Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 78986: 2001-032-00 EXP HANGMAN CREEK FISHERIES
Project Number:
Title:
Coeur D'Alene Fisheries Enhancement-Hangman Creek
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Spokane 100.00%
Contract Number:
78986
Contract Title:
2001-032-00 EXP HANGMAN CREEK FISHERIES
Contract Continuation:
Previous: Next:
75767: 2001-032-00 EXP HANGMAN CREEK FISHERIES
  • 82051: 2001-032-00 EXP HANGMAN CREEK FISHERIES
Contract Status:
Closed
Contract Description:
The Scope of Work and budget presented in this document represent the activities associated with the Coeur 'd Alene Tribe's resident fish enhancement project on Hangman Creek within the Spokane Sub-basin corresponding to the contract period May 1, 2018 to April 30, 2019.  Total amount of this budget request is $359,000  The Coeur d'Alene Tribe has requested that BPA transfer $51,900 dollars from funds available to BPA project #199004400 to Project #200103200  in order to meet the Tribe's restoration priorities.

Ongoing objectives include:
o Determine areas that are in need of restoration to supply spawning and rearing habitat for Redband and other naturally reproducing trout.
o Support an educational outreach program to facilitate a “holistic watershed protection process managed thru BPA Project #199004400.
o Implement a habitat/in-stream restoration strategy that will provide self-sustaining, naturall... y reproducing, and harvestable populations of native trout.
o Implement a monitoring and evaluation program to determine the effectiveness of habitat/in-stream restoration project.


The Hangman Creek watershed has experienced land use changes that have resulted in degraded in-stream habitat for fish and other aquatic species.  Conserving habitats in the upper tributaries is a priority along with increasing fish distribution and reconnecting fragmented populations. A primary method of accomplishing habitat enhancement is to enlist beaver in a holistic strategy to address multiple ecological and hydrologic process deficiencies. Beaver influenced channel and floodplain morphology and vegetation historically, but alteration of their habitat and trapping have substantially reduced their influence and the ability for their populations to rebound.  The absence of large wood to serve as foundations for dams and impacts to the availability of suitable dam-building material in the riparian zone have influenced the resilience of beaver dams currently.  If conditions could be made more favorable for their re-establishment, it is likely that channel conditions and in-stream habitat could be restored to a more desired state, thereby restoring fish habitat, the riparian zone, and the floodplain in the process.

The following work will facilitate measured progress toward achieving the objectives for the project during this scope of work:
      
1) Implementing restoration designs for utilizing beaver as a partner in restoring natural hydrologic function, overbank flow, and connection between streams and riparian habitats.
An EPA grant awarded as an $80,000 cost share will supply plant materials for WEs E, F, G and H in the form of willow cuttings and large deciduous potted plants.
WE I will provide a temporary source of food and building materials for beaver by providing clippings at key locations with active beaver colonies.

New restoration work elements include:
WE D - Reactivation of historic channel alignments in lower Sheep Creek.
WE J  - Bank stabilization in Phase 2 of the k'wne' 'ulchiyark'wmtsut Project, using bioengineering.
WE K - Construction of 4,000 feet of wildlife exclusion fencing to minimize damage to plantings by animal browse.

2) RM&E activities to track status and trends for water quality and fish populations and their movement.
This includes WE's for continuous temperature monitoring throughout the watershed (WE Q); as well as discharge and hydrolab monitoring (WE P), RM&E activities associated with trout populations and movement include summer backpack electroshock surveys (WE M & S), evaluate status and trends in redband trout populations, and spring migration trapping (WE L & T ) and associated pit tagging technology (WEs M, N & U)  to monitor seasonal movements of redband trout in specific reaches of the upper Hangman watershed.

Fixed PIT-tag antennae arrays will be installed at three locations on Hangman Creek to monitor mainstem use by redband trout: one at the mouth of Indian Creek; at the mouth of Nehchen Creek; and a new station within the k'wne' 'ulchiyark'wmtsut restoration area. New tributary stations will be installed at Indian Creek, Smith Creek, Nehchen Creek and Sheep Creek.

