SOW Report
Contract 74313 REL 65: 1989-024-01 EXP UMATILLA JUVENILE SALMONID OUTMIGRATION M&E 2020
Project Number:
Title:
Evaluate Umatilla Juvenile Salmonid Outmigration
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
74313 REL 65
Contract Title:
1989-024-01 EXP UMATILLA JUVENILE SALMONID OUTMIGRATION M&E 2020
Contract Continuation:
Previous: Next:
74313 REL 41: 1989-024-01 EXP UMATILLA JUVENILE SALMONID OUTMIGRATION M&E 2019
  • 74313 REL 87: 1989-024-01 EXP UMATILLA JUVENILE SALMONID OUTMIGRATION M&E
Contract Status:
Closed
Contract Description:
This contract funds long-term smolt monitoring activities and implementation of pHOS surveys for the ESA-listed Umatilla River steelhead population.  Smolt monitoring activities include the capture, counting, examination, and PIT tagging of steelhead smolts.  Data collected are used to characterize life history metrics, including size, age, condition, and timing of seaward moving juvenile steelhead.  Key performance metrics; including smolt abundance and survival, and high level indicators; including smolt-to-adult return, egg-to-smolt survival, and smolts-per-spawner are calculated and tracked through time.  pHOS surveys provide a direct measure of the proportion of natural spawners that are of hatchery origin and is an important measure of population diversity in a supplemented system.  Work conducted under this contract provides important population-level survival, productivity, and life history infor... mation that is necessary to better understand the relationships between habitat conditions, hatchery programs, and the production of smolts within the Umatilla River.  Managers use the information to judge success of habitat enhancement and hatchery reform.   
Account Type(s):
Expense
Contract Start Date:
11/01/2019
Contract End Date:
10/31/2020
Current Contract Value:
$521,110
Expenditures:
$521,110

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarker
20 km
10 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing 13 of 13 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A197641165Produce Environmental Compliance DocumentationEnvironmental compliance for monitoring workCoordinate and work with BPA staff to ensure all work elements have appropriate NEPA/ESA clearance. Provide NOAA Fisheries with copy of annual report and annual operating plan related to data collection activities.$2,5200.48%11/01/201910/31/2020
B197642157Collect/Generate/Validate Field and Lab DataThree Mile Falls Dam and Birch Creek natural summer steelhead smolt trappingSmolt outmigration estimates are necessary to separate the freshwater and ocean portions of anadromous salmonid life history. Estimates of outmigrant abundance allow evaluation of trends in habitat productivity, without the masking influence of Columbia River migratory and ocean survival conditions. Outmigrant estimates also allow estimates of freshwater survival (e.g. egg to smolt survival) and productivity (e.g. smolts/adult or smolts/redd) when combined with additional monitoring efforts. Smolt trapping will be conducted at Three Mile Falls Dam and Birch Creek to determine annual smolt yield and document inter-annual variation in life history characteristics (i.e. emigration timing & size) for the Middle Columbia River DPS Umatilla River steelhead MPG.$172,22533.05%11/01/201910/31/2020
C197643158Mark/Tag AnimalsPIT tag up to 6,000 natural summer steelheadPIT tag up to 6,000 natural summer steelhead at downstream migrant traps in Birch Creek and at Three Mile Falls Dam to estimate annual smolt yield, life-stage specific survival, and migration timing for the Middle Columbia River DPS Umatilla River steelhead MPG. Fish will be PIT tagged according to standards outlined in the PIT Tag Marking Procedures Manual.$62,62612.02%11/01/201910/31/2020
D197644159Transfer/Consolidate Regionally Standardized DataUpload PIT Tagging data to PTAGISCheck and upload PIT tag data for natural summer steelhead tagged at downstream migrant traps to PTAGIS system to allow tracking of Middle Columbia River DPS Umatilla River steelhead MPG smolts downstream.$28,7035.51%11/01/201910/31/2020
E197645159Transfer/Consolidate Regionally Standardized DataUpload Three Mile Falls Dam interrogation data to PTAGISOperate and maintain PIT tag detection system at Three Mile Falls Dam.$36,5327.01%11/01/201910/31/2020
F197646162Analyze/Interpret DataStatistical summary and analysis of Umatilla River natural summer steelhead smolt trapping dataProvide statistical summaries and analysis to determine status and trends through 24 years of life history, smolt production, life-stage specific survival, and freshwater productivity data for Middle Columbia River DPS Umatilla River steelhead MPG. Fish and Wildlife Program RM&E strategies supported by this work element include assessment of the status and trend of juvenile abundance and productivity of natural origin fish populations and diversity of natural and hatchery origin fish populations. The status and trend data is also used to facilitate assessment of the Umatilla Basin Fisheries Restoration Program and support of tracking BPA's progress toward BiOp goals.$109,84121.08%11/01/201910/31/2020
G197647157Collect/Generate/Validate Field and Lab DataUmatilla River adult steelhead surveys and data collection.Conduct adult steelhead surveys for the Middle Columbia River DPS Umatilla River steelhead MPG using standard ODFW methods. Data will be used to determine the proportion of natural origin spawners composed of hatchery origin fish (pHOS).$15,6553.00%11/01/201906/30/2020
H197648162Analyze/Interpret DataStatistical summary and analysis of Umatilla River adult steelhead dataProvide statistical summaries and analysis comparing pHOS from adult steelhead surveys and TMF dam counts for Middle Columbia River DPS Umatilla River steelhead MPG. Develop and maintain long term data set.$10,4382.00%11/01/201910/31/2020
I197649189Coordination-Columbia BasinwideCoordinate with local and regional management and M&E groupsCoordination and planning with Umatilla Subbasin projects, co-managers and researchers through monthly meetings and other venues.$26,1225.01%11/01/201910/31/2020
J197650119Manage and Administer ProjectsUmatilla Outmigration and Survival Project AdministrationCovers all project management and administrative work related to the contract excluding environmental compliance * SOW/budget/Property Renewal * Cost Share * CPR/1st Aid Training$15,4262.96%11/01/201910/31/2020
K197651132Produce Progress (Annual) ReportAnnual RME Report - January 2019 - December 2019ODFW will produce a “technical“ Annual report; summarizing 2019 calendar year results for Umatilla Juvenile Outmigration RM&E. This report will summarize the work completed and provide updates to long-term status and trend data for the ESA-listed Umatilla steelhead population, the significance of the findings as well as challenges faced, money spent and future directions.$35,9826.90%11/01/201903/31/2020
L197652202Produce BiOp RPA Report2019 BiOp RPA ReportSubmit BiOp RM&E Report in Taurus for Calendar Year 2019. The finalized version of this report will be due March 15, 2020. FCRPS 2008 (RPA 50.1, RPA 50.3, RPA 50.6, RPA 56.1, RPA 50.2, RPA 50.8, RPA 56.2, RPA 56.3, RPA 72.1) Covers work conducted for the calendar year 2019. Reports satisfy RPA reporting requirements in support of tracking BPA's progress toward BiOp goals.$2,5200.48%11/01/201903/15/2020
M197640185Produce CBFish Status ReportQuarterly Status ReportsODFW shall report on the status of milestones and deliverables in Pisces on a quarterly basis. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$2,5200.48%01/01/202010/31/2020
      
