1992-009-00 EXP WDFW SCR O&M, YAK, UCR, LCR
Contract Start Date:
7/1/2019
Contract End Date:
6/30/2020
Title:
F: 69 - Screen Placeholder #3 Provide Materials to Support install of Fish Screen (Task #3)
Description:
WDFW will provide pre-fabricated material, or fabricate modular gravity diversion, fish screens adherent to WDFW and NOAA screening criteria for use in the Middle and Upper Columbia River regions for salmon recovery efforts. These screens will constitute WDFW's cost share contribution. Other partners may handle actual screen facility construction, though WDFW staff may assist and oversee with fish screen installation.
WE Agreement Type:
Contracted
Deliverable Specification:
Screens will be compliant with WDFW, NOAA, and USFWS screening specifications as appropriate.
WSE Effective Budget:
$200
% of Total WSE Effective Budget:
0.15%
WSE Start:
07/01/2019
WSE End:
06/30/2020
WSE Completion:
06/30/2020
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $3,000 $200 pump screen stand fabrictaion and powder coating

5 Milestones
Sort Type Title Start End Status Modified By Modified Date
A EC Environmental compliance requirements complete 7/1/2019 7/31/2019 Concluded Jamie Cleveland (Inactive) 2/7/2019 11:00:01 AM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff.
B Participate in Cost Shares with Partners, Facilitate Compliant Fish Screen Installation as Appropriate 7/1/2019 6/30/2020 Concluded Jamie Cleveland (Inactive) 2/7/2019 11:00:01 AM
Description: Cost share partners will complete actual installations.
C Assure EC Requirements Have Been Met Prior to Water-User Installation of Pump Screen 7/1/2019 6/30/2020 Concluded Jamie Cleveland (Inactive) 4/19/2019 5:31:23 PM
Description: If the water user is installing the fish screen, assure all EC is met.
D Assure EC and Cultural Resource Requirements Have Been Met Prior to WDFW Crews Installing Gravity Fish Screen 7/1/2019 6/30/2020 Concluded Jamie Cleveland (Inactive) 4/19/2019 5:23:51 PM
Description: If WDFW is installing the fish screen, assure all EC is met including cultural resources requirements.
E DELIV Provide Pre-fabricated Fish Screens and Fish Screening Materials as Appropriate 6/30/2020 Concluded Jamie Cleveland (Inactive) 2/7/2019 11:00:01 AM
Description: Screens will be compliant with WDFW, NOAA, and USFWS screening specifications as appropriate.

Work Site ID Latitude Longitude State County Province Subbasin
33628 47.465816 -120.337286 Washington Chelan Columbia Cascade Wenatchee

Primary Focal Species:
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
Secondary Focal Species:
None

This work element does not require RM&E metadata