SOW Report
Contract 49324: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-CUSTER
Project Number:
Title:
Pahsimeroi River Habitat
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
49324
Contract Title:
2008-603-00 EXP PAHSIMEROI RIVER HABITAT-CUSTER
Contract Continuation:
Previous: Next:
44134: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-MOA
  • 57289: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-CUSTER
Contract Status:
Closed
Contract Description:
This project is an expansion of the existing project 2007-268-000 and was identified early in the BPA State of Idaho MOA process as a high priority for inclusion.  Both the IDF&G and the draft NOAAF recovery plans highlight the importance of carrying out habitat actions to assist this key salmon population.

The Pahsimeroi River has a unique population of Snake River Chinook salmon, and in contrast with the Lemhi River and East Fork of the Salmon River watersheds, the salmon population in the Pahsimeroi River is a later migrating summer-run Chinook salmon rather than spring-run. Historically, spawning and rearing habitat was probably supported within the watershed for at least two federally –listed anadromous fish species, spring/summer Chinook salmon, and steelhead. (P. Murphy, 2008)  

The Upper Salmon Watershed Project Technical Team, including IDFG Anadromous Fish Screen Program and Regional Fishery Management...  has prioritized the lower Pahsimeroi River and its major tributary, Patterson/Big Springs Creek, as SHIPUSS Priority I streams. Those are tributaries and river reaches that have the potential to realize immediate, tangible benefits to fish if recovery efforts are directed toward them. Goals in the lower Pahsimeroi River and Patterson/Big Springs Creek are to enhance migration in both streams by increasing flow regimes and reestablishing habitat connectivity to unused stream reaches. Mechanisms for attaining these goals focus on diversion consolidations and removal/alterations of diversions hindering fish passage. (P. Murphy, 2008)  

At the request of the Idaho Governor’s Office of Species Conservation (OSC) a technical panel with knowledge and expertise of project opportunities within the Pahsimeroi. This team included Paddy Murphy (Fisheries Biologist), Eric Leitzinger, Larry Weeks, Lynn Stratton and Jim Lukins, Idaho Department of Fish and Game, Morgan Case and Helen Herrington, Idaho Department of Water Resources, Mark Olson, Natural Resources Conservation Service, Brian Hamilton, Bureau of Reclamation, Mark Davidson, TNC, Clif Tipton, Bureau of Land Management Fisheries Biologist, Mike Edmondson, OSC and Karma Bragg, Custer Soil and Water Conservation Service. This core team identified the areas of Pahsimeroi with most potential for fisheries enhancement and recovery within the middle Pahsimeroi. Additional support and input is provided by the Custer Soil and Water Conservation District Board of Supervisors. The projects were predominantly in Patterson/Big Springs Creek. Patterson/Big Springs Creek is a very important tributary for spawning and rearing of the unique population of Chinook salmon found in the Pahsimeroi.

Reconnection of Duck Creek, increased flows within Patterson/Big Springs Creek with a focus on the lower five irrigation diversions (PBSC 1-5). This includes flow enhancements on PBSC #1,  #9  and work to close P-13 Diversion. These projects were prioritized as projects that could be implemented within the next eighteen months. Work reflected in this statement of work is for PBSC #1 and PBSC #9 in addition to final work to complete the lower Pahsimeroi Fencing project and willow planting and re-hab on the IDFG property.
  
Account Type(s):
Expense
Contract Start Date:
10/16/2010
Contract End Date:
04/30/2012
Current Contract Value:
$1,279,682
Expenditures:
$1,279,682