WE O is a non-native fish removal project on Nehchen Creek where a genetically confirmed population of illegally introduced cutthroat trout have occupied the upper reaches of the mainstem. Non-native fish removal began in summer of 2015. WE L and M help monitor the responses to removal efforts.

3) Reporting on project activities and outcomes.
A non-technical report will be drafted during this contract as a means of reporting on the instream work completed through four phases of the k'wne' 'ulchiyark'wmntsut project. Monitoring data will be compiled from the 2017-2018 field seasons to aid in writing a technical report covering RM&E activities that will be delivered during the 2019 contract period.
  
Account Type(s):
Expense
Contract Start Date:
05/01/2018
Contract End Date:
04/30/2019
Current Contract Value:
$358,376
Expenditures:
$358,376

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarker
5 km
3 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration No Interested Party dxaffonso@bpa.gov (503) 230-5918
Thomas Biladeau Coeur D'Alene Tribe Yes Interested Party tbiladeau@cdatribe-nsn.gov (209) 686-6307
Jon Firehammer Coeur D'Alene Tribe Yes Interested Party jfirehammer@cdatribe-nsn.gov (208) 686-7037
Cameron Heusser Coeur D'Alene Tribe Yes Interested Party cheusser@cdatribe-nsn.gov (208) 686-5521
Bruce Kinkead Coeur D'Alene Tribe Yes Contract Manager bkinkead@cdatribe-nsn.gov (208) 686-6071
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Angelo Vitale Coeur D'Alene Tribe Yes Supervisor ajvitale@cdatribe-nsn.gov (208) 686-6903
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing 26 of 26 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A178815165Produce Environmental Compliance DocumentationNEPA analysis and documentationSubmit required documents to BPA to ensure NEPA and ESA compliance for all project activities, include those proposed within the Indian, Sheep, and Hangman Creek drainages.$16,4234.57%05/01/201804/30/2019
B178816114Identify and Select ProjectsIdentify and select new restoration projects in the Hangman watershedEngage in advanced scoping of restoration projects with private landowners in 4 target areas (Sheep, Indian, Mission Creek, and Hangman upstream of Mission Cr). Make contacts with landowners by mail, phone, or by personal visits in these priority areas in order to obtain signed landowner agreements which lead to restoration projects for 2018 and beyond. Additional priority areas may be identified once the staff working on the companion project (BPA Project #200103300) develop and write management plans for properties purchased downstream on Nehchen Creek. The program manager will take a new role in this WE to aid in the negotiations of contracts and planning of restoration designs. A large proportion of time will be spent on the process of identifying key projects on properties purchased thru settlements with Avista Utilities.$24,1796.74%05/01/201804/30/2019
C18030529Increase Aquatic and/or Floodplain ComplexityActivate historical channels on lower Sheep CreekThis WE is a partnership between BPA Projects #200103300 and #200103200. The property is a mitigation property purchased by BPA for the Coeur d' Alene Tribe and managed through BPA Project #200103300. The current proposed project on Sheep Creek will divert stream flow to an engineered channel leading to historical stream channels, thereby greatly increasing stream length, improving stream/floodplain connectivity and elevating ground water tables. This WE builds on previous efforts by the BPA 200103300 wherein an engineered channel was constructed (but not activated) to connect historic channel locations with the existing incised and straightened channel. Additional work was completed in 2016 to construct a flow choke structure upstream of the proposed channel diversion to meter flood waters onto the floodplain, and install additional LWD structures at the head and toe of the engineered channel for maintenance of channel morphology and stability. During this contract, the straightened stream alignment will be filled to activate the engineered and historic channels. Both ends of the channel fill will be armored with rock and/or wood to resist scouring and erosion by high flows from Hangman Creek and Sheep Creek. Fill material is already staged on site adjacent to the channel to be filled. This fill material was generated during the process of excavating the engineered channel and through construction of other nearby floodplain features. The rock and wood is also already staged on site.$19,8415.53%05/01/201804/30/2019
D17882047Plant VegetationRiparian enhancement at Hangman Creek, Phase 3: EPA GrantThe entire project k'wne' 'ulchiyark'wmtsut takes place on property purchased thru Avista dam mitigation and purchased for the Coeur d'Alene Tribe. It is managed by the CDA Tribe's Wildlife Program, and the Fisheries Program does all the instream and riparian work, while the Wildlife Program works on the uplands. This work element is associated with the newly activated channel constructed in WE E in a previous contract (CR-72434). The proposed work was initiated as a result of receiving a grant from Western Native Trout Initiative in 2016 to provide rock for an engineered relief channel and provide an early phase of upland and riparian plants. During the spring of 2018 1,985 live cuttings will be planted including; 150 Drummond willow, 50 sandbar willow, 1085 Pacific willow, and 300 MacKenzie Willow, and 400 Black cottonwood. It is anticipated that anywhere between 600 and 1,000 will be planted using the trenching method. This involves a Mini excavator digging a 8 inch wide trench down to the ground water level and filling in after poles are laid down in the trench. During the fall of 2018 1,500 5 gallon potted hardwoods will be planted, including 400 Thinleaf alder, 400 Pacific willow, 200 Aspen, 100 Coyote willow, and 400 Black cottonwood. All potted hardwood trees will be done by hand using shovels, with a chance that some will be installed using 12inch auger bit that will be drilled in less than 12" deep using a mini excavator. Separate personal will monitor holes prior to dropping in potted trees to check for artifacts. Cultural Resources Dept of CDAT has determined that such measures do not pose a threat to disturbing cultural artifacts.$25,0946.99%05/01/201804/30/2019
