Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 76317: 2010-004-00 EXP ESTUARY HABITAT RESTORATION (CREST)
Project Number:
Title:
CREST Estuary Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Columbia Estuary 100.00%
Contract Number:
76317
Contract Title:
2010-004-00 EXP ESTUARY HABITAT RESTORATION (CREST)
Contract Continuation:
Previous: Next:
69497: 2010-004-00 EXP ESTUARY HABITAT RESTORATION (CREST)
  • 82217: 2010-004-00 EXP CREST ESTUARY HABITAT RESTORATION (CREST)
Contract Status:
Closed
Contract Description:
CREST proposes to continue to implement estuary habitat restoration projects during this contract period.  Projects developed, designed, and permitted during previous contract periods will move to construction.  CREST will continue to develop and design new restoration projects working with landowners, stakeholders, and subcontracted design and engineering consultants.    CREST will continue to invest staff time in community outreach and project development including participating in regional meetings with BPA, the Corps, as well as partner coordination forums such as the Estuary Partnership's Science Work Group (SWG).  CREST biologists will conduct Level 3 pre and post project evaluation (Action Effectiveness Monitoring; AEMR) at our restoration sites in coordination with partners and the Columbia Estuary Ecosystem Restoration Program (CEERP).....  

Restoration of estuary habitat foc... uses on habitat opportunity, capacity, and realized function critical to the recovery of Threatened/Endangered salmon utilizing the Columbia River Estuary.  CREST Habitat Restoration Program Deliverables include:
1)  Identification, prioritization, and development of potential estuary habitat restoration projects.
2)  Scoping and selecting restoration projects based on technical evaluation during feasibility stage and scientific review by Estuary Partnership Project Review Committee and partners.
3)  Design, permit, and implement 3-5 on the ground estuarine restoration projects each year.
4)  Conduct Action Effectiveness Monitoring and Research of restoration projects in coordination with regional partners.

The following projects are currently in full design, engineering, and permitting and will move to construction in 2017:
• Flights End:  This project, a ODFW managed property on Sauvie Island, aims to enhance tidal wetlands by removing 3 culverts and associated berms in order to reconnect 42 acres of floodplain wetlands to Crane Slough and Multnomah Channel. This project also includes lowering 11 acres of low productivity wetland to reduce the presence of reed canary grass and convert the area to wet prairie habitat.

• Enyarts Property/McCarthy Creek: This project involves the removal of two culverts and wetland grading to restore floodplain connection and juvenile rearing habitat to 70 acres of wetlands along the Multnomah Channel of the Columbia River.  


The following projects are currently in feasibility and will begin design, engineering, and permitting phases and will move to construction in 2018:
• Bear and Mary's Creeks:  Restoration actions for the Bear Creek and Mary's Creek sites will involve lowering 2,050 linear feet of levee, creating an additional 1,775 linear feet of tidal channels, removing 3 undersized culverts, and replanting nearly 15 acres of native vegetation species. These actions will improve access to approximately 40 acres of off-channel habitat for juvenile salmonids, as well as restore tidal inundation and food web connectivity.

• Ferris Creek: Project actions at the Ferris Creek project site will entail restoring connection to approximately 25 acres of off-channel habitat to juvenile salmonids through the removal of 44 feet of remnant levee, creating approximately 220 linear feet of tidal channels into the floodplain. An additional 2 acres at the Ferris Creek project site will be planted with native vegetation.

• West Sand Island: The West Sand Island project aims to enhance fish access and tidal connection to approximately 80 acres of shrub-scrub/ forested marsh habitat through the removal of a berm, and creation of tidal channels into the interior of the island. This project also proposes to treat 16 acres of invasive plants and revegetate the area with beneficial native plants.

• John Day #11:  The John Day #11 restoration replacing 2 undersized culverts on an unnamed tributary to the John Day River, with a free- span bridge to improve salmonid access to more than 20 acres of upstream wetland and spawning habitat.

• Dairy Creek: This project will reconnect Sturgeon Lake to the Columbia River, opening up off channel habitat, improving water quality, and increasing estuarine wetland function through nutrient exchange and food web productivity. Project elements will include replacing 2 existing culverts under Reeder Road with a free-span bridge, and enhancing the existing channel connection.

CREST will also continue to work through design and engineering process in support of the following projects for implementation in 2019.
• Palensky Wildlife Area
• Aldrich Point Railroad
• Wolf Bay Railroad
• Government Island

Each of the projects described above provides immediate access to estuarine habitats for juvenile salmonids.  CREST will also invest project manager staff time working with specific landowners, project partners, and in data gathering and investigations at other sites including the Youngs Bay Watershed, John Day River, and other potential restoration sites for construction in 2019 and beyond.  

CREST will pursue cost share for project engineering and construction during this contract period from the National Park Service, Oregon Watershed Enhancement Board, Salmon Recovery Funding Board, United States Fish and Wildlife Service, as well as the Lower Columbia River Estuary Partnership.  

Within this contract, major work elements are directly related to implementation of previously designed projects and on engineering and permitting for out year projects.  Additional actions focus on community outreach and project development.  

