SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 55189 (11/01/2011 - 12/31/2012) | $30,000 | $30,000 | ||
Work Element Budget (Current Performance Period) | $30,000 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 11/1/2011 | 11/30/2011 | Active | Dorothy Welch | 9/19/2012 4:44:43 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Collect hydrologic data from staff gauges | 12/1/2011 | 10/30/2012 | Concluded | Dorothy Welch | 9/19/2012 4:51:45 PM | |
Description: The landowners and River Design Group will collect seasonal flow information from staff gauges installed at the Horseshoe Lake properties. The data will be used to refine and calibrate 2-year inundation models that River Design Group will develop to assist in the management plans for these properties. | |||||||
C | Collect aerial imagery | 12/1/2011 | 6/30/2012 | Concluded | Dorothy Welch | 9/19/2012 4:44:43 PM | |
Description: Greenbelt Land Trust will contract with Eagle Imaging to complete geo-referenced aerial imagery of selected reaches between the Santiam/Willamette River confluence and Green Island. The images will be taken during high flow events (action stage or above) of these reaches and will be used to further calibrate the flow models created by River Design Group and assist in the management and restoration planning for Horseshoe Lake properties with proposed conservation easements and the selection of future areas for protection and restoration. | |||||||
D | Conduct winter fish sampling | 12/1/2011 | 4/30/2012 | Concluded | Dorothy Welch | 9/19/2012 4:44:43 PM | |
Description: OSU (Stan Gregory's lab) will sample fish species and populations in the back-channel habitats on the Horseshoe Lake properties during winter. The intent of the sampling is to develop an inventory of species and age classes in the side channels on these properties to assist in the management planning and restoration opportunities. | |||||||
E | Conduct summer fish sampling | 6/1/2012 | 10/31/2012 | Concluded | Dorothy Welch | 9/19/2012 4:44:43 PM | |
Description: OSU (Stan Gregory's lab) will sample fish species and populations in the back-channel habitats on the Horseshoe Lake properties during summer. The intent of the sampling is to develop an inventory of species and age classes in the side channels on these properties to assist in the management planning and restoration opportunities. | |||||||
F | Form a technical team to propose restoration actions based on collected data | 6/1/2012 | 12/31/2012 | Active | Dorothy Welch | 9/19/2012 4:44:43 PM | |
Description: Form a technical team with landowners to discuss and select proposed restoration actions based on collected hydrologic and fish sampling data for Horseshoe Lake. | |||||||
G | Draft management/restoration plan | 7/1/2012 | 12/15/2012 | Active | Dorothy Welch | 9/19/2012 4:51:46 PM | |
Description: Complete a draft management plan for restoration actions for Horseshoe Lake. | |||||||
H | DELIV | Management/restoration plan for Horseshoe Lake properties | 12/31/2012 | Active | Dorothy Welch | 9/19/2012 4:51:56 PM | |
Description: The management plan will be developed with the assistance of a technical team and will be submitted to OWEB, ODFW, and BPA for review as outlined in the conservation easement. Once finalized, Greenbelt Land Trust will attach the management plan in Pisces. |