Province | Subbasin | % |
---|---|---|
Columbia Plateau | Umatilla | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Mar-2025.
A | 165308 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR. | $1,025 | 0.20% | 07/01/2017 | 02/28/2018 |
B | 165309 | 186 | Operate and Maintain Habitat/Passage/Structure | Stanfield Diversion Site O&M | Operation and Maintenance of Fish Screens and Related Equipment at Stanfield Diversion Site | $42,000 | 8.05% | 03/01/2017 | 02/28/2018 |
C | 165310 | 186 | Operate and Maintain Habitat/Passage/Structure | Stanfield Ladder O&M | Operation and Maintenance of Stanfield Ladder | $22,550 | 4.32% | 03/01/2017 | 02/28/2018 |
D | 165311 | 186 | Operate and Maintain Habitat/Passage/Structure | Feed Canal Diversion Site O&M | Operation and Maintenance of Fish Screens and Related Equipment at Feed Canal Diversion Site | $42,000 | 8.05% | 03/01/2017 | 02/28/2018 |
E | 165312 | 186 | Operate and Maintain Habitat/Passage/Structure | Feed Canal Ladder O&M | Operation and Maintenance of Fish Screens and Related Equipment at Feed Canal Diversion Site | $36,900 | 7.07% | 03/01/2017 | 02/28/2018 |
F | 165313 | 186 | Operate and Maintain Habitat/Passage/Structure | Westland Fish Screens and Diversion O&M | Operation and Maintenance of Fish Screens and Related Equipment at Westland Diversion Site | $54,000 | 10.35% | 03/01/2017 | 02/28/2018 |
G | 165314 | 61 | Maintain Artificial Production Facility/Infrastructure | Westland Juvenile Sampling Facility O&M | Operation and Maintenance of Juvenile Sampling Facility at Westland Site | $12,800 | 2.45% | 03/01/2017 | 02/28/2018 |
H | 165315 | 186 | Operate and Maintain Habitat/Passage/Structure | Westland Ladder and Hydraulic System O&M | Operation and Maintenance of Westland ladder | $62,400 | 11.96% | 03/01/2017 | 02/28/2018 |
I | 165316 | 186 | Operate and Maintain Habitat/Passage/Structure | Maxwell Diversion Site O&M | Operation and Maintenance of Fish Screens and Related Equipment at Maxwell Diversion Site | $35,000 | 6.71% | 03/01/2017 | 02/28/2018 |
J | 165317 | 186 | Operate and Maintain Habitat/Passage/Structure | Three Mile Left Diversion Site O&M | Operation and Maintenance of Fish Screens and Related Equipment at Three Mile Left Diversion Site | $39,000 | 7.47% | 03/01/2017 | 02/28/2018 |
K | 165318 | 61 | Maintain Artificial Production Facility/Infrastructure | Three Mile Right Spawning Facility O&M | Operation and Maintenance of Spawning Facility and Related Equipment at Three Mile Site. | $9,500 | 1.82% | 03/01/2017 | 02/28/2018 |
L | 165319 | 61 | Maintain Artificial Production Facility/Infrastructure | Fish By-Pass and Sampling Area at WEID Diversion O&M | Operation and Maintenance of Fish By-Pass and Sampling Area at WEID (West Extension Irrigation District) Diversion | $6,500 | 1.25% | 03/01/2017 | 02/28/2018 |
M | 165320 | 186 | Operate and Maintain Habitat/Passage/Structure | Three Mile Right Ladder and Trap O&M | Operation and Maintenance of Fish Ladder and Trap Facility at Three Mile Right | $120,000 | 22.99% | 03/01/2017 | 02/28/2018 |
N | 165321 | 61 | Maintain Artificial Production Facility/Infrastructure | Thornhollow Acclimation Site O&M | Operation and Maintenance of Equipment Related to Thornhollow Acclimation Site | $3,500 | 0.67% | 03/01/2017 | 02/28/2018 |
O | 165322 | 61 | Maintain Artificial Production Facility/Infrastructure | Pendleton Acclimation Site O&M | Operation and Maintenance of Equipment Related to Pendleton Acclimation Site | $1,000 | 0.19% | 03/01/2017 | 02/28/2018 |
P | 165323 | 61 | Maintain Artificial Production Facility/Infrastructure | Imeques Acclimation Site O&M | Operation and Maintenance of Equipment Related to Imeques Acclimation Site | $2,200 | 0.42% | 03/01/2017 | 02/28/2018 |
Q | 165324 | 61 | Maintain Artificial Production Facility/Infrastructure | Minthorn Acclimation Site O&M | Operation and Maintenance of Equipment Related to Minthorn Trapping Site | $3,000 | 0.57% | 03/01/2017 | 02/28/2018 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
