A |
|
Advertise construction contract |
4/1/2018 |
4/30/2018 |
Concluded |
Andre L'Heureux (Inactive) |
11/7/2019 9:12:53 AM |
|
Description: Develop public bid document and solicit sub-contractors for construction contracts: (a) Advertise the construction bids for grubbing access points and staging areas; (b) Advertise the bids for helicopter delivery of trees, boulders and other construction materials; and (c) Advertise the construction bids for implementation of additional ground-based elements of the project build-out. |
B |
|
Obtain materials for structure composition (purchase of logs, boulders, etc.) |
4/1/2018 |
6/30/2018 |
Concluded |
Andre L'Heureux (Inactive) |
11/7/2019 9:12:53 AM |
|
Description: Construction materials sourced and acquired: transported and staged in secure storage locations; or identified and secured in areas adjacent to the project site/construction zone. |
C |
|
Award the construction contract: site prep and materials |
4/16/2018 |
5/14/2018 |
Concluded |
Andre L'Heureux (Inactive) |
11/7/2019 9:12:53 AM |
|
Description: Select the subcontractor(s) based on: a) the construction bids for developing access points and staging areas; and b) the bids for securing and delivering of trees, boulders, and racking or other construction materials. |
D |
|
Award the construction contract: LWD structures and single-log placements |
4/16/2018 |
6/15/2018 |
Concluded |
Andre L'Heureux (Inactive) |
11/7/2019 9:12:53 AM |
|
Description: Select the subcontractor(s) based on the construction bids; award contract for: 1) helicopter delivery & installation of the additional channel development and floodplain engagement project elements (wood-loading); and 2) additional ground activity work components. |
E |
|
Construction inspection: a) access points and staging areas; b) PA-3 maintenance (FY18) |
4/30/2018 |
9/14/2018 |
Concluded |
Andre L'Heureux (Inactive) |
11/7/2019 9:12:53 AM |
|
Description: Provide construction inspections and guidance in the pre-construction activities (access points and equipment or materials staging areas), and in the maintenance and supplementation (additional wood-loading) of major channel complexity elements for the project. Field engineering will be a major component of this work element.
Continue supervision of sub-contract activities, and provide implementation oversight throughout the construction period until the project work is completed as designed. |
F |
|
Award construction contract for vegetative plantings (restoration design elements & site remediation) |
6/1/2018 |
10/1/2018 |
Concluded |
Andre L'Heureux (Inactive) |
11/7/2019 9:12:53 AM |
|
Description: Select the subcontractor(s) based on the construction bids; award contract to plant trees, shrubs and grasses to support the restoration design and the remediation of site impacts |
G |
|
Provide as-built drawings and daily construction logs |
7/2/2018 |
11/2/2018 |
Concluded |
Andre L'Heureux (Inactive) |
11/7/2019 9:12:53 AM |
|
Description: Development and submittal of as-built drawings of access points and staging areas. Review and certify as-built drawings and review daily construction logs for supplemental wood-loading and other construction activities (PA-3). |
H |
|
[CCR-42622]: Construction inspection (FY19/20): a) PA-3 (maintenance); b) RM-42 (LWD install) |
9/30/2019 |
10/30/2020 |
Canceled |
Andre L'Heureux (Inactive) |
11/15/2019 11:02:57 AM |
|
Description: Provide construction inspections and guidance in the pre-construction activities (access points and equipment or materials staging areas), and in the maintenance and supplementation (additional wood-loading) of channel complexity elements for the projects. Field engineering will be a major component of this work element.
Continue supervision of sub-contract activities (if any), and provide implementation oversight throughout the construction period until the project work is completed as designed. |
I |
|
[CCR-42622]: Award construction contract for vegetative plantings (restoration design elements & site remediation) |
6/1/2018 |
10/30/2020 |
Canceled |
Andre L'Heureux (Inactive) |
11/15/2019 11:02:57 AM |
|
Description: Select the subcontractor(s) based on the construction bids; award contract to plant trees, shrubs and grasses to support the restoration maintenance design and the remediation of site impacts |
J |
DELIV |
Provide pre-construction project management activities; supervise the wood-loading and additional features: PA-3 |
|
6/30/2020 |
Concluded |
Andre L'Heureux (Inactive) |
11/7/2019 9:12:53 AM |
|
Description: Where feasible and as clearances are obtained, conduct site preparation - including projected construction access points and material or equipment staging areas, in anticipation of the follow-up maintenance and supplemental LWD whole-tree additions to the Project Area during the Summer of 2018.
Source, confirm with USFS, and plan the acquisition of construction materials needed for habitat features and restoration actions. Hazard trees, and/or windblown (salvage) trees are being made available to project implementation staff (CTUIR-SRSRB) for placement as supplemental habitat structure at PA-3. Secure and, as necessary, transport trees (large wood) and other construction materials to pre-arranged storage locations.
Provide construction oversight, contractor supervision, and inspection of completed access points, materials or equipment storage sites, preliminary design features, and initial project components. As applicable: 1) Collect and review daily construction logs; 2) Review/approve change order requests: contractor shall consult with BPA CO (in consultation with BPA COTR) on any desired change orders before directing the construction contractor to make them; 3) Review sub-contractor's requests for payments; and 4) Maximize the acquisition and secure-storage of construction materials in anticipation of current and anticipated construction needs. |