E178822198Maintain VegetationMaintain vegetation on Hangman Creek, Phases 1-4The entire project k'wne' 'ulchiyark'wmtsut takes place on property purchased thru Avista dam mitigation and purchased for the Coeur d'Alene Tribe. It is managed by the CDA Tribe's Wildlife Program, and the Fisheries Program does all the instream and riparian work, while the Wildlife Program works on the uplands. This work element would encompass a variety of actions that respond appropriately to pressures from aquatic and terrestrial browsers, flash flooding, and invasive weeds. Protective plant devices and fencing would be installed and repaired as needed for a variety of plants already in place from previous contracts. In some cases, additional vegetation would be planted to replace plantings that did not survive with a lean toward plants that are showing the better survival rates. All plantings will be done by hand using 2- 5 inch auger bits that will be drilled in less than 6" - 24" deep. Cultural Resources Dept of CDAT has determined that such measures do not pose a threat to disturbing cultural artifacts.$38,00010.58%05/01/201804/30/2019
F181598198Maintain VegetationMaintain vegetation on Hangman Creek, SweatlodgeThis work element would encompass a variety of actions that respond appropriately to pressures from aquatic and terrestrial browsers, flash flooding, and invasive weeds. Protective plant devices and fencing would be installed and repaired as needed for a variety of plants already in place from previous contracts. In some cases, additional vegetation would be planted to replace plantings that did not survive with a lean toward plants that are showing the better survival rates. All plantings will be done by hand using 2- 5 inch auger bits that will be drilled in less than 6" - 24" deep. Cultural Resources Dept of CDAT has determined that such measures do not pose a threat to disturbing cultural artifacts.$2,9480.82%05/01/201804/30/2019
G181597198Maintain VegetationMaintain vegetation on Sheep CreekThis work element would encompass a variety of actions that respond appropriately to pressures from aquatic and terrestrial browsers, flash flooding, and invasive weeds. Protective plant devices and fencing would be installed and repaired as needed for a variety of plants already in place from previous contracts. In some cases, additional vegetation would be planted to replace plantings that did not survive with a lean toward plants that are showing the better survival rates. All plantings will be done by hand using 2- 5 inch auger bits that will be drilled in less than 6" - 24" deep. Cultural Resources Dept of CDAT has determined that such measures do not pose a threat to disturbing cultural artifacts.$2,8530.79%05/01/201804/30/2019
H178823186Operate and Maintain Habitat/Passage/StructureMaintain beaver dams in Hangman Creek with hardwood supplementationNo ground disturbance is to occur under this Work Element. In order to keep beaver away from recent riparian plantings, we will provide enough dam building materials to maintain the six active dams built in the restoration area, as well as cuttings provided for food. Aspen will be cut and delivered to dam locations on 3-4 different occasions during the summer and fall of 2018. The entire project k'wne' 'ulchiyark'wmtsut takes place on property purchased thru Avista dam mitigation and purchased for the Coeur d'Alene Tribe. Land management is performed by the CDA Tribe's Wildlife Program, the Tribe’s Fisheries Program does all the in-stream and riparian work when needed.$4,5501.27%05/01/201804/30/2019
I18030755Erosion and Sedimentation ControlTreat stream banks on Hangman Creek using bioengineeringrk'wmntsut has several sections of the reach that raw banks need to be treated to decrease erosion and fine sediment in the channel. What is proposed is a bioengineering treatment called encapsulated soil lift, where the channel will be prepared to have boulder placed and embedded into the channel and three layer of soil with willows wrapped in erosion control matting.$37,30010.39%05/01/201804/30/2019
J18030640Install FenceInstall wildlife exclusion fencing on Hangman CreekThis work element involves installation of 7,900 feet and 50.8 acres of wildlife exclusion fencing using 10 feet fence post and 8 ft tall wire gauge fence designed to keep out a large herd of elk found in the area. The fence will cross or butt up against the mainstem of Hangman Creek, ponds created by restoration, and small intermittent channels entering Phase 3 of k'wne' 'ulchiyark'wmtsut.$22,2506.20%05/01/201804/30/2019
