This page shows which work elements use this metric.
Work Element | Work Element Association Status | Description | FY Start | FY End | Guidance ID | Guidance | Required / Optional | Is Activated By Default | Included in PI | Supports PCSRF/PNSHP (Katz) | PNSHP Metric Code | PNSHP Metric |
---|---|---|---|---|---|---|---|---|---|---|---|---|
69. Install Fish Screen | Active | Work to install or replace a fish screen associated with a diversion or pump. Typical screen types include rotary drum, flat plate or traveling. The design of complex or large-scale screens is typically a separate work element. See 175. Produce Design. | 2005 | 64 | Determined by what is stated in the water right or calculated based on flow rate. | Required | Yes | No | Yes | C.1.b | Quantity of water protected by screens | |
ITS Action Category:
Entrainment Screening
ITS Metric:
Quantity of flow protected by screening
|
||||||||||||
208. Irrigation Infrastructure Construction or Replacement | Expired | All actions related to the construction and installation of irrigation infrastructure for the purpose of fish and wildlife conservation. Includes fish screens (and related infrastructure such as concrete, gantries, solar panels, bypass pipe, etc.), headgates, flow measuring devices, irrigation diversions, siphons, wells, piping, pumps, and fish passage structures associated with irrigation diversions. The design of complex or large-scale screens is typically a separate work element. See 175. Produce Design. In known or potential lamprey habitat use guidance from these documents: Guidelines to Minimize Impacts and Maximize Benefits for Native Lamprey During In-water Work https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm Pacific Lamprey Habitat Restoration Guide https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm. Lamprey presence can be determined from Data Basin map https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm. This map does not show all distribution due to limited data. Pre-project lamprey surveys should be done (see USFWS lamprey Guidelines document) if the map does not show presence. |
2021 | 2021 | 64 | Determined by what is stated in the water right or calculated based on flow rate. | Optional | No | Yes | No | ||
ITS Action Category:
Flow Enhancement/Protection
ITS Metric:
Amount of water acquired/protected
|
Yes
PNSHP Metric Association | Work Element |
---|---|
C.0 Salmonid Habitat Restoration and Acquisition C.1 Fish Screening Project C.1.b Quantity of water protected by screens |
69. Install Fish Screen |