2007-216-00 PNAMP REVIEW, DESIGN & PROTOCOL DEVELOPMENT
Contract Start Date:
5/15/2007
Contract End Date:
9/30/2007
Title:
D: 156 - Develop process to provide regional recommendations for TTM protocols Phase 1 of 3
Description:
Objective 4: Final Report to BPA and PNAMP with proposed FY08 and FY09 SOW.

A single final report that documents all discussion, decisions, meeting notes, active participants, subcommittee members, reviewers and review process and participating groups, and PNAMP approval to proceed to Phase II process. Report will also include a scope of work, product(s), timelines, goals, objectives and budget to complete the final project.

Task 4.1 Phase I Report

Work Elements: Fish Population Monitoring WG TTM Guidance project report & FY 08-09 work plan
WE Agreement Type:
Contracted
Deliverable Specification:
A single final report that documents all discussion, decisions, meeting notes, active participants, subcommittee members, reviewers and review process and participating groups, and PNAMP approval to proceed to Phase II process. Report will also include a scope of work, product(s), timelines, goals, objectives and budget to complete the final project.
WSE Effective Budget:
$2,212
% of Total WSE Effective Budget:
11.22%
WSE Start:
05/24/2007
WSE End:
09/30/2007
WSE Completion:
09/30/2007
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $2,212 $2,212

2 Milestones
Sort Type Title Start End Status Modified By Modified Date
A Final FY 07 Report to include FY 08-09 scope of work, product(s) etc. 5/24/2007 9/30/2007 Concluded Tracey Yerxa (Inactive) 5/3/2007 9:50:43 AM
Description: Objective 4: Final Report to BPA and PNAMP with proposed FY08 and FY09 SOW. Task 4.1 Phase I Report Fish Population Monitoring WG TTM Guidance project report FY 08-09 work plan
B DELIV Final Report to BPA and PNAMP with proposed FY08 and FY09 SOW 9/30/2007 Concluded Tracey Yerxa (Inactive) 5/3/2007 9:55:58 AM
Description: A single final report that documents all discussion, decisions, meeting notes, active participants, subcommittee members, reviewers and review process and participating groups, and PNAMP approval to proceed to Phase II process. Report will also include a scope of work, product(s), timelines, goals, objectives and budget to complete the final project.

Implementation Metrics
None

This work element does not require Focal Species
Study Plan Name Study Plan Owner Protocol State Sample Design Name
BPA Fish and Wildlife Program Monitoring v1.0 Russell Scranton Draft

N/A

N/A