K178825157Collect/Generate/Validate Field and Lab DataSample Redband trout and non-native salmonids using migration trapsInvolves the sampling of trout and other fish species using upstream/downstream migration traps at one location in each of Indian and Nehchen creeks. Data will be collected from trout captured in traps from March 1 to June 1. Installation and maintenance of the traps are now part of the Work Element, rather than separated in different work elements.$28,0327.81%05/01/201804/30/2019
L178826157Collect/Generate/Validate Field and Lab DataSample Redband trout in Hangman Creek using electroshockingInvolves the sampling of trout and other fish species using backpack electroshocking equipment in early summer. Fish will be counted, measured for length and weight, inspected for marks such as adipose clips, scanned for PIT tags, and in some instances, implanted with a PIT tag.$5,7001.59%05/01/201804/30/2019
M178827158Mark/Tag AnimalsUniquely mark redband trout in Upper HangmanFish will be tagged using two methods, one from trap sampling (WE K), and summer backpack electroshocking (WE L). PIT-tag redband trout that are captured in traps located in Nehchen (RM 0.1) and Indian (RM 1.4) creeks. Tagged fish will also receive an adipose clip to evaluate long-term tag retention. PIT-tag redband trout during summer shock surveys in Indian Creek and in reaches of upper Nehchen Creek, and Smith Creek. Completion of this work element conditioned on completion of WEs K and L.$2,6830.75%05/01/201804/30/2019
N178828190Remove, Exclude and/or Relocate AnimalsRemove non-native cutthroat trout from Nehchen CreekCuthroat are not native the the Spokane River system and Hangman Creek. Fish from the Coeur d'Alene watershed were transplanted into Hangman Creek in 1990 and mixing with redbands within the Nehchen watershed. We have decided that complete removal is feasible. Summer of 2015 we initiated removal during summer electroshocking and continues with trapping fish in the spawning area. No longer finding large numbers of cutthroat spawners, but still present in 1+ fish during summer electroshocking surveys. We will continue removal methods until no hybrids are found for two successive years. Non-Native cutthroat trout will be removed from Nehchen Creek and mainstem reaches of Hangman during 2017 as a continuing project. Descriptive data will be collected from sacrificed cutthroat trout that are removed. A migratory studies weir will be installed in March and maintained through May as part of WE K. First pass will be done during normal population sampling in July (WE L), and another pass will be done in August within perennial waters.$1,7000.47%05/01/201804/30/2019
O178829157Collect/Generate/Validate Field and Lab DataCollect water quality and quantity data in Hangman CreekNo ground disturbance is to occur under this Work Element. This element includes all data collection of water quality and quantity, including temperature, discharge, turbidity, dissolved oxygen, pH and conductivity. Turbidity will be analyzed in-house. Water Quality data will be collected at ten primary sites and fifteen secondary sites. The primary sites are sometimes used for significant high flow events, in addition to the sampling done in June and August. The secondary sites are only sampled in June and August. There will be four sites on the mainstem of Hangman Creek, and at fish-bearing streams Sheep, Mission, Nehchen, Martin and Indian (2 sites), S.F. Hangman, and Smith. There will also be sampling at an additional 15 sites in June and August in the forested areas of the same streams.$9,4182.62%05/01/201804/30/2019
P178830157Collect/Generate/Validate Field and Lab DataMonitor water temperature in Hangman CreekNo ground disturbance is to occur under this Work Element. This element includes collection of continuous temperature data at 42 locations. Data loggers will be deployed from April 15th through November 1st at 37 locations, and June 1st through Nov 1st at 5 locations to represent the mainstem and tributaries of Hangman Creek. Hourly temperature readings to 0.1 C with an accuracy of 0.02 C covering spawning periods through fall at 42 locations using Hobo Pro temp monitors. Data will be analyzed to document the percent of time that stream temperatures exceed 14 degrees C from May 1st- June 30th, and at 20 degrees C from July 1st - August 31st. Graphical output will show: 1) March - October 7-day running average max/min daily temperatures; 2) hourly air temps synthesized with water temps; and 3) comparison of deep pool versus adjoining riffle temperatures at 3 locations.$8,3142.32%05/01/201804/30/2019
Q181328157Collect/Generate/Validate Field and Lab DataCollect data and maintain fixed PIT tag antennae arraysNo ground disturbance is to occur under this Work Element. This work element describes the field methodologies used to collect the data at stationary PIT-tag antenna arrays where interrogation data are passively logged and stored. Half-duplex (i.e., HDX) passive integrated transponder (i.e., PIT) technology is being implemented in the upper Hangman Creek watershed to monitor seasonal and life-history movements of fluvial interior redband trout. Monitoring in-stream movement patterns will provide data on seasonal habitats used (e.g., overwintering), and could aid in evaluating the response to restorative actions implemented to improve the quality of seasonal habitats. Monitoring the propensity of juveniles to move out of natal tributary habitats and into Hangman Creek. Understanding the current spatial distribution of the migratory lifehistory variant may aid in prioritizing future restoration efforts.$15,9094.43%05/01/201804/30/2019
      
