Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 65059: 2008-117-00 RUFUS WOODS REDBAND NET PENS
Project Number:
Title:
Rufus Woods Redband Net Pens
Stage:
Closed
Area:
Province Subbasin %
Intermountain Columbia Upper 100.00%
Contract Number:
65059
Contract Title:
2008-117-00 RUFUS WOODS REDBAND NET PENS
Contract Continuation:
Previous: Next:
61175: 2008-117-00 EXP RUFUS WOODS REDBAND NET PENS
Contract Status:
History
Contract Description:
The Colville Tribal Hatchery was built in 1989 and is over 20 years old. It was designed to produce 50,000 pounds of trout annually. Two additional permanent and two temporary raceways were constructed but no improvements or expansion was made to the water system. Consequently, insufficient water and space are available to meet all the diverse stocking requirements of boundary waters, lakes and streams on the Colville Reservation.
Several options for expanding facilities were investigated. It was concluded that the most practical and cost effective option was to contract with a local aquaculture facility to rear additional production and lessen the load on the hatchery and its water system. The primary goal of this project is to supplement hatchery production to assist in meeting resident fish stocking goals. Project provides more harvest opportunities to tribal members for subsistence and ceremonial use and provides a recreational sport fishery fo... r tribal and non-tribal members alike.   
Account Type(s):
Expense
Contract Start Date:
05/01/2014
Contract End Date:
04/30/2015
Current Contract Value:
$252,441
Expenditures:
$252,441

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarker
5 km
3 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing 7 of 7 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A142899165Produce Environmental Compliance DocumentationProduce environmental compliance documentationProduce environmental compliance documentation for BPA$1,5000.59%05/01/201404/30/2015
B142900119Manage and Administer ProjectsManage and Administer ProjectSupervision of the project will include subcontract bid preparation, selection and supervision as well as supplying necessary documentation to BPA.$20,2818.03%05/01/201404/30/2015
C14290166Trap/Collect/Hold/Transport Fish - HatcheryTransport Rainbow Trout (triploid) to Net Pen SiteRainbow Trout are reared, differentially marked at the Colville Tribal Hatchery. A designated population is transported by liberation trucks from the Colville Tribal Hatchery to the Net Pen site. Sub-contractor will be selected to rear fish according to agreed Project Goals and Objectives$8,0003.17%05/01/201407/15/2014
D142902176Produce Hatchery FishRear Rainbow Trout(triploid) in Net PensSelected contractor rears (hatchery provided) rainbow trout (triploid) at local net pen site according to established rearing guidelines. Rearing fish includes: daily feeding, population sub-sampling for weight, density driven split/transfer, mortality removal and accurate record keeping are all performed by the contractor. Fish health will be maintained throughout rearing cycle. A licensed Fish Pathologist is contracted to perform fish health inspections and recommend disease treatments to minimize fish losses. Feeding regime will be adjusted as water temperature vary from a high of 21C to a low of 3 C. Facility will comply with NPDES Standards, Reporting and Monitoring as appropriate.$172,66068.40%05/01/201404/30/2015
E142903176Produce Hatchery FishRear Rainbow Trout (triploid) to 2years of ageSelected contractor rears (hatchery provided) 15,000 held over rainbow trout (triploid) at local net pen site according to established rearing guidelines to two years old. Rearing fish includes: daily feeding, population sub-sampling for weight, density driven split/transfer, mortality removal and accurate record keeping are all performed by the contractor. Fish health will be maintained throughout rearing cycle. A licensed Fish Pathologist is contracted to perform fish health inspections and recommend disease treatments to minimize fish losses. Feeding regime will be adjusted as water temperature vary from a high of 21C to a low of 3 C Facility will comply with NPDES Standards, Reporting and Monitoring as appropriate.$40,00015.85%05/01/201404/30/2015
F142904132Produce Progress (Annual) ReportSubmit Progress Report for the period (May 1, 2013) to (Apr 30,2014)The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole. Date range will be agreed upon by the COTR and the contractor. This may or may not coincide with the contract period. For an ongoing project, a progress report covering a contract period may be submitted under the subsequent contract, if approved by the COTR. Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments. If producing a technical report for this contract, a discrete experiment, or a peer-reviewed publication, use work element 183: Produce Journal Article.$9,0003.57%05/01/201401/31/2015
G142905185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$1,0000.40%07/01/201404/30/2015
      
$252,441
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Produce environmental compliance documentation A: 165. Produce environmental compliance documentation 08/31/2014 08/31/2014
All administrative tasks fulfilled with timely quality products B: 119. Manage and Administer Project 04/30/2015 04/30/2015
Transport Rainbow Trout C: 66. Transport Rainbow Trout (triploid) to Net Pen Site 07/15/2014 05/28/2014
Rear rainbow trout (triploid) in net pens D: 176. Rear Rainbow Trout(triploid) in Net Pens 04/30/2015 04/30/2015
2 year-old Rainbow trout reared and released from net pens E: 176. Rear Rainbow Trout (triploid) to 2years of age 04/30/2015 04/30/2015
Attach Progress Report in Pisces F: 132. Submit Progress Report for the period (May 1, 2013) to (Apr 30,2014) 12/12/2014 03/11/2015

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Trout, Rainbow (Oncorhynchus mykiss)
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce environmental compliance documentation 05/01/2014
B 119 Manage and Administer Project 05/01/2014
C 66 Transport Rainbow Trout (triploid) to Net Pen Site 12/06/2013
D 176 Rear Rainbow Trout(triploid) in Net Pens 12/06/2013
E 176 Rear Rainbow Trout (triploid) to 2years of age 05/01/2014
F 132 Submit Progress Report for the period (May 1, 2013) to (Apr 30,2014) 05/01/2014
G 185 Periodic Status Reports for BPA 05/01/2014