Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 83100: 1995-009-00 EXP LAKE ROOSEVELT RAINBOW TROUT NET PENS
Project Number:
Title:
Lake Roosevelt Rainbow Trout Net Pens
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Columbia Upper 100.00%
Contract Number:
83100
Contract Title:
1995-009-00 EXP LAKE ROOSEVELT RAINBOW TROUT NET PENS
Contract Continuation:
Previous: Next:
80291: 1995-009-00 EXP LAKE ROOSEVELT RAINBOW TROUT NET PENS
  • 86171: 1995-009-00 EXP LAKE ROOSEVELT RAINBOW TROUT NET PENS
Contract Status:
Closed
Contract Description:
The Lake Roosevelt Volunteer Net Pen Program has a primary objective of rearing and releasing 350000 catchable rainbow trout annually with a target of approximately 150,000 fish harvested by anglers each year.  The program helps to mitigate for the loss of salmon in the blocked waters above Grand Coulee Dam.  Using volunteers for work, feeding, and construction of pens helps reduce the cost of this operation.
Account Type(s):
Expense
Contract Start Date:
10/01/2019
Contract End Date:
09/30/2020
Current Contract Value:
$187,210
Expenditures:
$187,210

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Grant
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarker
20 km
10 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jamie Cleveland Bonneville Power Administration Yes COR jacleveland@bpa.gov (503) 230-3160
Lisa Dexter Bonneville Power Administration Yes Contracting Officer lldexter@bpa.gov (503) 230-3893
Laurie Donohue Lake Roosevelt Development Association No Supervisor lakerooseveltda@gmail.com (509) 936-0322
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Tim Peone Spokane Tribe Yes Interested Party timpeone@spokanetribe.com (509) 258-7297
Carolyn Sharp Bonneville Power Administration Yes Env. Compliance Lead casharp@bpa.gov (503) 230-5206
Paul Smith Lake Roosevelt Development Association Yes Contract Manager lrda@centurytel.net (509) 725-2001


Viewing 8 of 8 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A196451165Produce Environmental Compliance DocumentationObtain Necessary PermitsObtain permits to install net pens on Lake Roosevelt from EPA.$7,6874.11%10/01/201909/30/2020
B196452176Produce Hatchery FishRear Fish in Net PensReceive fish from Spokane Tribal Hatchery and Sherman Creek Hatchery and rear triploid rainbow trout in pens located at Hall Creek (6), Hunters (4), Two Rivers (7), Seven Bays (12), Lincoln (12), and Keller Ferry (4). The purpose of the program is to enhance and supplement the Lake Roosevelt fishery by holding the fish during the winter drawdown and refill.$81,48743.53%10/01/201909/30/2020
C19645361Maintain Artificial Production Facility/InfrastructureInsure Operational Net Pen ReadinessComplete all activities related to readiness of net pens for fish.$42,53722.72%10/01/201909/30/2020
D196454174Produce PlanCreate Monthly GuidelineCreate a written monthly guideline of tasks necessary to insure readiness of pens for receiving/rearing hatchery delivered fish.$1,1720.63%10/01/201909/30/2020
E19645599Outreach and EducationLake Roosevelt Fisheries CoordinationLake Roosevelt Fisheries Coordination Team meetings are convened at least twice per year to decide the fish number, species, age, genetic type (diploid/triploid), type of marking, timing, location, etc. that will be transferred to Lake Roosevelt volunteer net pens for rearing followed by release at designated times. In addition the net pen program will participate in Lake Roosevelt Forum activities for school children.$9,7375.20%10/01/201909/30/2020
F196450185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$1,5370.82%01/01/202009/30/2020
G196456132Produce Progress (Annual) ReportSubmit Progress Report for the Period (Oct. 2018 to Sept. 2019)The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole. Date range Oct. 2018 to Sept. 2019 will be agreed upon by the COTR and the contractor. This may or may not coincide with the contract period. For an ongoing project, a progress report covering a contract period may be submitted under the subsequent contract, if approved by the COTR. Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments. If producing a technical report for this contract, a discrete experiment, or a peer-reviewed publication, use work element 183: Produce Journal Article.$2,5661.37%10/01/201901/09/2020
H196457119Manage and Administer ProjectsProject ExecutionCovers work by the contractor to manage on the ground efforts. Also covers administrative work in support of the on the ground efforts and in support of BPA/s programmatic requirements such as metric reporting, financial reporting of accruals, and development of an SOW package including SOW, budget, spending plan, and property inventory.$40,48721.63%10/01/201909/30/2020
      
$187,210
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain Permits A: 165. Obtain Necessary Permits 10/01/2019 10/01/2019
Rear/Release 350,000 Rainbow Trout B: 176. Rear Fish in Net Pens 06/06/2020 06/05/2020
Maintain Operation/Safety of Net Pens C: 61. Insure Operational Net Pen Readiness 09/30/2020 09/30/2020
Attach Guideline to Pisces Report D: 174. Create Monthly Guideline 09/30/2020 09/30/2020
Coordinate with those in Umbrella Program E: 99. Lake Roosevelt Fisheries Coordination 09/30/2020 09/30/2020
Completed Annual Report G: 132. Submit Progress Report for the Period (Oct. 2018 to Sept. 2019) 01/09/2020 01/09/2020
Effective implementation management and timely contract administration H: 119. Project Execution 09/30/2020 09/30/2020

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Necessary Permits
B 176 Rear Fish in Net Pens 10/01/2019
C 61 Insure Operational Net Pen Readiness 10/01/2019
D 174 Create Monthly Guideline 10/01/2019
E 99 Lake Roosevelt Fisheries Coordination
F 185 Periodic Status Reports for BPA
G 132 Submit Progress Report for the Period (Oct. 2018 to Sept. 2019)
H 119 Project Execution