Province | Subbasin | % |
---|---|---|
Columbia River Estuary | Columbia Estuary | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 31-Mar-2025.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Jason Karnezis | Bonneville Power Administration | Yes | COR | jpkarnezis@bpa.gov | (503) 230-3098 |
Denise Lofman | Columbia River Estuary Study Taskforce (CREST) | No | Supervisor | dlofman@columbiaestuary.org | (503) 325-0435 |
Jessica Power | Bonneville Power Administration | No | CO Assistant | jdpower@bpa.gov | (503) 230-4023 |
John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
Shawn Skinner | Bonneville Power Administration | No | Env. Compliance Lead | srskinner@bpa.gov | (503) 230-3727 |
Jason Smith | Columbia River Estuary Study Taskforce (CREST) | Yes | Contract Manager | jsmith@columbiaestuary.org | (503) 325-0435 |
Karen Wolfe | Bonneville Power Administration | Yes | Contracting Officer | ktwolfe@bpa.gov | (503) 230-3448 |
A | 252183 | 165 | Produce Environmental Compliance Documentation | EC work for this project is covered in the main CREST estuary contract 92647 | CREST completes all environmental compliance and permitting at the local, state, and federal levels. CREST has a history of completing all environmental compliance for its restoration projects. CREST has worked closely with BPA through other direct contracts and has a track record of successful design, permitting, and implementation of restoration projects. CREST has completed cultural resources assessments, programmatic endangered species act compliance, and NEPA documentation in support of past contracts and we will continue to due so for projects during this contract period. Since CREST is in design and construction on multiple restoration projects each year, environmental compliance work occurs throughout the contract period. **EC work for this project is covered in the main CREST estuary contract 92647 | $0 | 0.00% | 06/30/2025 | |
B | 252184 | 119 | Manage and Administer Projects | ALL CREST MANAGEMENT COVERED IN CREST EXPENSE CONTRACT | ALL CREST CONTRACT MANAGEMENT COVERED IN CREST EXPENSE CONTRACT | $0 | 0.00% | 01/18/2024 | 06/30/2025 |
C | 252185 | 132 | Produce Progress (Annual) Report | NOT REQUIRED | This project will be reported out in CREST's Annual Report under the CREST expense contract. | $0 | 0.00% | ||
D | 252186 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | $0 | 0.00% | 04/01/2024 | 06/30/2026 |
E | 252187 | 184 | Install Fish Passage Structure | WARREN SLOUGH RAILROAD - CONSTRUCTION--Install Bridge | Install a new 60ft long bridge to provide full fish passage to the 22 acres of floodplain habitat. * All projects in the estuary are subject to cost benefit analysis and approval by BPA. Each of the projects CREST is proposing during this contract undergo a cost/PBU preliminary review and final scoring by ERTG. If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet costs/PBU CREST will work with BPA to address. For all construction contracts over $30,000 CREST utilizes our procurement procedures through an RFP and competitive bid process. | $1,695,329 | 90.64% | 01/18/2024 | 06/30/2026 |
F | 252188 | 30 | Realign, Connect, and/or Create Channel | WARREN SLOUGH RAILROAD - CONSTRUCTION--Create New Channel | At the Warren Slough site, a new channel will be excavated through the railroad berm underneath the new bridges. Approximately 100 linear feet of new channel will be excavated to connect the site to the outside river. * All projects in the estuary are subject to cost benefit analysis and approval by BPA. Each of the projects CREST is proposing during this contract undergo a cost/PBU preliminary review and final scoring by ERTG. If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet costs/PBU CREST will work with BPA to address. For all construction contracts over $30,000 CREST utilizes our procurement procedures through an RFP and competitive bid process. | $150,000 | 8.02% | 01/18/2024 | 06/30/2026 |
G | 252189 | 47 | Plant Vegetation | WARREN SLOUGH RAILROAD - CONSTRUCTION--Plant Vegetation | Plant native emergent, riparian, and upland plant species over 2 acres. * All projects in the estuary are subject to cost benefit analysis and approval by BPA. Each of the projects CREST is proposing during this contract undergo a cost/PBU preliminary review and final scoring by ERTG. If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet costs/PBU CREST will work with BPA to address. For all construction contracts over $30,000 CREST utilizes our procurement procedures through an RFP and competitive bid process. | $25,000 | 1.34% | 01/18/2024 | 06/30/2026 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Obtain and provide BPA with Environmental Compliance Documentation | A: 165. EC work for this project is covered in the main CREST estuary contract 92647 | 06/30/2025 | ||
Effective implementation management and timely contract administration | B: 119. ALL CREST MANAGEMENT COVERED IN CREST EXPENSE CONTRACT | 06/30/2025 | ||
Warren Slough--Install Bridges | E: 184. WARREN SLOUGH RAILROAD - CONSTRUCTION--Install Bridge | 06/30/2026 | ||
Warren Slough--Completed channel construction | F: 30. WARREN SLOUGH RAILROAD - CONSTRUCTION--Create New Channel | 06/30/2026 | ||
Warren Slough--Install Plantings | G: 47. WARREN SLOUGH RAILROAD - CONSTRUCTION--Plant Vegetation | 06/30/2026 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened) |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | EC work for this project is covered in the main CREST estuary contract 92647 | |||||||
B | 119 | ALL CREST MANAGEMENT COVERED IN CREST EXPENSE CONTRACT | |||||||
C | 132 | NOT REQUIRED | |||||||
D | 185 | Periodic Status Reports for BPA | |||||||
E | 184 | WARREN SLOUGH RAILROAD - CONSTRUCTION--Install Bridge | |||||||
F | 30 | WARREN SLOUGH RAILROAD - CONSTRUCTION--Create New Channel | |||||||
G | 47 | WARREN SLOUGH RAILROAD - CONSTRUCTION--Plant Vegetation |