$359,000
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Completed NEPA Checklist A: 165. NEPA analysis and documentation 04/30/2019 04/30/2019
Selection of Restoration Projects B: 114. Identify and select new restoration projects in the Hangman watershed 04/30/2019 04/30/2019
Activation of engineered channel C: 29. Activate historical channels on lower Sheep Creek 04/30/2019 09/28/2018
Enhanced Floodplain Communities on Hangman Creek D: 47. Riparian enhancement at Hangman Creek, Phase 3: EPA Grant 04/30/2019 05/25/2018
Newly planted riparian plants maintained, protected, and or replaced E: 198. Maintain vegetation on Hangman Creek, Phases 1-4 04/30/2019 04/30/2019
Newly planted riparian plants maintained, protected, and or replaced F: 198. Maintain vegetation on Hangman Creek, Sweatlodge 04/30/2019 04/30/2019
Newly planted riparian plants maintained, protected, and or replaced G: 198. Maintain vegetation on Sheep Creek 04/30/2019 04/30/2019
Provide dam building materials for 6 dams H: 186. Maintain beaver dams in Hangman Creek with hardwood supplementation 04/30/2019 04/26/2019
Raw Bank Treated with Bioengineering on Hangman Creek, Phase 2 I: 55. Treat stream banks on Hangman Creek using bioengineering 04/30/2019 04/30/2019
Installation of Wildlife Exclusion Measures J: 40. Install wildlife exclusion fencing on Hangman Creek 09/21/2018 09/14/2018
Produce data from redband trout captured in migrant traps in Hangman Creek watershed K: 157. Sample Redband trout and non-native salmonids using migration traps 04/30/2019 04/30/2019
Produce Data from Electroshock Sampling of Fish in Hangman Watershed L: 157. Sample Redband trout in Hangman Creek using electroshocking 04/30/2019 03/29/2019
PIT-tag juvenile and adult redband trout in Hangman Creek project area. M: 158. Uniquely mark redband trout in Upper Hangman 04/30/2019 04/30/2019
Removal of non-native cutthroat trout from Nehchen Creek N: 190. Remove non-native cutthroat trout from Nehchen Creek 04/30/2019 04/30/2019
Collect Water Quality Data in the Hangman Creek Watershed O: 157. Collect water quality and quantity data in Hangman Creek 04/30/2019 04/30/2019
Collect Continuous Temperature Data in the Hangman Creek Watershed P: 157. Monitor water temperature in Hangman Creek 04/30/2019 04/30/2019
Collect Interrogation Data from Stationary PIT tag Antenna Arrays in the Hangman Creek Watershed Q: 157. Collect data and maintain fixed PIT tag antennae arrays 04/30/2019 04/30/2019
Examination of distribution and density patterns at the sub-watershed and watershed scale R: 162. Analyze data generated from sampling salmonids in tributary habitats in upper Hangman watershed 04/30/2019 04/30/2019
Abundance and life-history information for migratory redband trout in upper Hangman S: 162. Analyze data generated for redband trout captured in migrant traps in Hangman Creek 04/30/2019 04/30/2019
Pit Tag Array Data Analyzed T: 162. Analyze data logged at stationary PIT antenna arrays for Redband trout in Hangman Creek 04/30/2019 04/30/2019
Water Temperature Analyzed U: 162. Analyze stream temperature data in Hangman Creek 04/30/2019 04/30/2019
GIS Summarization of Project Data Collected and Updated Trout Distribution for input to Regional Map V: 161. Summarize Redband trout population status and habitat in Hangman Creek using GIS 04/30/2019 04/30/2019
Coordination of RM&E and Restoration for Redband partners in the Upper Columbia basin W: 191. Coordinate restoration and RM&E with Upper Columbia and Spokane Sub-basin partners 04/30/2019 04/30/2019
Management and Administration of Project Z: 119. Manage and administer project 04/30/2019 04/30/2019

