Province | Subbasin | % |
---|---|---|
Lower Columbia | Willamette | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 28-Feb-2025.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Steven Gagnon | Bonneville Power Administration | Yes | COR | skgagnon@bpa.gov | (503) 230-3375 |
Kristen Larson | Luckiamute Watershed Council | Yes | Contract Manager | director@luckiamutelwc.org | (503) 837-0237 |
Solomonn Marsh | Bonneville Power Administration | Yes | Contracting Officer | spmarsh@bpa.gov | (503) 230-3943 |
Justin Moffett | Bonneville Power Administration | Yes | Env. Compliance Lead | jtmoffett@bpa.gov | (503) 230-3233 |
Gail Oberst | Luckiamute Watershed Council | No | Supervisor | gailoberst@yahoo.com | (503) 871-1242 |
Christopher Roper | Bonneville Power Administration | No | CO Assistant | cproper@bpa.gov | (503) 230-3514 |
Tybee Sheidler | Bonneville Power Administration | No | CO Assistant | tasheidler@bpa.gov | (503) 230-3820 |
John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
Elham Zolmajd-Haghighi | Bonneville Power Administration | No | CO Assistant | ezolmajd-haghighi@bpa.gov | (503) 230-7414 |
A | 170139 | 165 | Produce Environmental Compliance Documentation | Review NEPA/ESA/Cultural Resources Requirements | Ensure all environmental compliance requirements have been satisfied. | $0 | 0.00% | 03/01/2016 | 12/30/2016 |
B | 170140 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR. | $224 | 0.56% | 07/01/2016 | 09/29/2017 |
C | 170141 | 119 | Manage and Administer Projects | Establish subcontracts and oversee project tasks and coordination | Covers project management and administrative work related to the contract excluding environmental compliance. | $6,264 | 15.66% | 03/01/2016 | 09/29/2017 |
D | 170142 | 174 | Produce Plan | Opportunities for Floodplain Reconnection and Monitoring Framework | Conduct "fish consultation" with Technical Review Team as requested from proposal feedback. Conduct analysis of Site Implementation Areas (SIAs) 7 and 8 as outlined in River Design Group's preliminary Hydrologic Analysis. Consider if there are other floodplain opportunities as described in TRT review feedback. Conduct cost-benefit analysis of potential implementation areas and outline a plan for future design and implementation work based on analysis. Develop and document monitoring framework in coordination with USGS and partners and begin pre-restoration monitoring. | $33,145 | 82.88% | 03/01/2016 | 09/29/2017 |
E | 170143 | 132 | Produce Progress (Annual) Report | Submit Progress Report for the period (Mar 2016 - Feb 2017) | The work that is completed under this contract will lead to the development of a restoration plan for the property. The restoration plan will be submitted in lieu of a progress report. | $359 | 0.90% | 09/29/2017 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental Compliance Documentation | A: 165. Review NEPA/ESA/Cultural Resources Requirements | 12/30/2016 | 12/30/2016 | |
All administrative tasks fulfilled with timely quality products | C: 119. Establish subcontracts and oversee project tasks and coordination | 09/29/2017 | 09/29/2017 | |
Final Restoration Plan and Monitoring Framework | D: 174. Opportunities for Floodplain Reconnection and Monitoring Framework | 09/14/2017 | 09/29/2017 | |
Completed Annual Report | E: 132. Submit Progress Report for the period (Mar 2016 - Feb 2017) | 09/29/2017 | 09/29/2017 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Willamette River ESU (Threatened) |
|
Cutthroat Trout, Coastal (O. c. clarkii) - Upper Willamette River ESU |
|
Steelhead (O. mykiss) - Upper Willamette River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Review NEPA/ESA/Cultural Resources Requirements | 01/01/2016 | ||||||
B | 185 | Periodic Status Reports for BPA | 03/01/2016 | ||||||
C | 119 | Establish subcontracts and oversee project tasks and coordination | 01/01/2016 | ||||||
D | 174 | Opportunities for Floodplain Reconnection and Monitoring Framework | |||||||
E | 132 | Submit Progress Report for the period (Mar 2016 - Feb 2017) | 02/01/2016 |