SOW Report
Contract 58747: 2009-026-00 CAP MILL CREEK REACH 6 IMPROVEMENTS
Project Number:
Title:
Umatilla Tribe Ceded Area Juvenile & Adult Fish Passage Improvement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
58747
Contract Title:
2009-026-00 CAP MILL CREEK REACH 6 IMPROVEMENTS
Contract Continuation:
Previous: Next:
51522: 2009-026-00 CAP MILL CREEK PASSAGE IMPROVEMENTS
  • 65899: 2009-026-00 CAP WALLA WALLA JUVENILE AND ADULT
Contract Status:
Closed
Contract Description:
This project will improve fish passage in a concrete lined section of Mill Creek in Walla Walla. The contract provides the 15% match required for a SRFB grant funding this project.
Account Type(s):
Capital
Contract Start Date:
10/01/2012
Contract End Date:
12/31/2013
Current Contract Value:
$75,500
Expenditures:
$75,500

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarker
5 m
10 ft
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Dawn Boorse Bonneville Power Administration Yes Env. Compliance Lead drboorse@bpa.gov (503) 230-5678
Brian Burns Tri-State Steelheaders Yes Contract Manager brian.burns@tristatesteelheaders.com (509) 529-3543
Gary James Umatilla Confederated Tribes (CTUIR) No Supervisor garyjames@ctuir.org (541) 429-7285
Jason Sweet Bonneville Power Administration Yes F&W Approver jcsweet@bpa.gov (503) 230-3349
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Jed Volkman Umatilla Confederated Tribes (CTUIR) No Interested Party jedvolkman@ctuir.org (541) 429-7539
Tracey Yerxa Bonneville Power Administration Yes COR tyerxa@bpa.gov (503) 230-4738


Viewing 6 of 6 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A107901185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$00.00%01/01/201312/31/2013
B106698165Produce Environmental Compliance DocumentationEnvironmental ComplianceCovers any work by the Contractor to investigate, gather, acquire, or prepare data and documents in support of obtaining environmental clearances for BPA. Work may include providing maps, drafting a biological assessment, obtaining permits, monitoring and reporting required by permits, conducting public involvement activities, completing a cultural resource survey and report, inspecting water craft, vehicles, and heavy equipment for invasive species, implementing best management practices for lamprey, etc. Contractors are required to comply with all applicable federal, state, and local laws, including those that restrict the transport of invasive species. In all cases, environmental compliance work done by the Contractor must be separated from all other work. It is not permitted to combine environmental compliance activities with any other work element.$00.00%10/01/201205/01/2013
C106700119Manage and Administer ProjectsProject AdminCovers the administrative and technical work by the contractor to fulfill BPA's programmatic and contractual requirements such as financial reporting (accruals), and development of an SOW package (includes SOW, budget, property inventory).$00.00%10/01/201212/31/2013
D106701175Produce DesignPlans & SpecsProduce and review plans and specifications$25,00033.11%10/01/201207/15/2013
E106703184Install Fish Passage StructureInstall fish passage improvementsModification of existing concrete channel to improve fish passage at high and low flow. Low flow modification will be the removal of existing baffles in the center trench, spaced at 60 feet and alternating from side to side. New baffles will be placed at 20 foot spacing, and all be on one side. The new baffle configuration eliminates supercritical flow by backwatering each baffle. The high flow modification will be to cut existing slab concrete adjacent to the center trench, adjusting the underlying grade, and placing new pre-cast 'roughness panels.' The roughness panels simulate the roughness of a natural channel, providing a zone of lower velocity where fish can swim at sustainable speeds during higher flows. Resting pools will be cut into the side of the center channel, and be interspersed with the roughness panels. The pools will provide a no-velocity resting area, especially during high flow.$50,50066.89%10/01/201209/30/2013
F108035132Produce Progress (Annual) ReportSubmit Progress Report for the period (10 2012) to (12 2013)The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole. Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments. If producing a technical report for this contract, a discrete experiment, or a peer-reviewed publication, use work element 183: Produce Journal Article.$00.00% 12/01/2013
      
$75,500
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Documentation B: 165. Environmental Compliance 05/01/2013 07/01/2013
Fulfill all administrative tasks with quality products and in a timely manner. C: 119. Project Admin 12/31/2013 12/16/2013
Plans & specs D: 175. Plans & Specs 05/01/2013 06/26/2013
Install fish passage improvements E: 184. Install fish passage improvements 09/30/2013 09/20/2013
Attach Progress Report in Pisces F: 132. Submit Progress Report for the period (10 2012) to (12 2013) 12/01/2013 12/16/2013

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2012
B 165 Environmental Compliance 10/01/2012
C 119 Project Admin 10/01/2012
D 175 Plans & Specs 10/01/2012
E 184 Install fish passage improvements 10/01/2012
F 132 Submit Progress Report for the period (10 2012) to (12 2013) 10/01/2012