This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $294,300 | $294,300 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 3/15/2011 | 3/28/2011 | Concluded | Christopher Beasley (Inactive) | 3/15/2011 7:26:28 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Suggested | Engineering/design | 3/21/2011 | 3/25/2011 | Active | Brian Beckley | 3/14/2011 9:03:48 AM |
Description: Engineering and Design Systems | |||||||
C | Suggested | Purchase, fabrication, construction, and/or installation of the equipment or facility | 3/28/2011 | 4/29/2011 | Active | Brian Beckley | 3/14/2011 9:04:48 AM |
Description: Fabricate antennas, enclosures, and communications equipment. | |||||||
D | Suggested | Testing, calibration, modification | 5/1/2011 | 5/31/2011 | Active | Brian Beckley | 3/14/2011 9:05:24 AM |
Description: Installation and test equipment on-site | |||||||
E | Suggested | Deliverable completed: in-place and fully functional | 6/1/2011 | 9/30/2011 | Active | Brian Beckley | 3/14/2011 9:06:10 AM |
Description: Install array during low-flow (June - September). | |||||||
F | DELIV | Install tandem PIT tag array Lolo Creek | 9/30/2011 | Active | Brian Beckley | 3/14/2011 9:01:25 AM | |
Description: Lolo Creek PIT tag array is installed and fully functional, including remote communications. |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
25179 | 46.29042 | -115.93397 | Idaho | Idaho | Mountain Snake | Clearwater |