O&M at Stanfield Diversion Site complete | B: 186. Stanfield Diversion Site O&M | 02/28/2018 | 02/28/2018 | |
O&M at Stanfield Ladder complete | C: 186. Stanfield Ladder O&M | 02/28/2018 | 02/28/2018 | |
O&M at Feed Canal Diversion Site complete | D: 186. Feed Canal Diversion Site O&M | 02/28/2018 | 02/28/2018 | |
O&M at Feed Canal Ladder complete | E: 186. Feed Canal Ladder O&M | 02/28/2018 | 02/28/2018 | |
O&M at Westland Fish Screens and Diversion complete | F: 186. Westland Fish Screens and Diversion O&M | 02/28/2018 | 02/28/2018 | |
O&M at Westland Juvenile Sampling Facility complete | G: 61. Westland Juvenile Sampling Facility O&M | 02/28/2018 | 02/28/2018 | |
O&M complete for Westland Ladder and Hydraulic System for Gate Operation | H: 186. Westland Ladder and Hydraulic System O&M | 02/28/2018 | 02/28/2018 | |
O&M at Maxwell Diversion Site complete | I: 186. Maxwell Diversion Site O&M | 02/28/2018 | 02/28/2018 | |
O&M at Three Mile Left Diversion Site complete | J: 186. Three Mile Left Diversion Site O&M | 02/28/2018 | 02/28/2018 | |
O&M at Three Mile Site Spawning Facility complete | K: 61. Three Mile Right Spawning Facility O&M | 02/28/2018 | 02/28/2018 | |
O&M at WEID Diversion Fish By-Pass and Sampling Area complete | L: 61. Fish By-Pass and Sampling Area at WEID Diversion O&M | 02/28/2018 | 02/28/2018 | |
O&M at Three Mile Right Ladder and Trap complete | M: 186. Three Mile Right Ladder and Trap O&M | 02/28/2018 | 02/28/2018 | |
O&M at Thornhollow Acclimation Site complete | N: 61. Thornhollow Acclimation Site O&M | 02/28/2018 | 02/28/2018 | |
O&M at Pendleton Acclimation Site complete | O: 61. Pendleton Acclimation Site O&M | 02/28/2018 | 02/28/2018 | |
O&M at Imeques Acclimation Site complete | P: 61. Imeques Acclimation Site O&M | 02/28/2018 | 02/28/2018 | |
O&M at Minthorn Trapping Site complete | Q: 61. Minthorn Acclimation Site O&M | 02/28/2018 | 02/28/2018 | |
O&M at South Fork of Walla Walla Spawning Site complete | R: 61. South Fork of Walla Walla Spawning Site O&M | 02/28/2018 | 02/28/2018 | |
All project work complies with environmental regulations | S: 165. Ensure project has environmental clearance from BPA | 02/28/2018 | 02/28/2018 | |
Final Annual Report for work conducted during FY16 contract period | T: 132. Prepare annual report FY16 (March 1, 2016 thru Feb 28, 2017) | 08/01/2017 | 09/18/2017 | |
All administrative tasks fulfilled with timely quality products | U: 119. Manage and administer project | 02/28/2018 | 02/28/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Coho (O. kisutch) - Unspecified Population |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 03/01/2017 | ||||||
B | 186 | Stanfield Diversion Site O&M | 03/23/2017 | ||||||
C | 186 | Stanfield Ladder O&M | 03/23/2017 | ||||||
D | 186 | Feed Canal Diversion Site O&M | 03/23/2017 | ||||||
E | 186 | Feed Canal Ladder O&M | 03/23/2017 | ||||||
F | 186 | Westland Fish Screens and Diversion O&M | 03/23/2017 | ||||||
G | 61 | Westland Juvenile Sampling Facility O&M | 03/23/2017 | ||||||
H | 186 | Westland Ladder and Hydraulic System O&M | 03/23/2017 | ||||||
I | 186 | Maxwell Diversion Site O&M | 03/23/2017 | ||||||
J | 186 | Three Mile Left Diversion Site O&M | 03/27/2017 | ||||||
K | 61 | Three Mile Right Spawning Facility O&M | 03/27/2017 | ||||||
L | 61 | Fish By-Pass and Sampling Area at WEID Diversion O&M | 03/27/2017 | ||||||
M | 186 | Three Mile Right Ladder and Trap O&M | 03/27/2017 | ||||||
N | 61 | Thornhollow Acclimation Site O&M | 03/27/2017 | ||||||
O | 61 | Pendleton Acclimation Site O&M | 03/27/2017 | ||||||
P | 61 | Imeques Acclimation Site O&M | 03/27/2017 | ||||||
Q | 61 | Minthorn Acclimation Site O&M | 03/27/2017 | ||||||
R | 61 | South Fork of Walla Walla Spawning Site O&M | 03/27/2017 | ||||||
S | 165 | Ensure project has environmental clearance from BPA | 03/01/2017 | ||||||
T | 132 | Prepare annual report FY16 (March 1, 2016 thru Feb 28, 2017) | 03/01/2017 | ||||||
U | 119 | Manage and administer project | 03/01/2017 |