2009-012-00 EXP LSNA FLOODPLAIN RECONNECTION DESIGN
Contract Start Date:
3/1/2016
Contract End Date:
9/29/2017
Title:
D: 174 - Opportunities for Floodplain Reconnection and Monitoring Framework
Description:
Conduct "fish consultation" with Technical Review Team as requested from proposal feedback. Conduct analysis of Site Implementation Areas (SIAs) 7 and 8 as outlined in River Design Group's preliminary Hydrologic Analysis. Consider if there are other floodplain opportunities as described in TRT review feedback. Conduct cost-benefit analysis of potential implementation areas and outline a plan for future design and implementation work based on analysis. Develop and document monitoring framework in coordination with USGS and partners and begin pre-restoration monitoring.
WE Agreement Type:
Contracted
Deliverable Specification:
Document result of analysis, plans for future design and restoration, and monitoring framework.
WSE Effective Budget:
$33,145
% of Total WSE Effective Budget:
82.88%
WSE Start:
03/01/2016
WSE End:
09/29/2017
WSE Completion:
09/29/2017
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
1. Amendment 001 (03/01/2016 - 02/28/2017) $44,074 $33,145 LWC, BEF (PM), and contactors
Work Element Budget (Current Performance Period) $44,074 $33,145 LWC, BEF (PM), and contactors

7 Milestones
Sort Type Title Start End Status Modified By Modified Date
A EC Environmental compliance requirements complete 9/30/2016 12/30/2016 Canceled Steven Gagnon (Inactive) 2/15/2017 12:42:45 PM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA).
B Suggested Incorporate final plan into the annual report 1/3/2017 9/29/2017 Concluded Steven Gagnon (Inactive) 2/15/2017 3:17:00 PM
Description: After review of draft, incorporate plan into annual report.
C Suggested Prepare draft plan 9/30/2016 8/18/2017 Concluded Steven Gagnon (Inactive) 2/15/2017 3:17:00 PM
Description: Prepare draft report and plan for future design and implementation based on analysis.
D Define monitoring framework 3/1/2016 2/28/2017 Active Steven Gagnon (Inactive) 2/15/2017 12:42:45 PM
Description: Work in coordination with USGS and other project partners to outline monitoring framework.
E Evaluate floodplain restoration alternatives 3/1/2016 7/31/2017 Concluded Steven Gagnon (Inactive) 2/15/2017 3:17:00 PM
Description: Evaluate two identified floodplain reconnection sites (SIA 7 & 8 in River Design Group 2013 Hydrologic Analysis) and consider other floodplain opportunities as recommended by Technical Review Team (TRT).
F Cultural Resources Review 9/1/2016 8/18/2017 Active Steven Gagnon (Inactive) 2/15/2017 3:17:00 PM
Description: Conduct preliminary cultural resources survey of identified priority floodplain reconnection sites. Survey can include literature review and may include preliminary shovel-probing.
G DELIV Final Restoration Plan and Monitoring Framework 9/14/2017 Concluded Steven Gagnon (Inactive) 2/15/2017 3:17:00 PM
Description: Document result of analysis, plans for future design and restoration, and monitoring framework.

This work element does not require Metrics
Primary Focal Species:
Chinook (O. tshawytscha) - Upper Willamette River ESU (Threatened); Cutthroat Trout, Coastal (O. c. clarkii) - Upper Willamette River ESU; Steelhead (O. mykiss) - Upper Willamette River DPS (Threatened)
Secondary Focal Species:
Lamprey, Pacific (Entosphenus tridentata)

This work element does not require RM&E metadata