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarker
20 km
10 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing 15 of 15 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A97629165Produce Environmental Compliance DocumentationProduce EC documents on identified projectsProvide environmental consultation documents to include, but not limited to draft biological assessment, HIP II, cultural surveys and/or permits on PBSC #1 water conservation project and PBSC #9 diversion closure and irrigation project. The EC on the IDFG re-habilitation project and willow planning on IDFG property and lower Pahsimeroi Fence was completed in last year's contract.$7,0000.55%10/18/201010/29/2011
B97630175Produce DesignProduce Design and/or SpecificationsFunds for this work element are intended to cost share with the NRCS for a staff position in Challis that will direct focus on BPA funded projects for the design, cultural surveys, construction specifications, construction certification and overall assistance with these projects. This will address projects currently in this FY project and those being developed for future FY contracts.$21,6001.69%10/01/201004/20/2012
C97631150Install SprinklerInstall irrigation system to provide water conservation on PBSC 1Install Sprinklers on property being irrigated from Patterson/Big Springs Creek #1 to provide opportunity for a water agreement providing 5 cfs to go past the last point of diversion on PBSC and into the Pahsimeroi.$414,00032.44%10/18/201004/27/2012
D97632150Install SprinklerInstall Sprinkler to allow closure of the PBSC #9 Ditch and DiversionInstall Sprinklers on property being irrigated from Patterson/Big Springs Creek #9 to provide opportunity to close the PBSC #9 Ditch and Diversion.$200,77315.73%10/16/201004/27/2012
E9763340Install FenceInstall fence on lower PahsimeroiMaterials for approximately 8000 feet of fence along property in the lower portion of the Pahsimeroi will have been purchased from contract #44134. Additional footage is necessary to complete this project and sea up the lower portion of the Pahsimeroi. Project funding from BPA will cost share on the materials for the fence. Landowner will cover costs to construct the fence. Some costs associated with preparation of the fence line may require some level of cost share.$5,8800.46%06/01/201109/15/2011
F9763422Maintain VegetationMaintain and Continue plantings on IDFG Easement PropertyGround prep and plantings will have been completed under contract #44134. This work element will determine success and either re-plant or maintain work completed in the previous contract.$2,2000.17%10/18/201008/31/2011
G97635119Manage and Administer ProjectsManage and administer projects within this contractProvide project management to improve water delivery and enhance flows from Patterson Big Springs Creek and the Pahsimeroi. This included but is not limited to project identification and prioritization, project management, oversight of environmental compliance, coordination with IDWR, guidance of bid process and tasks associated with project management. A project list has been identified within the working group that includes IDFG Screen Shop, TNC, NRCS and BOR. This list is provided as an attachment in this SOW. Projects in development and waiting written approval from DFG Screen Shop, BPA and OSC include but are not limited to the closure of Patterson/Big Springs Creek 9, Water Conservation Project on PBSC #1 and diversion closure of P-13 and diversion improvements above Furey Lane.$24,5791.93%10/18/201004/30/2012
H97636132Produce Progress (Annual) ReportSubmit Progress Report for the period Oct 10 thru Sept 11The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole. Date range Oct 09 thru Sept 11 will be agreed upon by the COTR and the contractor. This may or may not coincide with the contract period. For an ongoing project, a progress report covering a contract period may be submitted under the subsequent contract, if approved by the COTR. Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments. If producing a technical report for this contract, a discrete experiment, or a peer-reviewed publication, use work element 183: Produce Journal Article.$1,0000.08%06/01/201104/13/2012
I97637185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$1,5000.12%01/01/201104/30/2012
J97638184Install Fish Passage StructureRemove culverts/passage barriers on Patterson/Big Springs Creek on Hooper LaneHooper Lane cuts across the Pahsimeroi Valley approximately 13 miles upstream from the mouth of the Pahsimeroi River. There are 4 culvert crossings on the road that are currently undersized, and can restrict fish passage at certain flows. These culverts carry Big Springs Creek, Big Springs, Connector Channel, Little Springs Creek, and Pahsimeroi River flows. Replacing these culverts will improve passage to the upstream ends of these drainages for juvenile Chinook salmon, steelhead, and other native species. Replacement of the 4 culverts with bridges, originally suggested by Idaho Fish and Game biologists, was ranked by the Upper Salmon Basin Watershed Program Tech Team in December of 2010. The project scored 76, which is a "high" ranking. US Bureau of Reclamation has completed designs for the bridges. The project is being coordinated through the Custer Soil and Water Conservation District (CSWCD), the Custer County Road Department, and the Lemhi County Road Department. Reclamation will provide construction oversight, and CSWCD will act as the contract officer. Construction is planned for July/August of 2011.$155,71012.20%04/08/201109/30/2011
K97639184Install Fish Passage StructureRemove culverts/passage barriers on Patterson/Big Springs Creek Connector Channel on Hooper LaneHooper Lane cuts across the Pahsimeroi Valley approximately 13 miles upstream from the mouth of the Pahsimeroi River. There are 4 culvert crossings on the road that are currently undersized, and can restrict fish passage at certain flows. These culverts carry Big Springs Creek, Big Springs connection ditch, Little Springs Creek, and Pahsimeroi River flows. Replacing these culverts will improve passage to the upstream ends of these drainages for juvenile Chinook salmon, steelhead, and other native species. Replacement of the 4 culverts with bridges, originally suggested by Idaho Fish and Game biologists, was ranked by the Upper Salmon Basin Watershed Program Tech Team in December of 2010. The project scored 76, which is a "high" ranking. US Bureau of Reclamation has completed designs for the bridges. The project is being coordinated through the Custer Soil and Water Conservation District (CSWCD), the Custer County Road Department, and the Lemhi County Road Department. Reclamation will provide construction oversight, and CSWCD will act as the contract officer. Construction is planned for July/August of 2011.$129,30010.13%04/08/201109/30/2011
L97640184Install Fish Passage StructureRemove culverts/passage barriers on Patterson Little Spring Creek on Hooper LaneHooper Lane cuts across the Pahsimeroi Valley approximately 13 miles upstream from the mouth of the Pahsimeroi River. There are 4 culvert crossings on the road that are currently undersized, and can restrict fish passage at certain flows. These culverts carry Big Springs Creek, Big Springs connection ditch, Little Springs Creek, and Pahsimeroi River flows. Replacing these culverts will improve passage to the upstream ends of these drainages for juvenile Chinook salmon, steelhead, and other native species. Replacement of the 4 culverts with bridges, originally suggested by Idaho Fish and Game biologists, was ranked by the Upper Salmon Basin Watershed Program Tech Team in December of 2010. The project scored 76, which is a "high" ranking. US Bureau of Reclamation has completed designs for the bridges. The project is being coordinated through the Custer Soil and Water Conservation District (CSWCD), the Custer County Road Department, and the Lemhi County Road Department. Reclamation will provide construction oversight, and CSWCD will act as the contract officer. Construction is planned for July/August of 2011.$130,20510.20%04/08/201109/30/2011
M97641184Install Fish Passage StructureRemove culverts/passage barriers on Pahsimeroi on Hooper LaneHooper Lane cuts across the Pahsimeroi Valley approximately 13 miles upstream from the mouth of the Pahsimeroi River. There are 4 culvert crossings on the road that are currently undersized, and can restrict fish passage at certain flows. These culverts carry Big Springs Creek, Big Springs connection ditch, Little Springs Creek, and Pahsimeroi River flows. Replacing these culverts will improve passage to the upstream ends of these drainages for juvenile Chinook salmon, steelhead, and other native species. Replacement of the 4 culverts with bridges, originally suggested by Idaho Fish and Game biologists, was ranked by the Upper Salmon Basin Watershed Program Tech Team in December of 2010. The project scored 76, which is a "high" ranking. US Bureau of Reclamation has completed designs for the bridges. The project is being coordinated through the Custer Soil and Water Conservation District (CSWCD), the Custer County Road Department, and the Lemhi County Road Department. Reclamation will provide construction oversight, and CSWCD will act as the contract officer. Construction is planned for July/August of 2011.$161,71012.67%04/08/201109/30/2011
N9764285Remove/Breach Fish Passage BarrierRemove two culverts on Muddy Springs and replace with bottomless culvertsRemove two culverts along the Lower Muddy Springs to improve fish passage in that reach of the stream.$15,8401.24%05/01/201109/30/2011
O9764399Outreach and EducationCoordinate with Agencies and Contractors to complete a training for In-Stream Work WindowsCH2M HILL will conduct a one-day workshop for IDFG, other agency staff and contractors in Salmon, Idaho. The goal of the workshop is to discuss issues relating to in water construction of culvert installations/replacements (I/Rs), headgate I/R’s, bridge I/R’s, road construction, as well as restoration and habitat improvement projects in the State of Idaho. Topics will include best management practices for sediment control, channel diversion, rip rap, permitting, erosion control methods, water control during construction, and re-establishment of vegetation. CH2M HILL will present recent lessons learned on projects similar to those conducted by IDFG. As part of the workshop, CH2M HILL will provide attendees with a binder summarizing the workshop topics, and a laminated Best Management Practice (BMP) “quick reference” card for construction personnel to carry on project sites.$4,8000.38%04/15/201105/06/2011
      
