Province | Subbasin | % |
---|---|---|
Lower Columbia | Willamette | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 31-Mar-2025.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Jeff Baker | Greenbelt Land Trust | Yes | Contract Manager | jeff@greenbeltlandtrust.org | (541) 752-9609 |
Israel Duran | Bonneville Power Administration | No | Env. Compliance Lead | induran@bpa.gov | (503) 230-3967 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Michael Pope | Greenbelt Land Trust | Yes | Supervisor | michael@greenbeltlandtrust.org | (541) 752-9609 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Dorothy Welch | Bonneville Power Administration | Yes | COR | dwwelch@bpa.gov | (503) 230-5479 |
A | 109732 | 165 | Produce Environmental Compliance Documentation | Prepare NEPA/ESA documentation. | Comply with NEPA/ESA regulations. Obtain all necessary permits and complete all required consultation. | $200 | 0.22% | 11/01/2011 | 12/31/2011 |
B | 109733 | 119 | Manage and Administer Projects | Establish subcontracts and oversee project tasks and coordination | Greenbelt Land Trust will establish subcontracts with River Design Group, Oregon State University, and Eagle Imaging for the hydrologic work, fish sampling and aerial imagery. Greenbelt will also coordinate reports and the establishment of a Technical Team to propose restoration alternatives for the project sites (Horseshoe and Harkens Lake). | $12,000 | 13.06% | 11/01/2011 | 12/31/2012 |
C | 109734 | 148 | Install Flow Measuring Device | Install Staff gauges at Little Willamette and Horseshoe Lake for innundation/flow informatio | River Design Group will install 5-8 staff gauges in selected areas on the Little Willamette and Horseshoe Lake properties south of Bowers Rock State Park near Albany along mainstem of the Willamette River. The gauges will be fixed and installed in early fall 2011 to allowed for monitoring of flows (highs and lows) to determine inundation characteristics. . | $1,500 | 1.63% | 11/01/2011 | 11/30/2011 |
D | 109735 | 174 | Produce Plan | Develop management/restoration plan for Harkens Lake | Produce management plans that include restoration priorities and timelines for the Harkens Lake properties. | $30,000 | 32.65% | 11/01/2011 | 12/31/2012 |
E | 109736 | 174 | Produce Plan | Develop management/restoration plan for Horseshoe Lake | Produce management plans that include restoration priorities and timelines for the Horseshoe Lake properties. | $30,000 | 32.65% | 11/01/2011 | 12/31/2012 |
F | 109737 | 174 | Produce Plan | Collect additional data to refine Little Willamette management plan | Collect additional data to refine management plan for the Little Willamette property. | $18,000 | 19.59% | 11/01/2011 | 12/31/2012 |
G | 109738 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR. | $186 | 0.20% | 01/01/2012 | 12/31/2012 |
H | 109739 | 132 | Produce Progress (Annual) Report | Submit Progress Report for the period - Not Required | The work that is completed under this contract will lead to the development of a restoration plan for each property. The restoration plans will be submitted in lieu of a progress report. | $0 | 0.00% |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Receipt of environmental compliance clearance from BPA | A: 165. Prepare NEPA/ESA documentation. | 12/31/2011 | 12/31/2011 | |
Establish Subcontracts and Coordinate Project Tasks and Reporting | B: 119. Establish subcontracts and oversee project tasks and coordination | 12/31/2012 | 12/31/2012 | |
Installation of 5-8 Staff Gauges on Horseshoe Lake and Little Willamette properties | C: 148. Install Staff gauges at Little Willamette and Horseshoe Lake for innundation/flow informatio | 11/30/2011 | 11/30/2011 | |
Management/restoration plan for Harkens Lake properties | D: 174. Develop management/restoration plan for Harkens Lake | 12/31/2012 | 12/15/2012 | |
Management/restoration plan for Horseshoe Lake properties | E: 174. Develop management/restoration plan for Horseshoe Lake | 12/31/2012 | ||
Refined management plan for Little Willamette property | F: 174. Collect additional data to refine Little Willamette management plan | 12/31/2012 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Willamette River ESU (Threatened) |
|
Steelhead (O. mykiss) - Upper Willamette River DPS (Threatened) |
|
Chub, Oregon (Oregonichthys crameri) (Endangered through FY2015) |
|
Wildlife |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Prepare NEPA/ESA documentation. | 09/26/2011 | ||||||
B | 119 | Establish subcontracts and oversee project tasks and coordination | 09/26/2011 | ||||||
C | 148 | Install Staff gauges at Little Willamette and Horseshoe Lake for innundation/flow informatio | 10/31/2011 | ||||||
D | 174 | Develop management/restoration plan for Harkens Lake | 10/15/2011 | ||||||
E | 174 | Develop management/restoration plan for Horseshoe Lake | 10/15/2011 | ||||||
F | 174 | Collect additional data to refine Little Willamette management plan | 10/15/2011 | ||||||
G | 185 | Periodic Status Reports for BPA | 09/26/2011 | ||||||
H | 132 | Submit Progress Report for the period - Not Required | 09/26/2011 |