Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 88873: 1995-009-00 EXP LAKE ROOSEVELT RAINBOW TROUT NET PENS
Project Number:
Title:
Lake Roosevelt Rainbow Trout Net Pens
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Columbia Upper 100.00%
Contract Number:
88873
Contract Title:
1995-009-00 EXP LAKE ROOSEVELT RAINBOW TROUT NET PENS
Contract Continuation:
Previous: Next:
86171: 1995-009-00 EXP LAKE ROOSEVELT RAINBOW TROUT NET PENS
  • 90960: 1995-009-00 EXP LAKE ROOSEVELT RAINBOW TROUT NET PENS
Contract Status:
Closed
Contract Description:
This project addresses losses of anadromous fish and sustainable resident fisheries in Lake Roosevelt caused by the Federal Columbia River Power System (FCRPS).  The Lake Roosevelt Rainbow Trout Net Pen Project is one of four aquaculture projects forming the Lake Roosevelt Hatcheries Program (LRHP).  The project is managed by a coordinator, assistant and volunteers of the Lake Roosevelt Development Association. Associated LRHP projects include the Sherman Creek and Ford Trout Hatcheries, operated by the Washington Department of Fish & Wildlife, and the Spokane Tribal Hatchery operated by the Spokane Tribe of Indians.  Collectively, the LRHP program is tasked with producing triploid rainbow trout to support a segregated harvest program for Tribal subsistence and sport fisheries.  Annual production and release strategies are decided by the Lake Roosevelt Hatcheries Coordination Team (LRHCT), a group comprised of...  fisheries staff from the Spokane Tribe, Colville Confederated Tribes and Washington Department of Fish and Wildlife.  The LRHCT utilizes recommendations from the Lake Roosevelt Data Collection Program, the project tasked with monitoring and evaluating performance of LRHP releases.  Decisions are made in accordance with strategies outlined in the Lake Roosevelt Fisheries Guiding Document (LRGD), a living document developed by co-managers with a logic path to adapt to new circumstances and connect the various Lake Roosevelt fisheries project goals for fisheries protection, restoration, and enhancement.  While hatchery rainbow trout production consistently meets harvest objectives, project sponsors plan to add more emphasis on producing rainbow trout suited to meet the programs mitigation goals and objectives.  The Lake Roosevelt Net Pen Project is funded by Bonneville Power Administration under provisional requirements of the 1980 Northwest Power Planning and Conservation Act.     
Account Type(s):
Expense
Contract Start Date:
10/01/2021
Contract End Date:
09/30/2022
Current Contract Value:
$187,210
Expenditures:
$187,210

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Grant
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarker
20 km
10 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration Yes Contracting Officer dxaffonso@bpa.gov (503) 230-5918
James Barron Bonneville Power Administration Yes COR jmbarron@bpa.gov (503) 230-5706
Laurie Donohue Lake Roosevelt Development Association No Supervisor lakerooseveltda@gmail.com (509) 936-0322
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jennifer McKenna Bonneville Power Administration No CO Assistant jmmckenna@bpa.gov (503) 314-8915
Tim Peone Spokane Tribe Yes Interested Party timpeone@spokanetribe.com (509) 258-7297
Carolyn Sharp Bonneville Power Administration Yes Env. Compliance Lead casharp@bpa.gov (503) 230-5206
Paul Smith Lake Roosevelt Development Association Yes Contract Manager lrda@centurytel.net (509) 725-2001


Viewing 8 of 8 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A219652165Produce Environmental Compliance DocumentationObtain Necessary PermitsObtain permits to install net pens on Lake Roosevelt from EPA.$7,6874.11%10/01/202109/30/2022
B219653176Produce Hatchery FishRear Fish in Net PensReceive fish from Spokane Tribal Hatchery and Sherman Creek Hatchery and rear triploid rainbow trout in pens located at Hall Creek (6), Hunters (4), Two Rivers (7), Seven Bays (12), Lincoln (12), and Keller Ferry (4). The purpose of the program is to enhance and supplement the Lake Roosevelt fishery by holding the fish during the winter draw down and refill.$81,48743.53%10/01/202106/06/2022
C21965461Maintain Artificial Production Facility/InfrastructureInsure Operational Net Pen ReadinessComplete all activities related to readiness of net pens for fish.$42,53722.72%10/01/202109/30/2022
D219655174Produce PlanCreate Monthly GuidelineCreate a written monthly guideline of tasks necessary to insure readiness of pens for receiving/rearing hatchery delivered fish.$1,1720.63%10/01/202109/30/2022
E21965699Outreach and EducationLake Roosevelt Fisheries CoordinationLake Roosevelt Fisheries Coordination Team meetings are convened at least twice per year to decide the fish number, species, age, genetic type (diploid/triploid), type of marking, timing, location, etc. that will be transferred to Lake Roosevelt volunteer net pens for rearing followed by release at designated times. In addition the net pen program will participate in Lake Roosevelt Forum activities for school children.$9,7375.20%10/01/202109/30/2022
F219651185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$1,5370.82%01/01/202209/30/2022
G219657132Produce Progress (Annual) ReportSubmit Progress Report for the Period (Oct. 2020 to Sept. 2021)The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole. Date range Oct. 2020 to Sept. 2021 will be agreed upon by the COTR and the contractor. This may or may not coincide with the contract period. For an ongoing project, a progress report covering a contract period may be submitted under the subsequent contract, if approved by the COTR. Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments. If producing a technical report for this contract, a discrete experiment, or a peer-reviewed publication, use work element 183: Produce Journal Article.$2,5661.37%10/01/202102/28/2022
H219658119Manage and Administer ProjectsProject ExecutionCovers work by the contractor to manage on the ground efforts. Also covers administrative work in support of the on the ground efforts and in support of BPA/s programmatic requirements such as metric reporting, financial reporting, and development of an SOW package including SOW, budget, and property inventory.$40,48721.63%10/01/202109/30/2022
      
$187,210
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain Permits A: 165. Obtain Necessary Permits 09/30/2022 09/30/2022
Rainbow Trout Net Pen Rearing and Release B: 176. Rear Fish in Net Pens 06/06/2022 05/18/2022
Maintain Operation/Safety of Net Pens C: 61. Insure Operational Net Pen Readiness 09/30/2022 09/30/2022
Attach Guideline to Pisces Report D: 174. Create Monthly Guideline 09/30/2022 09/30/2022
Coordinate with those in Umbrella Program E: 99. Lake Roosevelt Fisheries Coordination 09/30/2022 09/30/2022
Completed Annual Report G: 132. Submit Progress Report for the Period (Oct. 2020 to Sept. 2021) 02/28/2022 02/28/2022
Manage Contract Administration H: 119. Project Execution 09/30/2022 09/30/2022

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Necessary Permits
B 176 Rear Fish in Net Pens 08/04/2021
C 61 Insure Operational Net Pen Readiness 08/04/2021
D 174 Create Monthly Guideline 08/04/2021
E 99 Lake Roosevelt Fisheries Coordination
F 185 Periodic Status Reports for BPA
G 132 Submit Progress Report for the Period (Oct. 2020 to Sept. 2021)
H 119 Project Execution