$521,110
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Compliance for monitoring A: 165. Environmental compliance for monitoring work 10/31/2020 10/31/2020
Smolt trapping dataset and metadata B: 157. Three Mile Falls Dam and Birch Creek natural summer steelhead smolt trapping 10/31/2020 10/31/2020
PIT tag 6,000 natural summer steelhead C: 158. PIT tag up to 6,000 natural summer steelhead 10/31/2020 10/31/2020
Tagging files D: 159. Upload PIT Tagging data to PTAGIS 10/31/2020 10/31/2020
Interrogation files E: 159. Upload Three Mile Falls Dam interrogation data to PTAGIS 10/31/2020 10/31/2020
Population status and trends dataset and metadata F: 162. Statistical summary and analysis of Umatilla River natural summer steelhead smolt trapping data 10/31/2020 10/31/2020
pHOS dataset and metadata G: 157. Umatilla River adult steelhead surveys and data collection. 06/30/2020 06/30/2020
Steelhead pHOS dataset and metadata H: 162. Statistical summary and analysis of Umatilla River adult steelhead data 10/31/2020 10/31/2020
Research results, attendance of monthly meetings, coordination among groups I: 189. Coordinate with local and regional management and M&E groups 10/31/2020 10/31/2020
Successful contract/project administration J: 119. Umatilla Outmigration and Survival Project Administration 10/31/2020 10/31/2020
Upload 2019 RME Annual Report K: 132. Annual RME Report - January 2019 - December 2019 03/31/2020 03/31/2020
Submit 2019 BiOp RPA Report L: 202. 2019 BiOp RPA Report 03/15/2020 03/15/2020

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 2 instances of WE 159 Transfer/Consolidate Regionally Standardized Data
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental compliance for monitoring work
B 157 Three Mile Falls Dam and Birch Creek natural summer steelhead smolt trapping 08/22/2019
C 158 PIT tag up to 6,000 natural summer steelhead 08/22/2019
D 159 Upload PIT Tagging data to PTAGIS
E 159 Upload Three Mile Falls Dam interrogation data to PTAGIS
F 162 Statistical summary and analysis of Umatilla River natural summer steelhead smolt trapping data
G 157 Umatilla River adult steelhead surveys and data collection. 08/22/2019
H 162 Statistical summary and analysis of Umatilla River adult steelhead data
I 189 Coordinate with local and regional management and M&E groups
J 119 Umatilla Outmigration and Survival Project Administration
K 132 Annual RME Report - January 2019 - December 2019
L 202 2019 BiOp RPA Report
M 185 Quarterly Status Reports