Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program

Summary

RSS Feed for updates to BOG Change Request #272 for Project 2002-070-00 Follow this via RSS feed. Help setting up RSS feeds?
BOG Change Request #272 for Project 2002-070-00

BOG Change Request #272 (None) for Project 2002-070-00


Author Information:   Christine Read - Bonneville Power Administration
Primary Contact Information:   None


Request Status: BPA Approved
Scheduled for Meeting: Unscheduled
Project Number:2002-070-00
Project Name:Lapwai Creek Anadromous Habitat
Proponents:Nez Perce Soil and Water Conservation District (SWCD)
BPA Project Manager: Virginia Preiss
  
Author: Christine Read
Requesting changes to:Budget

Explanation of Need:

IMPORTED FROM CBFWA MODIFICATIONS DATABASE ON 01-07-2010

"Explanation or Additional Information"

The original budget tasks are for task 4.1 and 4.2 which total 132, 683. Task 4.1 original budget was 25,810. All funds for this task need to be rescheduled. However, task 4.2 was originally for $106,873. This task has numerous components. Several of these components will be completed as scheduled so the entire amount does not need to be rescheduled. The amount for rescheduling for task 4.2 is $38,000. Task 4.1 is a high priority project and has been identified as one of the top two fish barriers in the Lapwai Creek watershed. Completion of this task will result in the restoration of approximately 15 miles of habitat. Task 4.1 is a cost-shared project with PL566 program. The PL566 program will be contributing 65% of project costs and the BPA 35%. The PL566 funds will not be available after 2005 due to funding deadlines. Completion of tasks in 4.2 are for erosion control, barrier removal, and in-stream cover. These projects were identified as priorities and are cost-shared with other funding sources (USDA EQIP and PL566). THe PL566 funds will not be available after 2005 due to program deadlines.

"Budget Impact"

$0.00

Plan to proceed if request is denied:

"Reducing existing scope of project"

Reducing the scope of the 2005 project would prevent the installation of planned practices for 2005 and also delay the completion of the stream fish habitat inventory. The completion of the inventory is critical to match the Nez Perce Tribe's monitoring schedule and allow the prioritization of reach restoration. In addition, the rescheduled projects are cost-shared with the PL566 program. The PL566 funds will not be available after 2005 due to program deadlines.

"Shifting entire schedule"

Shifting will delay the completion of the stream inventory. Ths inventory will be used by other projects and agencies to make prioritization decisions. In addition, the projects that are being rescheduled are not a major time increase to NPSWCD staff. The majority of the design and permitting work is being completed by partner agencies. PL566 funds which are used to match 65% of the project costs will not be available after 2005, due to program deadlines.

Please explain any NEW cost share associated with this request:

None

 

No Budget changes in Change Request.


Fiscal Year Account Type Adjustment Adjustment Type
2005 Expense $0 Within-Year

View Budget Transfers for this project


Date Time Type From To By
12/30/2004 12:00 AM Status BPA Approved

Go To Project Overview for Project 2002-070-00: Lapwai Creek Anadromous Habitat

Project Number:
2002-070-00
Title:
Lapwai Creek Anadromous Habitat
Summary:
This project restores, protects and enhances steelhead spawning and rearing habitat in the Lapwai Creek Watershed. Information is collected to fill data gaps and BMPs are installed on agricultural and forest lands to achieve biological objectives.

Lapwai Creek historically provided spawning and rearing habitat for A-run wild summer steelhead in the Clearwater River Subbasin. However, the regular occurrence of extreme high runoff events and low summer flows, high summer water temperatures, poor instream/riparian cover, and siltation of spawning gravels have become limiting factors in the watershed. Low stream flows and a lack of adequate multi-layered riparian vegetation along with excessive sediment have reduced the suitability of Lapwai Creek and its tributaries as quality spawning and rearing habitat for anadromous and resident cold water fish. In addition, sediment, nutrients, and bacteria from existing land use practices adversely impact water quality. The primary pollutant sources and habitat degradations are agricultural, livestock, forestry and road practices. The large percentage of private land and low agricultural commodity prices prohibit landowners from implementing practices to solve these problems.

The Nez Perce Soil and Water Conservation District (NPSWCD or District) requested funding for the Restoring Fish Habitat in the Lapwai Creek Watershed project proposal to enhance steelhead trout natural production within the Lapwai Creek watershed by improving salmonid spawning and rearing habitat. The project funds coordination, planning, technical assistance, conservation practice design and implementation, monitoring, and educational outreach to identify and correct problems associated with agricultural and livestock activities impacting water quality and salmonid habitat. The project addresses specific needs identified in the Clearwater Subbasin Summary 2001 Draft and the 2000 Columbia River Basin Fish and Wildlife Program documents.

