-term monitoring and management plan for Pend Oreille River (WA) northern pike | 4/30/2015 | Active | Nick Bean | 1/28/2014 3:46:40 PM | |
Description: Assemble and facilitate meetings with fisheries management agencies and stakeholders to produce a management plan to guide the future monitoring and management direction of northern pike in Box Canyon Reservoir, Pend Oreille River, WA . |