SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $400 | $400 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | NonT1 | Review progress report format requirements | 10/1/2013 | 10/1/2013 | Concluded | Pamela Nelle | 12/3/2012 11:36:36 AM |
Description: Contractor must review formatting requirements before starting the first draft of their report. Please follow the BPA-required format. https://efw.bpa.gov/IntegratedFWP/technicalreports.aspx | |||||||
B | NonT3 | Submit progress report for internal contractor review | 12/23/2013 | 12/31/2013 | Concluded | Pamela Nelle | 12/3/2012 11:36:36 AM |
Description: Use this milestone if the annual report requires an internal review before being reviewed externally. Make sure to allow for both technical and policy reviews if necessary. | |||||||
C | IntRev | Submit progress report for external review | 12/23/2013 | 12/31/2013 | Concluded | Pamela Nelle | 12/3/2012 11:36:36 AM |
Description: Use this milestone if the progress report requires external review. | |||||||
D | DELIV | Confirm BPA has posted the progress report | 2/3/2014 | 2/28/2014 | Concluded | Pamela Nelle | 12/3/2012 11:36:36 AM |
Description: It usually takes BPA 30-45 days to post the final version of a report. This milestone's end date should therefore be 45 days after the Deliverable milestone. You will receive an email from BPA confirming that your report has been finalized and posted to the web. | |||||||
E | DELIV | Final (annual) report to NOAA Fisheries and BPA | 2/28/2014 | Concluded | Pamela Nelle | 12/3/2012 11:36:36 AM | |
Description: Submit Final (Annual) Report to NOAA Fisheries and BPA as follows: A final (annual) report will be prepared as outlined in 1-6 below covering the period of performance for this SOW. 1. Brief abstract (limit 600 words). 2. Introduction based on project purpose and rationale. 3. Concise description of project area. 4. Description of methods and materials used to perform tasks. 5. Summary of results (effectiveness of task completion; presentation of summarized field data in tabular or GIS format) and brief discussion of results by task. 6. If necessary, supplemental electronic copies of summarized field data in spreadsheet or GIS format." Additionally, the report will cover the following: - landowner access agreement forms - copies of newsletter articles and mailings - meeting agendas and minutes, as appropriate Final (Annual) Report: The Contractor shall submit an Annual Report to the Principal Investigator, Chris Jordan, at the Northwest Fisheries Science Center, to the ISEMP Wenatchee/Entiat Coordinator (Mike Ward, Terraqua, Inc.), as well as to the BPA Project Manager / COTR. Final versions of annual/technical reports should be submitted electronically, preferably as a portable document format (pdf) file, in one of the following ways: 1. Upload on-line (60MB maximum file size). The form with instructions for uploading files is located at: https://efw.bpa.gov/cgi-bin/FW/publications.cgi. 2. Copy to a CD or other portable storage device for mail or hand delivery (recommended for non-pdf files and documents over 60MB). 3. Attach to an email (for documents under 5MB). **** Upload annual report for the period Mar 2007 to Feb 2008. Currently, this is done via the BPA website; down the road, this may be done via attachments supported directly within Pisces. For guidance on how/where to upload: https://efw.bpa.gov/Integrated_Fish_and_Wildlife_Program/technicalreports.aspx Deliverables will include: - landowner access agreement forms - copies of newsletter articles and mailings - meeting agendas and minutes, as appropriate |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1768. Start date of reporting period | 3/1/2013 | 3/1/2013 | |||
1769. End date of reporting period | 2/25/2014 | 2/28/2014 |