This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. Amendment 001 (03/01/2016 - 02/28/2017) | $44,074 | $33,145 | LWC, BEF (PM), and contactors | |
Work Element Budget (Current Performance Period) | $44,074 | $33,145 | LWC, BEF (PM), and contactors |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 9/30/2016 | 12/30/2016 | Canceled | Steven Gagnon (Inactive) | 2/15/2017 12:42:45 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Suggested | Incorporate final plan into the annual report | 1/3/2017 | 9/29/2017 | Concluded | Steven Gagnon (Inactive) | 2/15/2017 3:17:00 PM |
Description: After review of draft, incorporate plan into annual report. | |||||||
C | Suggested | Prepare draft plan | 9/30/2016 | 8/18/2017 | Concluded | Steven Gagnon (Inactive) | 2/15/2017 3:17:00 PM |
Description: Prepare draft report and plan for future design and implementation based on analysis. | |||||||
D | Define monitoring framework | 3/1/2016 | 2/28/2017 | Active | Steven Gagnon (Inactive) | 2/15/2017 12:42:45 PM | |
Description: Work in coordination with USGS and other project partners to outline monitoring framework. | |||||||
E | Evaluate floodplain restoration alternatives | 3/1/2016 | 7/31/2017 | Concluded | Steven Gagnon (Inactive) | 2/15/2017 3:17:00 PM | |
Description: Evaluate two identified floodplain reconnection sites (SIA 7 & 8 in River Design Group 2013 Hydrologic Analysis) and consider other floodplain opportunities as recommended by Technical Review Team (TRT). | |||||||
F | Cultural Resources Review | 9/1/2016 | 8/18/2017 | Active | Steven Gagnon (Inactive) | 2/15/2017 3:17:00 PM | |
Description: Conduct preliminary cultural resources survey of identified priority floodplain reconnection sites. Survey can include literature review and may include preliminary shovel-probing. | |||||||
G | DELIV | Final Restoration Plan and Monitoring Framework | 9/14/2017 | Concluded | Steven Gagnon (Inactive) | 2/15/2017 3:17:00 PM | |
Description: Document result of analysis, plans for future design and restoration, and monitoring framework. |