This proposal was coordinated with the Idaho Department of Fish and Game (IDFG), Idaho Department of Environmental Quality (DEQ), University of Idaho (U of I), Nez Perce Tribe (NPT), Clearwater Focus Program, Clearwater Basin Weed Committee, and the Nez Perce County Board of Commissioners.
Proposer:
None
Proponent Orgs:
Nez Perce Soil and Water Conservation District (SWCD) (SWCD)
Starting FY:
2002
Ending FY:
2025
BPA PM:
Stage:
Implementation - Project Status Report
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
Chinook - Snake River Fall ESU
Chinook - Snake River Spring/Summer
Chinook - Snake River Spring/Summer ESU
Chinook - Upper Columbia River Spring ESU
Coho - Unspecified Population
Lamprey, Pacific
Lamprey, River
Other Resident
Pikeminnow, Northern
Steelhead - All Populations
Steelhead - Snake River DPS
Trout, Interior Redband
Trout, Rainbow
Whitefish, Mountain
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Special:
None
BiOp Association:
FCRPS 2008 - view list of FCRPS 2008 BiOp Actions


Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

Decided Budget Transfers  (FY2024 - FY2026)

Acct FY Acct Type Amount Fund Budget Decision Date
FY2024 Expense $270,918 From: BiOp FCRPS 2008 (non-Accord) FY24 SOY Budget Upload 06/01/2023
FY2025 Expense $270,918 From: BiOp FCRPS 2008 (non-Accord) FY25 SOY 05/31/2024

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2025
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2023 (Draft)
2022 $556,392 68%
2021 $461,925 64%
2020 $562,958 68%
2019 $360,753 58%
2018 $490,683 65%
2017 $675,125 72%
2016 $312,166 54%
2015 $299,907 53%
2014 $229,218 47%
2013 $399,936 60%
2012 $343,216 57%
2011 $318,936 53%
2010 $236,864 47%
2009 $233,653 47%
2008 $255,712 50%
2007 $228,635 64%

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
11573 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 LAPWAI CREEK ANADROMOUS FISH Closed $686,924 9/1/2002 - 3/31/2005
21982 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 RESTORING ANAD. FISH HABITAT IN LAPWAI CREEK WATERSH Closed $330,374 3/1/2005 - 3/31/2006
26945 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION Closed $332,796 3/1/2006 - 6/30/2007
32840 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION Closed $129,957 4/1/2007 - 4/30/2008
38238 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION Closed $259,103 5/1/2008 - 8/31/2009
42391 SOW Nez Perce Soil and Water Conservation District (SWCD) 200207000 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION Closed $495,863 5/1/2009 - 4/30/2011
39929 REL 3 SOW Nez Perce Tribe CULTURAL RESOURCE INVENTORY OF THE 2010 NEZ PERCE SOIL AND WATER Closed $7,482 5/15/2010 - 8/15/2010
52837 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NP SWCD LAPWAI CREEK WATERSHED RESTORATION Closed $272,228 5/1/2011 - 8/31/2012
39929 REL 6 SOW Nez Perce Tribe NEZ PERCE TRIBE CR PROGRAM-LAPWAI CREEK PROJECT Closed $13,282 8/12/2011 - 12/30/2011
57048 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION Closed $261,756 5/1/2012 - 4/30/2013
61265 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION Closed $261,759 5/1/2013 - 7/31/2014
64969 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION Closed $261,759 5/1/2014 - 4/30/2015
68701 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION Closed $261,759 5/1/2015 - 4/30/2016
72618 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NPSWCD - LAPWAI CK WATERSHED RESTORATION Closed $268,284 5/1/2016 - 4/30/2017
75932 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP LAPWAI CREEK WATERSHED RESTORATION Closed $268,272 5/1/2017 - 4/30/2018
79145 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NP SWCD LAPWAI CREEK WATERSHED RESTORATION Closed $268,303 5/1/2018 - 4/30/2019
82058 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP NP SWCD LAPWAI CREEK WATERSHED RESTORATION Closed $259,500 5/1/2019 - 6/30/2020
85245 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP LAPWAI CREEK WATERSHED RESTORATION Closed $259,496 5/1/2020 - 4/30/2021
87866 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP LAPWAI CREEK WATERSHED RESTORATION Closed $259,455 5/1/2021 - 4/30/2022
90256 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP LAPWAI CREEK WATERSHED RESTORATION Closed $259,500 5/1/2022 - 4/30/2023
92377 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP LAPWAI CREEK WATERSHED RESTORATION Closed $259,500 5/1/2023 - 4/30/2024
94706 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP LAPWAI CREEK WATERSHED RESTORATION Issued $270,918 5/1/2024 - 4/30/2025
CR-375383 SOW Nez Perce Soil and Water Conservation District (SWCD) 2002-070-00 EXP LAPWAI CREEK WATERSHED RESTORATION Pending $270,918 5/1/2025 - 4/30/2026



