This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $5,000 | $5,000 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | NonT1 | Review CLOSEOUT progress report format requirements | 1/15/2013 | 12/1/2013 | Concluded | Anne Creason | 11/19/2012 1:55:09 PM |
Description: Contractor must review formatting requirements before starting the first draft of their report. Please follow the BPA-required format. https://efw.bpa.gov/IntegratedFWP/technicalreports.aspx | |||||||
B | NonT3 | Submit CLOSEOUT progress report for internal contractor review | 10/1/2013 | 10/1/2013 | Concluded | Anne Creason | 10/29/2012 1:10:53 PM |
Description: Use this milestone if the annual report requires an internal review before being reviewed externally. Make sure to allow for both technical and policy reviews if necessary. | |||||||
C | IntRev | Submit CLOSEOUT progress report for external review | 10/1/2013 | 10/1/2013 | Concluded | Anne Creason | 10/29/2012 1:10:53 PM |
Description: Use this milestone if the progress report requires external review. | |||||||
D | DELIV | Confirm BPA has posted the CLOSEOUT progress report | 1/14/2014 | 1/14/2014 | Concluded | Anne Creason | 11/19/2012 12:06:25 PM |
Description: It usually takes BPA 30-45 days to post the final version of a report. This milestone's end date should therefore be 45 days after the Deliverable milestone. You will receive an email from BPA confirming that your report has been finalized and posted to the web. | |||||||
E | Deliver CLOSEOUT report to BPA | 12/15/2013 | 12/15/2013 | Concluded | Anne Creason | 11/14/2012 3:08:10 PM | |
Description: Deliver the Plume Project's FY13 Closeout Progress Report. The Report will cover all contracts under this project (1998-014-00). | |||||||
F | RME DRAFT Report covering 2012 calendar year | 1/15/2013 | 1/15/2013 | Concluded | Anne Creason | 10/29/2012 1:08:04 PM | |
Description: Draft Annual Report of work conducted for the calendar year to be submitted to BPA for upload by your COTR and if a RM&E Technical Report include RMESupport@bpa.gov. | |||||||
G | RME FINAL Report covering 2012 calendar year | 3/1/2013 | 3/1/2013 | Concluded | Anne Creason | 10/29/2012 1:08:04 PM | |
Description: Final Annual Report of work conducted for the calendar year to be submitted to BPA COTR and RMESupport@bpa.gov to be uploaded into Pisces. | |||||||
H | RPA BiOp Report | 3/15/2013 | 3/15/2013 | Concluded | Anne Creason | 10/29/2012 1:08:04 PM | |
Description: If you support an ESA BiOp RM&E RPA, electronically submit a Final Annual BiOp RPA Report of work conducted for the calendar year for upload into Taurus for FCRPS BiOp or as appendix to annual report for upload in Pisces and notify your BPA COTR and RMESupport@bpa.gov that the report is complete. | |||||||
I | DELIV | Deliver Annual Reports (RME, BiOp and Close out) to BPA | 1/14/2014 | Concluded | Anne Creason | 11/19/2012 12:06:25 PM | |
Description: Three separate Reports are due to BPA: 1) Report on closeout products as completed for the plume project (for NOAA only) 2) RME DRAFT and FINAL Reports (see Milestones) 3) ESA BiOp RPA Report |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1768. Start date of reporting period | 10/1/2012 | 1/14/2013 | |||
1769. End date of reporting period | 9/30/2013 | 1/14/2014 |