This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $15,000 | $15,000 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | NonT1 | Review progress report format requirements | 3/1/2012 | 3/9/2012 | Concluded | Deborah Docherty (Inactive) | 11/29/2011 8:48:25 AM |
Description: Contractor must review formatting requirements before starting the first draft of their report. Please follow the BPA-required format. https://efw.bpa.gov/IntegratedFWP/technicalreports.aspx | |||||||
B | NonT3 | Submit progress report for internal contractor review | 3/9/2012 | 4/1/2012 | Concluded | Deborah Docherty (Inactive) | 11/29/2011 8:48:25 AM |
Description: Use this milestone if the annual report requires an internal review before being reviewed externally. Make sure to allow for both technical and policy reviews if necessary. | |||||||
C | Submit progress report to CTUIR | 4/1/2012 | 4/1/2012 | Concluded | Deborah Docherty (Inactive) | 11/29/2011 8:48:25 AM | |
Description: Progress report submitted to CTUIR. | |||||||
D | Coordination with CTUIR on any needed revisions to progress report | 4/1/2012 | 4/15/2012 | Concluded | Deborah Docherty (Inactive) | 11/29/2011 8:48:25 AM | |
Description: NOAA will work with CTUIR during final revision stage of progress report, assisting with any needed revisions prior to CTUIR's April 15, 2012 submission date to BPA. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1768. Start date of reporting period | 10/1/2010 | ||||
1769. End date of reporting period | 9/30/2011 |