$1,276,097
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain or complete Environmental consultation documents and provide to BPA A: 165. Produce EC documents on identified projects 08/01/2011 07/08/2011
Produce Design and/or Specifications B: 175. Produce Design and/or Specifications 08/31/2011 08/19/2011
Install Sprinklers to provide water savings in Patterson/Big Sprigs Creek from POD to Pahsimeroi C: 150. Install irrigation system to provide water conservation on PBSC 1 04/27/2012 04/16/2012
Install irrigation system to allow for the closure of the PBSC #9 Ditch and Diversion D: 150. Install Sprinkler to allow closure of the PBSC #9 Ditch and Diversion 04/27/2012 04/16/2012
Installation of 9800 feet of fence to be completed on the Lower Pahsimeroi E: 40. Install fence on lower Pahsimeroi 09/15/2011 06/30/2011
Maintain and/or re-plant vegetation on IDFG easement property F: 22. Maintain and Continue plantings on IDFG Easement Property 08/31/2011 08/30/2011
Installation of projects yet to be identified and approved. G: 119. Manage and administer projects within this contract 04/30/2012 04/30/2012
Attach Progress Report in Pisces H: 132. Submit Progress Report for the period Oct 10 thru Sept 11 04/13/2012
Remove culverts/passage barriers on Patterson/Big Springs Creek at Hooper Lane i J: 184. Remove culverts/passage barriers on Patterson/Big Springs Creek on Hooper Lane 09/30/2011 09/16/2011
Remove culverts/passage barriers on Patterson/Big Springs Creek Connector Channel at Hooper Lane K: 184. Remove culverts/passage barriers on Patterson/Big Springs Creek Connector Channel on Hooper Lane 09/30/2011 09/16/2011
Remove culverts/passage barriers on Patterson Little Spring Creek at Hooper Lane L: 184. Remove culverts/passage barriers on Patterson Little Spring Creek on Hooper Lane 09/30/2011 09/16/2011
Remove culverts/passage barriers on Pahsimeroi at Hooper Lane M: 184. Remove culverts/passage barriers on Pahsimeroi on Hooper Lane 09/30/2011 09/16/2011
Remove two culverts and replace with bottomless arch bridges. N: 85. Remove two culverts on Muddy Springs and replace with bottomless culverts 09/30/2011 09/02/2011
One day workshop provided by CH2M Hill in cooperation with OSC and USBoR facilitated by IDFG O: 99. Coordinate with Agencies and Contractors to complete a training for In-Stream Work Windows 05/06/2011 04/19/2011

