SOW Report
Contract 63791: 2012-015-00 EXP WALLOOSKEE YOUNGS 408 PERMIT-FY14
Project Number:
Title:
Cowlitz Indian Tribe Estuary Restoration Program
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Cowlitz 100.00%
Contract Number:
63791
Contract Title:
2012-015-00 EXP WALLOOSKEE YOUNGS 408 PERMIT-FY14
Contract Continuation:
Previous: Next:
59092: 2012-015-00 EXP COWLITZ INDIAN TRIBE ESTUARY R
Contract Status:
Closed
Contract Description:
The Northwest Power Act directs the Northwest Power and Conservation Council (NPCC) and Bonneville Power Administration (BPA) to consult with the region’s appropriate Indian Tribes in the development and implementation of the Fish and Wildlife Program.  The Power Act also calls for fish and wildlife management coordination to assist protection, mitigation, and enhancement of fish and wildlife resources in the Columbia River Basin.  The Cowlitz Indian Tribe is a federally recognized Indian tribe whose area of influence extends from the crest of the Cascade Mountains and Celilo Falls to Pacific County in Washington and Clatsop County in Oregon.  The northern area of influence extends to Thurston County in Washington and is bounded on the south inside Columbia, Washington, Multnomah, and Hood River Counties in Oregon.  Many culturally important landscapes and species to the Cowlitz People within its areas of influenc... e are affected by the operations of the Federal Columbia River Power System (FCRPS).  The development of the FCRPS has adversely affected wildlife, resident fish, and anadromous fish resources along the entirety of the ancestral Cowlitz landscape including, but not limited to:  The Lewis River and its tributaries, the Cowlitz River and its tributaries, the Kalama River and its tributaries, as well as the Columbia River Estuary from Bonneville Dam to the Plume.

The goal of this project is to acquire and restore lands that support the habitats of culturally relevant native fish, wildlife and plant species in the Columbia River estuary (CRE) for the purpose of ecosystem restoration and cultural continuity. The purpose is to increase the quantity and improve the quality of degraded aquatic and floodplain habitats within the Lower Columbia River mainstem and tidally influenced reaches of tributaries in both OR and WA from Bonneville Dam at RM 146 to the plume of the Columbia River, all located within the Cowlitz Tribe's Historical Area of Interest. The Cowlitz Indian Tribe works with the NPCC, BPA and her partners to identify, develop and implement salmonid habitat restoration projects on the Lower Columbia River from Bonneville Dam to the Plume of the Columbia River, all located within the Cowlitz Tribe's Historical Area of Interest. This project will allow the Cowlitz Indian Tribe to identify, develop, and implement habitat restoration activities throughout the lower Columbia River by funding activities which assess the feasibility of acquisition, implementation and management actions all necessary to successfully implement BPA's obligations under the 2008 BiOp.

One of these projects identified and developed through the Estuary process is a 232 acre floodplain project which occurs at the confluence of the Wallooskee River and Youngs Bay near Astoria Oregon.

The Wallooskee-Youngs Confluence restoration project is sponsored by the Cowlitz Indian Tribe. The site has been purchased by Astoria Wetlands, LLC which will fund the site’s restoration design, permitting, and construction; the land’s title will be conveyed to the Tribe. The Tribe will provide perpetual stewardship of the site, manage the area, and provide access to the site for the Cowlitz and other Tribes’ cultural activities.

The project will restore tidal processes, a functioning tidal marsh system, and fish access to the historically estuarine portion of the site: 164.50 acres of isolated floodplain habitat. This site is characterized by an extensive dike along the perimeter that isolates the area and prevents daily tidal interaction with historical floodplain habitat that is now drained pasture land. The dike, which is privately owned and operated, is poorly constructed of unconsolidated materials and is eroding in extensive areas. Breaching the dike and further weakening it in selected areas will immediately restore tidal hydrology and, through time, promote more connectivity with the bay as the dike continues to erode.

What this contract sets out to perform is to facilitate, develop and come into compliance with the US Army Corps of Engineers (USACE) authority to modify (in this case breach in several locations) a levee under the authority of USACE. This process is known as Section 408 Compliance. Section 408 is an intensive process that requires several steps and independent review to ensure that infrastructure and human safety drive the design process of any modifications to USACE authorized levees. This project will fund the design steps, review, coordination and technical assessments necessary to bring the Wallooskee-Youngs Confluence Project into compliance with USACE Section 408 rules.
  
Account Type(s):
Expense
Contract Start Date:
02/01/2014
Contract End Date:
01/31/2015
Current Contract Value:
$86,419
Expenditures:
$86,419

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
30 km
20 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Taylor Aalvik Cowlitz Indian Tribe No Supervisor taylor.a@cowlitz.org (360) 575-3306
Rossana Callejas Bonneville Power Administration No Interested Party rxcallejas@bpa.gov (503) 230-7558
Jason Karnezis Bonneville Power Administration Yes COR jpkarnezis@bpa.gov (503) 230-3098
Rudy Salakory Cowlitz Indian Tribe Yes Contract Manager rsalakory@cowlitz.org (360) 947-2242
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Jesse Wilson Bonneville Power Administration Yes Env. Compliance Lead jcwilson@bpa.gov (503) 230-4506


Viewing 4 of 4 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A126534165Produce Environmental Compliance DocumentationUS Army CoE 408 Compliance ProcessCowlitz Indian Tribe will complete all of the necessary tasks involved with US Army Corps of Engineers 408 compliance needs on the Young's Bay/Walooski River Confluence Project. This includes: 1) Initiating and maintaining USACoE coordination, 2)Real Estate/Geotech/Structural analysis, 3)Hydraulic and hydrology evaluation, 4)Safety Assurance Review Plan (starting the IEPR process), 5) 60% Level Design IEPR/USACoE Review and Response, 6) 80% Level Design IEPR/USACoE Review and Response, 7) 90% Level Design IEPR/USACoE Review and Response, 8) IEPR Review Report, and finally 9) the 100% Level design delivery and USACoE 408 approval.$104,03798.15%02/01/201401/31/2015
B126535119Manage and Administer ProjectsManage and Administer ProjectAdministrative tasks to ensure delivery of contract deliverables. This task includes execution of current contract and scoping of following annual contracts.$6540.62%09/01/201401/31/2015
C126536132Produce Progress (Annual) ReportSubmit Progress Report for the period (June 2011) to (December 2012)The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole. Date range June 2011 - Dec. 2012 will be agreed upon by the COTR and the contractor. This may or may not coincide with the contract period. For an ongoing project, a progress report covering a contract period may be submitted under the subsequent contract, if approved by the COTR. Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments. If producing a manuscript for a peer-reviewed publication, use work element 183: Produce Journal Article.$6540.62%02/01/201404/01/2014
D126502185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$6550.62%07/01/201401/31/2015
      
$106,000
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Completion of the United States Army Corps of Engineers 408 Compliance Process A: 165. US Army CoE 408 Compliance Process 01/31/2015 07/01/2014
All administrative tasks fulfilled with timely quality products B: 119. Manage and Administer Project 01/31/2015 09/30/2014
Attach Progress Report in Pisces C: 132. Submit Progress Report for the period (June 2011) to (December 2012) 02/15/2014 04/14/2014

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 US Army CoE 408 Compliance Process 02/01/2014
B 119 Manage and Administer Project 02/01/2014
C 132 Submit Progress Report for the period (June 2011) to (December 2012) 02/01/2014
D 185 Periodic Status Reports for BPA 02/01/2014