SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 81592 (03/01/2019 - 03/31/2020) | $20,186 | $20,186 | ||
Work Element Budget (Current Performance Period) | $20,186 | $20,186 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | NonT1 | Non-Technical: Prepare for non-technical Progress Report. Review most recent guidance and template. | 3/1/2019 | 5/31/2019 | Concluded | Jody Lando | 8/28/2019 8:23:11 AM |
Description: Contractor must review guidance and template before starting the first draft of their non-technical report. Please follow the newly revised BPA-required format for Non-Technical Reports at: https://www.cbfish.org/Help.mvc/GuidanceDocuments. | |||||||
B | NonT2 | Non-Technical: Write Non-technical Progress Report | 11/1/2019 | 12/31/2019 | Concluded | Jody Lando | 8/28/2019 8:23:11 AM |
Description: Please follow the BPA-required format. The newly revised BPA-required format for Non-Technical Reports can be found at: https://www.cbfish.org/Help.mvc/GuidanceDocuments. | |||||||
C | NonT3 | Non-Technical: Upload Non-Technical Progress Report in Pisces | 12/31/2019 | 2/28/2020 | Concluded | Jody Lando | 8/28/2019 8:23:11 AM |
Description: Use the attachment tab in Pisces to upload your progress report in MS-Word format as "Non-Technical, Draft". After BPA review and finalized editing, BPA staff with post the report for public access. If the file size is too large for Pisces to accept, contact Pisces Support for help. | |||||||
D | IntRev | Distribute Progress Report for Internal Contractor Review | 1/9/2020 | 1/10/2020 | Concluded | Jody Lando | 8/28/2019 8:23:11 AM |
Description: Internal review will be conducted by [Chris Beasley, Director of Biomark Applied Biological Services] before being reviewed externally or being uploaded. | |||||||
E | ExtRev | Distribute Progress Report for External Review to [Insert external review entity] | 1/11/2020 | 1/15/2020 | Concluded | Jody Lando | 8/28/2019 8:23:11 AM |
Description: External (non-BPA) review of the report will be conducted by [Evan Brown, IFWIS] before being uploaded. | |||||||
F | DELIV | Completed Annual Report | 2/29/2020 | Concluded | Jody Lando | 8/28/2019 8:23:11 AM | |
Description: The Deliverable is considered complete when the final report is posted. It usually takes BPA 30-45 days to post the final PDF version of a report. This milestone's end date should therefore be 45 days after the final version is uploaded in Pisces. You will receive an email from BPA confirming that your report has been finalized and posted to the web. Mark this milestone complete when you have confirmed your final report has been posted. If you do not receive such an email after 45 days, contact your COTR. 45 days is not possible, given the expected termination of data collection. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1768. Start date of reporting period | 1/1/2019 | 3/1/2019 | |||
1769. End date of reporting period | 12/31/2019 | 2/29/2020 |