Work Element 35: Develop Pond - Published
WE Name:
35. Develop Pond (Develop Pond)
Work Category:
Habitat - Habitat Improvement
WE Agreement Type:
Contracted
Status:
Active
Definition:
Develop a pond and its surrounding habitat for resident fish and/or waterfowl. May involve the installation of a water control structure or excavation. Does not apply to sediment control ponds (55. Erosion and Sedimentation Control), acclimation ponds (171. Build, Modify, and/or Refurbish Artificial Production Facility), or wetlands (181. Create, Restore, and/or Enhance Wetland).
WSE Description Template:
Effective Dates:
FY2005 to <no end date>
Work Phase:
construction/implementation
Sort Sequence:
5.06
Focal Species Required:
Yes
RM&E Metadata Required:
No
Finite or Recurring:
Finite
Is BPA Internal:
No
Is Contracted:
Yes
Is Cost Share:
No
Is Construction:
Yes


Deliverable Status:
Required
Default Deliverable Desc:
Pond
Potential Deliverables:
  • Pond construction completed at the specified area

  • Rule 1 (Environmental Compliance): Any associated ESA, cultural resources, NEPA, permitting, or other environmental compliance work should be split out under 165. Produce Environmental Compliance Documentation.

    Example:

    WE: 35. Develop Pond
    WE Title: Develop pond on Johnson property
    WE Description: Develop 5 acre pond on Johnson property for put and take fishery.

    WE: 165. Produce Environmental Compliance Documentation
    WE Title: Permitting, NEPA compliance, and cultural resource surveys
    WE Description: Obtain permits and NEPA compliance, and conduct cultural resource surveys prior to building pond.

  • Rule 2 (Location of Work): If you are constructing ponds at more than one location, you may lump multiple locations in a single subbasin under a single work element. However, you may wish to break the work into separate work elements if it provides clarity or better supports project management. Note that different locations do not need to be separated into multiple environmental compliance work elements.

    Example:

    WE: 35. Develop Pond
    WE Title: Develop pond on Johnson property
    WE Description: Develop 5 acre pond on Johnson property for put and take fishery.

    WE: 35. Develop Pond
    WE Title: Develop ponds on Smith and Jones properties
    WE Description: Develop 17 acre pond on Smith property and 11 acre pond on Jones property to benefit waterfowl. Both ponds are in Fishy Subbasin.


Milestone Title
Type
Deliverable?
Description

Environmental compliance requirements complete -New
Required
No
On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff.
Environmental Compliance followed for duration of work element
Suggested
No
Contractor and sub-contractors shall adhere to all mitigation and conservation measures, terms and conditions, avoidance areas, and best management practices required under environmental laws as directed by BPA.
Discuss HIP ESA coverage with BPA EC Lead; obtain HIP risk determination
Recommended
No
The EC Lead will determine if work under this work element may be able to have ESA-coverage (NMFS & USFWS) under the current version of the Habitat Improvement Program Biological Opinions (HIP BiOps). Work that qualifies must comply with conservation measures in the HIP Handbook. Medium to high risk projects will require a technical review by the Bonneville Engineering Technical Services. Before conceptual design commences, contact the EC lead for HIP applicability, instructions and information requirements.

See risk determination work categories here: https://www.cbfish.org/WorkElement.mvc/Summary/165 .
Site plan and/or excavation plan complete
Suggested
No
Negotiations with landowners completed
Suggested
No
Verify water rights/well capacity (if applicable) or water collection method has high assuredness
Suggested
No
Begin excavation
Suggested
No
Completion of pond
Suggested
No


Location Requirement Type:
Location Work Site in CBFish
Number of Locations:
1 - 100
Location Guidance:
Identify point at location of installation. You may enter more than one point for this work element. If a location already exists in Pisces, click the "Link" button to synchronize locations.

Applicability and status of the following environmental compliance requirements can be found on the Environmental Compliance tab for that work element in your SOW for all 2007 contracts forward. BPA's Environmental staff will update and maintain this information in CBFish in real time, so that you can check the status of environmental compliance on your project at any time.

Note: Many of the fields are set to auto-load in CBFish, but the settings will be reviewed by BPA's Environmental staff prior to the contract being finalized, and may be revised depending on the specific circumstances.

  • National Environmental Policy Act (NEPA)
    NEPA coverage for this work element will be determined by BPA's Environmental staff and could include an Environmental Impact Statement (EIS), Environmental Assessment (EA), Record of Decision to an existing EIS, or Categorical Exclusion.

  • Endangered Species Act (ESA)
    ESA consultation is typically required for this work element.

  • National Historic Preservation Act (NHPA)
    NHPA Section 106 consultation is typically required for this work element which often includes a cultural/historic resource survey by a qualified archaeologist.

  • Public Involvement
    Public involvement is typically not required for this work element.


Reports that Use this Work Element

This work element and its metrics are used in measures in the following reports. These PDF reports are generated dynamically, always showing you the most up to date information. Most of them also have links to download the underlying data sets to structured text or Excel format.

Stats and Overview

Number of active contracts using Work Element #35 by FY

Top 5 BPA Project Managers using this Work Element:
(by number of current contracts)
Virgil Watts III 7
Tracy Hauser 4
John Baugher (Inactive) 2
Roy Beaty (Inactive) 2
David Roberts (Inactive) 2
Average Work Element Budget: $25,894
Average Duration: 10 months