Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program

Milestones Summary

Contract 36039: 2002-050-00 EXP ACCD COUSE-TENMILE HABITAT RESTORATION
Viewing 44 of 44 Milestones
Sort Order
WE ID
Work Element Name
Title
Description
Sort
Type
Title
Start
End
Status
Modified By
Modified Date
A119Manage and Administer ProjectsProject administrationManage on the ground efforts and administrative work in support of BPA's programmatic requirements. Solicit media coverage for project work on Couse and Tenmile Creeks and other ESA listed streams in Asotin County. Activities will include coverage of District, participating agencies, local schools, and cooperator activities that protect and enhance resources while restoring habitat.AASSEBAccrual - Submit September estimate to BPA09/01/200809/20/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
A119Manage and Administer ProjectsProject administrationManage on the ground efforts and administrative work in support of BPA's programmatic requirements. Solicit media coverage for project work on Couse and Tenmile Creeks and other ESA listed streams in Asotin County. Activities will include coverage of District, participating agencies, local schools, and cooperator activities that protect and enhance resources while restoring habitat.B 2009 SOW, budget, & property inventory sent to COTR06/01/200810/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
A119Manage and Administer ProjectsProject administrationManage on the ground efforts and administrative work in support of BPA's programmatic requirements. Solicit media coverage for project work on Couse and Tenmile Creeks and other ESA listed streams in Asotin County. Activities will include coverage of District, participating agencies, local schools, and cooperator activities that protect and enhance resources while restoring habitat.CDELIVProject operating smoothly 12/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
B114Identify and Select ProjectsDirect planning & implementation of habitat enhancement projectsDirect and coordinate the planning and implementation of fish habitat enhancement, restoration, and maintenance (conversion to direct seed agriculture, riparian planting and fencing, grazing BMPs, CREP) in Couse and Tenmile Creeks area and other ESA listed streams in Asotin County. ACCD will coordinate with landowners to identify and establish habitat enhancement projects.A Landowner coordination for Habitat Enhancement Projects01/01/200812/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
B114Identify and Select ProjectsDirect planning & implementation of habitat enhancement projectsDirect and coordinate the planning and implementation of fish habitat enhancement, restoration, and maintenance (conversion to direct seed agriculture, riparian planting and fencing, grazing BMPs, CREP) in Couse and Tenmile Creeks area and other ESA listed streams in Asotin County. ACCD will coordinate with landowners to identify and establish habitat enhancement projects.BDELIVLandowner coordination for Habitat Enhancement Projects 12/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
C185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report quarterly on the status of milestones and deliverables in Pisces. When indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.ASRJan-Mar 2008 (1/1/2008 - 3/31/2008)04/01/200804/15/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
C185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report quarterly on the status of milestones and deliverables in Pisces. When indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.BSRApr-Jun 2008 (4/1/2008 - 6/30/2008)07/01/200807/15/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
C185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report quarterly on the status of milestones and deliverables in Pisces. When indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.CSRJul-Sep 2008 (7/1/2008 - 9/30/2008)10/01/200810/15/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
C185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report quarterly on the status of milestones and deliverables in Pisces. When indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.DSRFinal Oct-Dec 2008 (10/1/2008 - 12/31/2008)12/17/200812/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
D132Produce Progress (Annual) ReportAnnual ReportUtilize data base and project photos to accurately capture project scope and deliverables with a final report showing before and after pictures.A Draft FY 2007 annual report provided to COTR for review01/01/200811/30/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
D132Produce Progress (Annual) ReportAnnual ReportUtilize data base and project photos to accurately capture project scope and deliverables with a final report showing before and after pictures.BDELIVFinal FY 2007 Annual Report provided to COTR for posting 12/20/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
E165Produce Environmental Compliance DocumentationObtain environmental compliance for upland and riparian projectsCoordinate with BPA Environmental Specialist (KEC) to fulfill NEPA, ESA, cultural resources, and other environmental compliance requirements.A Obtain sign-off from BPA's EC Group that EC requirements are complete for 200801/01/200812/20/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
E165Produce Environmental Compliance DocumentationObtain environmental compliance for upland and riparian projectsCoordinate with BPA Environmental Specialist (KEC) to fulfill NEPA, ESA, cultural resources, and other environmental compliance requirements.B Obtain/renew applicable local, state, federal, and tribal permits as needed01/01/200812/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
E165Produce Environmental Compliance DocumentationObtain environmental compliance for upland and riparian projectsCoordinate with BPA Environmental Specialist (KEC) to fulfill NEPA, ESA, cultural resources, and other environmental compliance requirements.C Contact BPA's EC Group to determine what will be needed for 200910/01/200812/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
E165Produce Environmental Compliance DocumentationObtain environmental compliance for upland and riparian projectsCoordinate with BPA Environmental Specialist (KEC) to fulfill NEPA, ESA, cultural resources, and other environmental compliance requirements.DDELIVAll environmental clearances & permits obtained before work begins 12/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
F157Collect/Generate/Validate Field and Lab DataData and Photos for ReportingPhotos will be taken of selected individual practices at the same photo points on most projects before, during, and after project completion. Project information is entered into internal database for non-CREP activities in Asotin County. CREP has it's own database required by the State of Washington. Database includes information for funding sources, regulatory agencies and interested citizens on what has been accomplished with habitat restoration and protection funding.AECEnvironmental compliance requirements complete01/01/200801/01/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM
F157Collect/Generate/Validate Field and Lab DataData and Photos for ReportingPhotos will be taken of selected individual practices at the same photo points on most projects before, during, and after project completion. Project information is entered into internal database for non-CREP activities in Asotin County. CREP has it's own database required by the State of Washington. Database includes information for funding sources, regulatory agencies and interested citizens on what has been accomplished with habitat restoration and protection funding.B Take photos of practices implemented, before--during--after01/01/200812/31/2008ConcludedSarah Branum (Inactive)09/24/2008 1:25 PM