Annual Progress Reports
Expected (since FY2004):23
Completed:22
On time:22
Status Reports
Completed:99
On time:57
Avg Days Late:4

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
11573 21982, 26945, 32840, 38238, 42391, 52837, 57048, 61265, 64969, 68701, 72618, 75932, 79145, 82058, 85245, 87866, 90256, 92377, 94706, CR-375383 2002-070-00 EXP LAPWAI CREEK WATERSHED RESTORATION Nez Perce Soil and Water Conservation District (SWCD) 09/01/2002 04/30/2026 Pending 99 498 12 0 6 516 98.84% 1
Project Totals 99 498 12 0 6 516 98.84% 1


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: 2022 Anadromous Fish Habitat & Hatchery Review

Council Recommendation

Assessment Number: 2002-070-00-NPCC-20230310
Project: 2002-070-00 - Lapwai Creek Anadromous Habitat
Review: 2022 Anadromous Fish Habitat & Hatchery Review
Approved Date: 4/15/2022
Recommendation: Implement
Comments: Bonneville and Sponsor to take the review remarks into consideration in project documentation.

[Background: See https://www.nwcouncil.org/2021-2022-anadromous-habitat-and-hatchery-review/]

Independent Scientific Review Panel Assessment

Assessment Number: 2002-070-00-ISRP-20230324
Project: 2002-070-00 - Lapwai Creek Anadromous Habitat
Review: 2022 Anadromous Fish Habitat & Hatchery Review
Completed Date: None
Documentation Links:
Review: 2013 Geographic Category Review

Council Recommendation

Assessment Number: 2002-070-00-NPCC-20131126
Project: 2002-070-00 - Lapwai Creek Anadromous Habitat
Review: 2013 Geographic Category Review
Proposal: GEOREV-2002-070-00
Proposal State: Pending BPA Response
Approved Date: 11/5/2013
Recommendation: Implement with Conditions
Comments: Implement through FY 2018: Sponsor should consider addressing ISRP qualification #2 in future reviews. See Programmatic Issue and Recommendation A for effectiveness monitoring (ISRP qualification #1).
Conditions:
Council Condition #1 ISRP Qualification: Qualification #1—See Programmatic Issue and Recommendation A for effectiveness monitoring (ISRP qualification #1).
Council Condition #2 ISRP Qualification: Qualification #2—Sponsor should consider addressing ISRP qualification #2 in future reviews.
Council Condition #3 Programmatic Issue: A. Implement Monitoring, and Evaluation at a Regional Scale—See Programmatic Issue and Recommendation A for effectiveness monitoring (ISRP qualification #1).

Independent Scientific Review Panel Assessment

Assessment Number: 2002-070-00-ISRP-20130610
Project: 2002-070-00 - Lapwai Creek Anadromous Habitat
Review: 2013 Geographic Category Review
Proposal Number: GEOREV-2002-070-00
Completed Date: 6/11/2013
Final Round ISRP Date: 6/10/2013
Final Round ISRP Rating: Meets Scientific Review Criteria (Qualified)
Final Round ISRP Comment:

1. Purpose: Significance to Regional Programs, Technical Background, and Objectives

This proposal provides excellent technical background information that demonstrates the significance of the project to regional programs. A map with overview of landownership helps describe the physical setting. The descriptive summary of existing habitat and fundamental habitat problems is generally well done. Efforts in Lapwai Creek are conducted jointly by this project on private lands and by project #199001700 on land owned by the Nez Perce Tribe, tribal members, and public lands. Objectives for the two projects are the same and work is based upon the 2009 Lapwai Creek Restoration Strategy, developed by both organizations that delineated the priority stream assessment units in the watershed.

Limiting factors were identified and standards were established for reducing their impacts. Importantly, quantitative deliverables and objectives were presented so reviewers and stakeholders have a good idea of what may be accomplished by this effort.

