This contract view shows expenditures by fiscal year, and provides various views of estimated expenditures. All expenditures data includes accruals and are based on data through 28-Feb-2025. Work Statement Element data is current through 04/05/2025. This page offers a handful of data grids that provide breakdowns of estimated contract expenditures. The data in these grids form the basis of various 'Spending by ...' reports available from the Budget & Expenditure Reports page.
This grid lists expenditures by fiscal year, and provides a breakdown of estimated expenditures by work classification, which are determined using the work element budget ratios from statements of work.
2013 | Expense | $40,000 | $6,076 | $8,476 | $0 | $0 | $0 | $5,849 | $0 | $0 | $0 | $228 |
2012 | Expense | $40,000 | $33,924 | $31,524 | $0 | $0 | $0 | $32,651 | $0 | $0 | $0 | $1,272 |
Estimated Expenditures by Work Statement Element - this grid lists estimated expenditures by work statement element. Estimates are determined using work statement element effective budget ratios.
2013 | Expense | 74081 | 185 | A: Periodic Status Reports for BPA | $500 | 1.25% | $76 | 07/01/2012 | 02/28/2013 | Concluded | Reporting | |
2013 | Expense | 74083 | 191 | B: Entiat IMW Coordination by All-Things-Entiat personnel | $30,000 | 75.00% | $4,557 | 03/01/2012 | 02/28/2013 | Concluded | Planning and Coordination | |
2013 | Expense | 74084 | 99 | C: Wenatchee and Entiat CHaMP Status and Trend Monitoring Outreach | $7,500 | 18.75% | $1,139 | 04/15/2012 | 10/28/2012 | Concluded | Planning and Coordination | |
2013 | Expense | 74085 | 119 | D: Manager and Administer Contract | $1,000 | 2.50% | $152 | 09/01/2012 | 02/28/2013 | Concluded | Planning and Coordination | |
2013 | Expense | 74086 | 132 | E: Submit CCD final (annual) report for the period of performance | $1,000 | 2.50% | $152 | 11/01/2012 | 02/28/2013 | Concluded | Reporting | |
2012 | Expense | 74081 | 185 | A: Periodic Status Reports for BPA | $500 | 1.25% | $424 | 07/01/2012 | 02/28/2013 | Concluded | Reporting | |
2012 | Expense | 74083 | 191 | B: Entiat IMW Coordination by All-Things-Entiat personnel | $30,000 | 75.00% | $25,443 | 03/01/2012 | 02/28/2013 | Concluded | Planning and Coordination | |
2012 | Expense | 74084 | 99 | C: Wenatchee and Entiat CHaMP Status and Trend Monitoring Outreach | $7,500 | 18.75% | $6,361 | 04/15/2012 | 10/28/2012 | Concluded | Planning and Coordination | |
2012 | Expense | 74085 | 119 | D: Manager and Administer Contract | $1,000 | 2.50% | $848 | 09/01/2012 | 02/28/2013 | Concluded | Planning and Coordination | |
2012 | Expense | 74086 | 132 | E: Submit CCD final (annual) report for the period of performance | $1,000 | 2.50% | $848 | 11/01/2012 | 02/28/2013 | Concluded | Reporting |
Estimated Expenditures by Focal Species - this grid lists estimated expenditures by primary focal species. Allocations to primary focal species are done according to work statement element effective budget ratios.
2012 | Expense | $0 | $0 | |
2013 | Expense | $0 | $0 |
Estimated Expenditures by ESA-Listed Focal Species - this grid lists estimated expenditures by primary focal species for ESA-Listed focal species only. If this contract does not have any work statement elements where the primary focal species is an ESA-listed species, then this grid will be empty.
2012 | Expense | $0 | $0 | |
2013 | Expense | $0 | $0 |
Estimated Expenditures by Work Statement Element by Focal Species - this grid lists estimated expenditures by work statement element and by primary focal species. Allocations to primary focal species are done according to work statement element effective budget ratios.
2012 | Expense | 74084 | C: Wenatchee and Entiat CHaMP Status and Trend Monitoring Outreach | $0 | $0 | |
2012 | Expense | 74086 | E: Submit CCD final (annual) report for the period of performance | $0 | $0 | |
2013 | Expense | 74086 | E: Submit CCD final (annual) report for the period of performance | $0 | $0 | |
2013 | Expense | 74084 | C: Wenatchee and Entiat CHaMP Status and Trend Monitoring Outreach | $0 | $0 | |
2012 | Expense | 74081 | A: Periodic Status Reports for BPA | $0 | $0 | |
2013 | Expense | 74081 | A: Periodic Status Reports for BPA | $0 | $0 | |
2012 | Expense | 74085 | D: Manager and Administer Contract | $0 | $0 | |
2012 | Expense | 74083 | B: Entiat IMW Coordination by All-Things-Entiat personnel | $0 | $0 | |
2013 | Expense | 74085 | D: Manager and Administer Contract | $0 | $0 | |
2013 | Expense | 74083 | B: Entiat IMW Coordination by All-Things-Entiat personnel | $0 | $0 |
Estimated Expenditures by Work Statement Element by ESA-Listed Focal Species - this grid lists estimated expenditures by work statement element and by primary focal species for ESA-Listed focal species only. If this contract does not have any work statement elements where the primary focal species is an ESA-listed species, then this grid will be empty.
2013 | Expense | 74083 | B: Entiat IMW Coordination by All-Things-Entiat personnel | $0 | $0 | |
2013 | Expense | 74085 | D: Manager and Administer Contract | $0 | $0 | |
2012 | Expense | 74083 | B: Entiat IMW Coordination by All-Things-Entiat personnel | $0 | $0 | |
2012 | Expense | 74085 | D: Manager and Administer Contract | $0 | $0 | |
2013 | Expense | 74081 | A: Periodic Status Reports for BPA | $0 | $0 | |
2012 | Expense | 74081 | A: Periodic Status Reports for BPA | $0 | $0 | |
2013 | Expense | 74084 | C: Wenatchee and Entiat CHaMP Status and Trend Monitoring Outreach | $0 | $0 | |
2013 | Expense | 74086 | E: Submit CCD final (annual) report for the period of performance | $0 | $0 | |
2012 | Expense | 74084 | C: Wenatchee and Entiat CHaMP Status and Trend Monitoring Outreach | $0 | $0 | |
2012 | Expense | 74086 | E: Submit CCD final (annual) report for the period of performance | $0 | $0 |
Estimated Expenditures by Work Statement Element by Location - this grid lists estimated expenditures by work statement element and, using the primary work site location, allocates these estimated expenditures to individual Counties, States, Subbasins and Provinces.