Milestones Summary

Contract 28739: 1991-073-00 NATURAL PRODUCTION M&E
Viewing 56 of 56 Milestones
Sort Order
WE ID
Work Element Name
Title
Description
Sort
Type
Title
Start
End
Status
Modified By
Modified Date
A165Produce Environmental Compliance DocumentationProject PermittingApply for all necessary ESA permitsA ESA permit 210/01/200611/01/2006ConcludedTim Copeland03/16/2006 9:12 AM
A165Produce Environmental Compliance DocumentationProject PermittingApply for all necessary ESA permitsBDELIVPermitting Complete 11/01/2006ConcludedJody White (Inactive)06/08/2006 7:43 AM
B119Manage and Administer ProjectsAnnual Project Planning & AdministrationProject management and planning activitiesA Complete contract funding package & submit to BPA10/01/200610/30/2006ConcludedJody White (Inactive)06/19/2006 10:22 AM
B119Manage and Administer ProjectsAnnual Project Planning & AdministrationProject management and planning activitiesB Internal project coordination & operational planning meetings01/01/200701/31/2007ConcludedJody White (Inactive)06/19/2006 10:22 AM
B119Manage and Administer ProjectsAnnual Project Planning & AdministrationProject management and planning activitiesC Attend any mandatory NPCC/CBFWA/BPA meetings07/01/200601/31/2007ConcludedJody White (Inactive)06/19/2006 10:22 AM
B119Manage and Administer ProjectsAnnual Project Planning & AdministrationProject management and planning activitiesDFPCIRFunding Package - Conduct internal review (e.g., Supervisor or Interagency)09/01/200609/29/2006ConcludedJody White (Inactive)06/19/2006 10:22 AM
B119Manage and Administer ProjectsAnnual Project Planning & AdministrationProject management and planning activitiesEASJEBAccrual - Submit January estimate to BPA01/01/200701/10/2007ConcludedJody White (Inactive)06/19/2006 10:22 AM
B119Manage and Administer ProjectsAnnual Project Planning & AdministrationProject management and planning activitiesFASSEBAccrual - Submit September estimate to BPA09/01/200609/10/2006ConcludedTim Copeland03/14/2006 3:14 PM
B119Manage and Administer ProjectsAnnual Project Planning & AdministrationProject management and planning activitiesGDELIVPlanning & Administration Complete 01/31/2007ConcludedJody White (Inactive)06/19/2006 10:22 AM
C132Produce Progress (Annual) ReportAnnual Progress Report (FY 2005)Finish editing and submittal of the FY 2005 annual report reporting all results, analyses, and recommendations from FY 2005 activities.A Submit FY2005 annual report for internal IDFG approval07/03/200607/31/2006ConcludedTim Copeland03/14/2006 3:18 PM
C132Produce Progress (Annual) ReportAnnual Progress Report (FY 2005)Finish editing and submittal of the FY 2005 annual report reporting all results, analyses, and recommendations from FY 2005 activities.B Draft final version of FY2005 annual report09/01/200609/29/2006ConcludedTim Copeland03/14/2006 3:19 PM
C132Produce Progress (Annual) ReportAnnual Progress Report (FY 2005)Finish editing and submittal of the FY 2005 annual report reporting all results, analyses, and recommendations from FY 2005 activities.C Upload FY2005 report to BPA website10/02/200610/16/2006ConcludedTim Copeland03/14/2006 3:20 PM
C132Produce Progress (Annual) ReportAnnual Progress Report (FY 2005)Finish editing and submittal of the FY 2005 annual report reporting all results, analyses, and recommendations from FY 2005 activities.DDELIVAnnual Report Complete 10/16/2006ConcludedTim Copeland04/04/2006 2:30 PM
D185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.ASRJul-Sep 2006 (7/1/2006 - 9/30/2006)10/01/200610/15/2006ConcludedRoy Beaty (Inactive)04/03/2006 9:24 AM
D185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.BSROct-Dec 2006 (10/1/2006 - 12/31/2006)01/01/200701/15/2007ConcludedRoy Beaty (Inactive)04/03/2006 9:24 AM
D185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.CSRFinal Jan 2007 (1/1/2007 - 1/31/2007)01/17/200701/31/2007ConcludedRoy Beaty (Inactive)06/20/2006 10:25 AM
E132Produce Progress (Annual) ReportAnnual Progress Report (FY 2006)Start production of FY 2006 annual progress report, incorporating all results, analyses, and recommendations from FY 2006 activities. This report will also incorporate an extensive review of the past five years of work and provide an assessment of each funded objective and the future direction for the study of natural production of Chinook salmon in Idaho.A Assemble results of analyses from FY200601/29/200701/31/2007ConcludedJody White (Inactive)06/19/2006 10:42 AM