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 4 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 150 Install Sprinkler
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 4 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 150 Install Sprinkler

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce EC documents on identified projects 10/01/2010
B 175 Produce Design and/or Specifications 10/01/2010
C 150 Install irrigation system to provide water conservation on PBSC 1 07/17/2011
D 150 Install Sprinkler to allow closure of the PBSC #9 Ditch and Diversion 07/17/2011
E 40 Install fence on lower Pahsimeroi 10/01/2010
F 22 Maintain and Continue plantings on IDFG Easement Property 10/01/2010
G 119 Manage and administer projects within this contract 10/01/2010
H 132 Submit Progress Report for the period Oct 10 thru Sept 11 10/01/2010
I 185 Periodic Status Reports for BPA 10/01/2010
J 184 Remove culverts/passage barriers on Patterson/Big Springs Creek on Hooper Lane 07/11/2011
K 184 Remove culverts/passage barriers on Patterson/Big Springs Creek Connector Channel on Hooper Lane 07/11/2011
L 184 Remove culverts/passage barriers on Patterson Little Spring Creek on Hooper Lane 07/11/2011
M 184 Remove culverts/passage barriers on Pahsimeroi on Hooper Lane 07/11/2011
N 85 Remove two culverts on Muddy Springs and replace with bottomless culverts 10/16/2010
O 99 Coordinate with Agencies and Contractors to complete a training for In-Stream Work Windows 10/16/2010