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
Trout, Interior Redband (O. mykiss gairdnerii)
  • 3 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 114 Identify and Select Projects
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 4 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 NEPA analysis and documentation 05/01/2018
B 114 Identify and select new restoration projects in the Hangman watershed 05/01/2018
C 29 Activate historical channels on lower Sheep Creek 05/10/2018
D 47 Riparian enhancement at Hangman Creek, Phase 3: EPA Grant 05/10/2018
E 198 Maintain vegetation on Hangman Creek, Phases 1-4 05/10/2018
F 198 Maintain vegetation on Hangman Creek, Sweatlodge 05/10/2018
G 198 Maintain vegetation on Sheep Creek 05/10/2018
H 186 Maintain beaver dams in Hangman Creek with hardwood supplementation 05/10/2018
I 55 Treat stream banks on Hangman Creek using bioengineering 05/10/2018
J 40 Install wildlife exclusion fencing on Hangman Creek 05/10/2018
K 157 Sample Redband trout and non-native salmonids using migration traps 05/10/2018
L 157 Sample Redband trout in Hangman Creek using electroshocking 05/10/2018
M 158 Uniquely mark redband trout in Upper Hangman 05/10/2018
N 190 Remove non-native cutthroat trout from Nehchen Creek 05/10/2018
O 157 Collect water quality and quantity data in Hangman Creek 05/10/2018
P 157 Monitor water temperature in Hangman Creek 05/10/2018
Q 157 Collect data and maintain fixed PIT tag antennae arrays 05/10/2018
R 162 Analyze data generated from sampling salmonids in tributary habitats in upper Hangman watershed 05/01/2018
S 162 Analyze data generated for redband trout captured in migrant traps in Hangman Creek 05/01/2018
T 162 Analyze data logged at stationary PIT antenna arrays for Redband trout in Hangman Creek 05/01/2018
U 162 Analyze stream temperature data in Hangman Creek 05/01/2018
V 161 Summarize Redband trout population status and habitat in Hangman Creek using GIS 05/01/2018
W 191 Coordinate restoration and RM&E with Upper Columbia and Spokane Sub-basin partners 05/01/2018
X 132 Draft non-technical progress report 05/01/2018
Y 185 Periodic Status Reports for BPA 05/01/2018
Z 119 Manage and administer project 05/01/2018