2. History: Accomplishments, Results, and Adaptive Management (Evaluation of Results)

The proposal provides an excellent, detailed, photographic and quantitative description of accomplishments associated with each objective during the past 10 years or so. Other proposals should take notice, as often other proposals simply provide reference to project reports. This approach makes it easy for reviewers and stakeholders to see that this effort has been successful in past efforts. The description of the prioritization process and the flow charts used are clear and nicely done.

The proposal indicates it will develop a robust adaptive management program that addresses concerns raised by the ISRP with regard to adaptive management in general. This is good, but given that the project has been in operation for many years it is not clear why a robust adaptive management plan has not already been developed. In the adaptive management section, the proposal provides examples of how it has learned from its ongoing activities.

3. Project Relationships, Emerging Limiting Factors, and Tailored Questions

The project has its own monitoring program, and the program discusses linkages to the Nez Perce Tribe's effort, action effectiveness monitoring, and the CHaMP effort that will begin in 2018. It would be good if the sponsor can directly address the issue of whether its proposed monitoring overlaps or duplicates that of other monitoring, and how well the proposed monitoring will contribute to programs that will begin in a few years, that is CHaMP.

The proposal provides a good discussion of several potential emerging limiting factors such as climate change impacts on temperature and flow, nonnative species, predators, and toxic chemicals. The proposal did not fully discuss, based on past experience, whether private landownership constrains implementation of the high priority projects; the sponsors did state that the success of certain objectives is dependent on cooperation by private landowners. This leads to high uncertainty. Past experience, as communicated on the site visit, is that landowners approach the SWCD for assistance during emergencies like the 1996 flood. The ISRP encourages the sponsors to continue their consideration of possible inducements.

4. Deliverables, Work Elements, Metrics, and Methods

Seven deliverables are proposed to support the objectives. They are presented in sufficient detail, with specific design criteria. Excellent benchmarks are provided with the proposed deliverables. Methods are briefly mentioned with each objective.


===========QUALIFICATIONS FOLLOW================

The ISRP has two concerns, both of which can be dealt with in contracting and future reviews:

 

Qualification #1 - Qualification #1
Ensure that ongoing monitoring is consistent with and can be efficiently utilized by monitoring programs that will begin in a few years (CHaMP in 2018),
Qualification #2 - Qualification #2
Further consider the issue of how private landownership inhibits high priority projects and develop additional approaches that encourage private landowners to participate.
First Round ISRP Date: 6/10/2013
First Round ISRP Rating: Meets Scientific Review Criteria (Qualified)
First Round ISRP Comment:

1. Purpose: Significance to Regional Programs, Technical Background, and Objectives

This proposal provides excellent technical background information that demonstrates the significance of the project to regional programs. A map with overview of landownership helps describe the physical setting. The descriptive summary of existing habitat and fundamental habitat problems is generally well done. Efforts in Lapwai Creek are conducted jointly by this project on private lands and by project #199001700 on land owned by the Nez Perce Tribe, tribal members, and public lands. Objectives for the two projects are the same and work is based upon the 2009 Lapwai Creek Restoration Strategy, developed by both organizations that delineated the priority stream assessment units in the watershed.

Limiting factors were identified and standards were established for reducing their impacts. Importantly, quantitative deliverables and objectives were presented so reviewers and stakeholders have a good idea of what may be accomplished by this effort.

2. History: Accomplishments, Results, and Adaptive Management (Evaluation of Results)

The proposal provides an excellent, detailed, photographic and quantitative description of accomplishments associated with each objective during the past 10 years or so. Other proposals should take notice, as often other proposals simply provide reference to project reports. This approach makes it easy for reviewers and stakeholders to see that this effort has been successful in past efforts. The description of the prioritization process and the flow charts used are clear and nicely done.

The proposal indicates it will develop a robust adaptive management program that addresses concerns raised by the ISRP with regard to adaptive management in general. This is good, but given that the project has been in operation for many years it is not clear why a robust adaptive management plan has not already been developed. In the adaptive management section, the proposal provides examples of how it has learned from its ongoing activities.

3. Project Relationships, Emerging Limiting Factors, and Tailored Questions

The project has its own monitoring program, and the program discusses linkages to the Nez Perce Tribe's effort, action effectiveness monitoring, and the CHaMP effort that will begin in 2018. It would be good if the sponsor can directly address the issue of whether its proposed monitoring overlaps or duplicates that of other monitoring, and how well the proposed monitoring will contribute to programs that will begin in a few years, that is CHaMP.

