This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $1,000 | $1,000 | PISCES Reporting serves this requirement |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | NonT1 | Review progress report format requirements | 4/1/2013 | 4/30/2013 | Concluded | Susan Offerdal (Inactive) | 1/11/2013 4:20:31 PM |
Description: Contractor must review formatting requirements before starting the first draft of their report. Please follow the BPA-required format. https://efw.bpa.gov/IntegratedFWP/technicalreports.aspx | |||||||
B | NonT3 | Submit progress report for internal contractor review | 6/3/2013 | 6/28/2013 | Concluded | Susan Offerdal (Inactive) | 1/11/2013 4:20:31 PM |
Description: Use this milestone if the annual report requires an internal review before being reviewed externally. Make sure to allow for both technical and policy reviews if necessary. | |||||||
C | IntRev | Submit progress report for external review | 7/1/2013 | 7/1/2013 | Concluded | Susan Offerdal (Inactive) | 1/11/2013 4:20:31 PM |
Description: Use this milestone if the progress report requires external review. | |||||||
D | DELIV | Confirm BPA has posted the progress report | 8/15/2013 | 8/15/2013 | Concluded | Susan Offerdal (Inactive) | 1/11/2013 4:20:31 PM |
Description: It usually takes BPA 30-45 days to post the final version of a report. This milestone's end date should therefore be 45 days after the Deliverable milestone. You will receive an email from BPA confirming that your report has been finalized and posted to the web. | |||||||
E | DELIV | Attach Annual Progress Report in Pisces | 7/1/2013 | Concluded | Susan Offerdal (Inactive) | 1/11/2013 4:20:31 PM | |
Description: Use the attachment tab in Pisces to attach your progress report. Progress reports attached in Pisces will be posted on the web. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1768. Start date of reporting period | 4/1/2012 | 4/1/2012 | |||
1769. End date of reporting period | 3/31/2013 | 3/31/2013 |