Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
Select a work element:
Contract Number:
Contract Title:
1998-016-00 EXP IMPLEMENT EMAP IN JOHN DAY SUBBASIN
Contract Start Date:
10/1/2014
Contract End Date:
1/31/2016
Title:
N: 132 - RM&E Technical Report
Description:
Each annual report will be organized as follows:
Abstract
Introduction
Description of project area
Materials and methods
Results and discussion of results by objective
Summary and conclusions
Appendices of supplemental information
WE Agreement Type:
Contracted
Deliverable Specification:
Final RM&E Technical Report for Calendar Year 2015 (1/1/15 - 12/31/15) uploaded to the BPA reports web site.
WSE Effective Budget:
$10,000
% of Total WSE Effective Budget:
1.29%
WSE Start:
10/05/2015
WSE End:
01/31/2016
WSE Completion:
01/26/2016
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $10,000 $10,000

4 Milestones
Sort Type Title Start End Status Modified By Modified Date
A RMET1 RM&E Technical: Prepare for RM&E Technical Report. Review the revised (2015) guidance & template 10/5/2015 10/15/2015 Concluded Jamie Cleveland (Inactive) 6/30/2015 11:45:54 AM
Description: Review the newly-revised guidance & template for your RME Technical Report. BPA Fish and Wildlife project sponsors who have the following work elements in their contracts are required to complete a RM&E technical report: 156 Develop RM&E Methods and Designs, 157 Collect/Generate/Validate Field and Lab Data, 158 Mark and Tag Animals, and/or 162 Analyze/Interpret Data. Reports must show cumulative results and synthesis for the duration data collection/analysis studies.
B RMET2 RM&E Technical: Upload draft RM&E Technical Report (MS Word) for BPA review 1/5/2016 1/31/2016 Concluded Ian Tattam 6/5/2015 3:09:36 PM
Description: Upload your draft RM&E report into the Pisces Attachments tab as an MS Word document as a "Technical, Draft" for BPA review. BPA will review the draft RM&E report. If your Word file is too big to be uploaded, contact fish support. For more information on structure and content of your report, please use the newly-revised guidance & template for RME Reports located at https://www.cbfish.org/Help.mvc/GuidanceDocuments. (Milestone start/end: September 15 - January 15).
C IntRev Distribute Progress Report for Internal Contractor Review 12/5/2015 12/20/2015 Concluded Ian Tattam 6/5/2015 3:09:36 PM
Description: Internal review will be conducted by Jim Ruzycki before being reviewed externally or being uploaded.
D DELIV RM&E Technical Report 1/31/2016 Concluded Jamie Cleveland (Inactive) 6/30/2015 2:28:40 PM
Description: Final RM&E Technical Report for Calendar Year 2015 (1/1/15 - 12/31/15) uploaded to the BPA reports web site.

Implementation Metrics
Metric Planned Actual Contractor Comments Measures HLIs
1768. Start date of reporting period 1/1/2015 1/1/2015
1769. End date of reporting period 12/31/2015 12/31/2015

This work element does not require Focal Species
This work element does not require Environmental Compliance
This work element does not require RM&E metadata