The proposal provides a good discussion of several potential emerging limiting factors such as climate change impacts on temperature and flow, nonnative species, predators, and toxic chemicals. The proposal did not fully discuss, based on past experience, whether private landownership constrains implementation of the high priority projects; the sponsors did state that the success of certain objectives is dependent on cooperation by private landowners. This leads to high uncertainty. Past experience, as communicated on the site visit, is that landowners approach the SWCD for assistance during emergencies like the 1996 flood. The ISRP encourages the sponsors to continue their consideration of possible inducements.

4. Deliverables, Work Elements, Metrics, and Methods

Seven deliverables are proposed to support the objectives. They are presented in sufficient detail, with specific design criteria. Excellent benchmarks are provided with the proposed deliverables. Methods are briefly mentioned with each objective.


===========QUALIFICATIONS FOLLOW================

The ISRP has two concerns, both of which can be dealt with in contracting and future reviews:

 

Modified by Dal Marsters on 6/11/2013 3:48:23 PM.
Documentation Links:
Review: FY07-09 Solicitation Review

Council Recommendation

Assessment Number: 2002-070-00-NPCC-20090924
Project: 2002-070-00 - Lapwai Creek Anadromous Habitat
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments: ISRP fundable in part:? funding in FY 07 for completion of inventory and assessments.

Independent Scientific Review Panel Assessment

Assessment Number: 2002-070-00-ISRP-20060831
Project: 2002-070-00 - Lapwai Creek Anadromous Habitat
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria - In Part
Final Round ISRP Comment:
The ISRP was provided a response to the fix-it loop for proposal 199901700 Protect and Restore Lapwai Creek Watershed (NPT) and 200207000 Lapwai Creek Anadromous Habitat (NPSWCD) - integrated sister projects to address habitat restoration and protection on Lapwai Creek on tribal and private land.

The sponsors addressed the questions raised by the ISRP in the preliminary review. The adequacy of the answers to inform and assist the ISRP in their proposal evaluation varied. The ISRP thanks the sponsors for the time and effort in producing the revised proposal narrative and explanations of the projects' history.

The sponsors indicated that stream habitat and watershed inventories, and a compilation on fish population abundance will be completed soon; final assessments shall be available in 2007. Based on that commitment, these projects are Fundable in Part (incrementally). In 2007, the fundable work includes completion of the inventory and assessments. Following that, work possibly fundable in 2008 and 2009 might be for restoration actions, contingent upon a written plan that uses those assessments to establish biological objectives, strategies and actions, and an approach to measure whether progress is being made in achieving the objectives.

The reporting of results was limited to a reporting of tasks accomplished, i.e., compliance monitoring. When they are developing their prescriptions they should include an evaluation of the biological results of their past actions. What is needed is a specific goal, with a timeframe for changes in habitat conditions and fish population abundance and productivity. Sponsors clarify for the ISRP their understanding of compliance and effectiveness monitoring, and inform the ISRP that they appreciate the necessity of effectiveness monitoring, but state that it is beyond the willingness of Council and BPA to fund those data collections and analysis. The ISRP understands the constraints placed on sponsors, but also believes sponsors need to be creative in developing methods to determine whether their restoration efforts are providing a benefit. Can riparian habitat be evaluated by photo points or aerial photography and be cost effective? How can stream flow and stream temperature be monitored to determine if treatments were effective? How can adult fish in and smolts out be measured? An evaluation plan is expected.

An integrated process of watershed assessment remains incomplete after several years, but they can be credited with developing conservation plans and completion of several small actions. The revised narrative for the proposed work was a much better presentation than the original, and may have been acceptable if originally submitted in this manner. It also outlined the acceptable qualifications of the proponents.

This work in Lapwai Creek is supportable because of the potential for anadromous fish production. The answers to the questions and the narrative revision go a long way to clarifying for the ISRP the status and progress of anadromous fish species (primarily steelhead) and restoration potential in this watershed. The ISRP had many questions for the sponsors, so the detailed evaluation of the response to each is beyond the space and time available in this fix it loop review.
Documentation Links:

Legal Assessment (In-Lieu)

Assessment Number: 2002-070-00-INLIEU-20090521
Project Number: 2002-070-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: Problems May Exist
Cost Share Rating: 2 - May be reasonable
Comment: Inventory, planning, and multiple restoration activities (weed control, LWD, erosion control measures, CAFO measures et); other entities authorized/required to perform some: need confirmation or criteria or other screening that BPA not funding activities already required of another entity; also need confirmation that cost share is adequate.

Capital Assessment

Assessment Number: 2002-070-00-CAPITAL-20090618
Project Number: 2002-070-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Project Relationships: None