Effective implementation management and timely contract administration |
A: 119. Manage and Administer Project |
|
02/29/2020 |
02/29/2020 |
Complete all required EC and obtain permits prior to implementation of project |
B: 165. Produce Environmental Compliance Documentation |
|
02/29/2020 |
02/29/2020 |
Completed Annual Report |
D: 132. Submit Progress Report for the period (Mar 2018) to (Feb 2019) |
|
07/26/2019 |
09/26/2019 |
3-phase power installed and irrigation equipment purchased |
E: 203. Lemhi SWCD: Bohannon Creek, Wellard Irrigation |
|
02/29/2020 |
02/17/2020 |
Fence Installation Complete |
F: 40. Lemhi SWCD: Hayden Creek Fence |
|
02/29/2020 |
02/26/2020 |
Effective implementation management and timely contract administration |
G: 119. Lemhi SWCD: Project Implementation: Provide Project Implementation Support |
|
02/29/2020 |
02/29/2020 |
Participate in local planning meetings |
H: 191. Lemhi SWCD: Project Implementation: Participate in local planning meetings as needed |
|
02/29/2020 |
02/29/2020 |
Rehabilitate project sites through hydroseeding, plant or seed purchase, and planting |
I: 47. Lemhi SWCD: Lemhi Vegetation Management: Rehabilitate Project Sites |
|
02/29/2020 |
11/29/2019 |
Vegetation maintenance activities complete |
J: 198. Lemhi SWCD: Lemhi Vegetation: ongoing treatment |
|
02/29/2020 |
11/29/2019 |
Vegetation managed through noxious weed herbicide treatments |
K: 199. Lemhi SWCD: Lemhi Vegetation: initial treatment |
|
02/29/2020 |
11/29/2019 |
LESA purchased and installed |
L: 203. Lemhi SWCD: Hawley Pivot Irrigation Improvement |
|
02/29/2020 |
10/18/2019 |
Bridge and timber mats purchased and delivered |
M: 55. Lemhi SWCD: Project Implementation Temporary Crossing Structures |
|
02/29/2020 |
10/18/2019 |
Irrigation system installed on Pratt Creek |
N: 203. Lemhi SWCD: Lower Pratt Irrigation Project (Hedt) |
|
08/30/2019 |
06/10/2019 |
Pools and overhanging willows installed to create and promote aquatic complexity |
O: 29. Lemhi SWCD: Middle Eighteenmile Creek Habitat Improvement Project Breshears: instream, bank, and floodplain complexity |
|
02/29/2020 |
10/30/2019 |
New channel constructed on Eighteenmile Creek |
P: 30. Lemhi SWCD: Middle Eighteenmile Creek Habitat Improvement Project Breshears: create channel |
|
02/29/2020 |
08/07/2019 |
Plants and seed purchased and installed |
Q: 47. Lemhi SWCD: Middle Eighteenmile Creek Habitat Improvement Project Breshears:: planting |
|
02/29/2020 |
08/30/2019 |
Effective implementation management and timely contract administration |
R: 119. IDFG: Lemhi Basin Habitat Improvement Manage & Administer |
|
02/29/2020 |
02/29/2020 |
IDFG: Produce 60% design and cost estimate Eagle Valley Subreach 1 |
S: 175. IDFG: Eagle Valley Subreach 1, Produce 60% design and cost estimate |
|
02/29/2020 |
|
IDFG: Produce final design Eagle Valley Subreach 4, Phase 1 and phase 2. |
T: 175. IDFG: Eagle Valley Subreach 4, Produce final design |
|
02/28/2020 |
|
Produce final design for Middle Lemhi River Henry Reach. |
U: 175. IDFG: Middle Lemhi River Henry Reach- Produce design Phase I |
|
02/28/2020 |
|
Final design provided by engineers |
Y: 175. LRLT - LLP Lower Lemhi Project: final design |
|
02/29/2020 |
|
Final design provided by engineers |
Z: 175. LRLT - Upper Big Springs and Pond Outlet Project: final design |
|
02/29/2020 |
|
Design, construction oversight, surveying, and staking provided by engineers |
AA: 175. LRLT - Canyon Creek LLP Project: engineering design, survey, and construction oversight |
|
02/29/2020 |
|
Instream structures installed to create and promote aquatic and floodplain complexity on Canyon Creek |
AB: 29. LRLT - Canyon Creek LLP Project: instream and floodplain complexity |
|
02/29/2020 |
|
Construction Management Complete |
AE: 100. LRLT - Big Springs Lemhi River Confluence Restoration Project, Year 2: engineering oversight |
|
02/29/2020 |
01/30/2020 |
New channel sections, point bars, and islands constructed on Big Springs |
AF: 30. LRLT - Big Springs Lemhi River Confluence Restoration Project, Year 2: create channel |
|
02/29/2020 |
08/31/2019 |
Structures installed to create and promote aquatic and floodplain complexity |
AG: 29. LRLT - Big Springs Lemhi River Confluence Restoration Project, Year 2: instream, bank, and floodplain complexity |
|
02/29/2020 |
08/31/2019 |
Plants, sod mats, and seed purchased and installed |
AH: 47. LRLT - Big Springs Lemhi River Confluence Restoration Project, Year 2: planting |
|
12/31/2019 |
10/31/2019 |
Fence installed |
AI: 40. LRLT - Big Springs Lemhi River Confluence Restoration Project, Year 2: fence |
|
02/29/2020 |
02/29/2020 |
Design, construction oversight, surveying, and staking provided by engineers |
AJ: 175. LRLT- L-63 Diversion Removal and Restoration: final design and construction oversight |
|
02/29/2020 |
08/31/2019 |
Three kiosks installed |
AN: 188. LRLT: Lemhi Kiosks |
|
12/31/2019 |
|
Analyze data |
AO: 162. RMRS: Lemhi Hydrologic Modeling 2019 |
|
02/29/2020 |
|
Collect data and write report |
AP: 157. RMRS: Lemhi Hydrologic Modeling - Data Collection and Report 2019 |
|
02/28/2020 |
|
Draft engineering designs |
AQ: 175. TU: Hayden Creek Channel Restoration (Hermits of Mt Carmel): draft design |
|
02/29/2020 |
02/12/2020 |
Draft engineering designs received for creek restoration on Eighteenmile Creek |
AS: 175. TU: Eighteenmile Creek Channel Restoration (Ellsworth): draft design |
|
02/29/2020 |
|
30% design for Middle Lemhi River, Hayden reach habitat improvement project |
AU: 175. IDFG: Middle Lemhi River - Hayden Reach Conceptual Design |
|
02/29/2020 |
|
Finalize culvert replacement project on Eighteenmile Creek |
AV: 85. IDFG: Eighteenmile Creek Culvert Replacement |
|
02/28/2020 |
|
Relocate decommissioned road and construct berm to prevent erosion of existing road |
AW: 33. LRLT: Big Springs Lemhi River Confluence Restoration Project: relocate ranch road |
|
02/28/2020 |
11/15/2019 |
Harden existing water gap |
AX: 55. LRLT: Big Springs Lemhi River Confluence Restoration Project: stockwater gap |
|
02/28/2020 |
11/15/2019 |