Projects in development will be subject to review by the Estuary Partnership's Project Review Committee (PRC) at 30% design and review and assignment of survival benefits by the Expert Regional Technical Group (ERTG) at 60% design.  All projects in the estuary are also subject to cost benefit analysis and approval by BPA.  Each of the projects CREST is proposing during this contract undergoes a cost/SBU preliminary review and final scoring by ERTG.  If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet BPA criteria CREST will work with BPA to address these issues.

Post project evaluation (Level 3 AEMR) will be conducted by CREST biologists at Otter Point, Colewort Creek, Gnat Creek Phases 1 and 2, South Tongue Point, Diblee Point, Sharnelle Fee, Karlson Island, Sauvie Island Phases 1, 2, and 3, Buckmire Slough Phase I, Crane, Domeyer, Willow Bar, and Westport Slough.  Both pre and post project monitoring will be conducted at the Bear and Mary's Creek, Ferris Creek, Flights End, Enyarts/McCarthy Creek, West Sand Island, and John Day #11 sites.  Pre project monitoring at other project sites such as the Palensky Wildlife Area will also occur during this contract period.  Project monitoring is used at restoration sites to better quantify use and habitat lift for individual restoration sites and to inform benefits of restoration actions at projects in development.
  
Account Type(s):
Expense
Contract Start Date:
07/01/2017
Contract End Date:
06/30/2019
Current Contract Value:
$6,399,776
Expenditures:
$6,399,776

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarker
30 km
20 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing 53 of 53 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A192909185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$1,0250.02%10/01/201706/30/2019
B192910165Produce Environmental Compliance DocumentationProduce EC for projectsCREST completes all environmental compliance and permitting at the local, state, and federal levels. CREST has a history of completing all environmental compliance for its restoration projects. CREST has worked closely with BPA through other direct contracts and has a track record of successful design, permitting, and implementation of restoration projects. CREST has completed cultural resources assessments, programmatic endangered species act compliance, and NEPA documentation in support of past contracts and we will continue to due so for projects during this contract period. Since CREST is in design and construction on multiple restoration projects each year environmental compliance work occurs throughout the contract period.$500,0007.81%07/01/201706/30/2019
C192911119Manage and Administer ProjectsManage and Administer ProjectsCREST will manage and administer the contract in compliance with Bonneville Power Administration policies and procedures.$488,0007.63%07/01/201706/30/2019
D19291299Outreach and EducationMeetings, Newsletters, and EducationOutreach and education actions follow a specific strategy targeting key watersheds/communities and supporting project goals. Targeted outreach not related to projects focuses on increasing relationships within communities which strengthen and improve relationships between CREST, landowners, and community groups. These relationships are important to develop and maintain for long term project success. Targeted outreach related to projects provides communities, landowners, and interested parties with information specifically related to the project and how it relates to that community, ecosystem, and other resources in the community. Specifically, CREST project managers Tom Josephson, Jason Smith, and Madeline Ishikawa will conduct community outreach and education related to projects. Actions include Technical Advisory Committee development, coordination, and oversight, community scoping meetings, community information meetings, permit and design meetings, and printed material development to name some specific actions. Activities account for approximately 20% of staff hours in this contract proposal.$5,0000.08%07/01/201706/30/2019
E192913114Identify and Select ProjectsSystematically Identify, Prioritize, and Select ProjectsCREST employs multiple methods for identification of projects. Opportunistic projects are developed when CREST is approached by a landowner with a specific project concept. CREST investigates and determines if it is feasible based on known biological objectives. Targeted projects are developed by CREST utilizing reach or watershed mapping, on-the-ground investigation, meeting with landowners, agencies, and partners to identify specific project opportunities. As part of this second process, CREST uses metrics based on limiting factors to determine site priorities, developing a project list and focusing on top priority projects first. Approximately 20% of Project Managers and CREST Director time is devoted to project development activities under this work element. It is critical that CREST continue to develop projects and work through the Action Agencies' Expert Regional Technical Group (ERTG) and project selection process as well as design and implement within a give contract period. Therefore, significant effort is devoted to identifying, prioritizing, and selecting projects. Top-priority projects are peripheral, shallow-water refugia or rearing habitats favored by out-of-basin ocean-type juvenile salmonids. CREST develops ERTG templates describing the project site and including project alternatives for top-priority projects. The template forms the basis for developing funding and review documents for BPA and the other AAs. CREST then completes letters of permission/agreement with individual landowners, finalizes ERTG templates, and begins developing design documents. CREST will continue to participate in regional coordination meetings with the Estuary Partnership, Columbia Land Trust, PC Trask, UW, etc., related to the development of new project prioritization tools. CREST will utilize these planning framework and prioritization tools as they come on line and available to practitioners and managers.$500,0007.81%07/01/201706/30/2019
F192914100Construction ManagementCREST oversight of purchasing, contracting, permit compliance of active projectsConstruction management activities include purchasing construction materials, arranging transport to the site, contract development and oversight, coordinating meetings between contractors and engineers, coordinating construction schedules, overseeing permit compliance, conducting construction site visits, reviewing construction budgets, releasing funds for contractor payment, and overseeing whatever elements of construction were not specifically contracted out, which may include fish rescue, temporary erosion and sediment control actions, monitoring, etc. During the contract period CREST will provide construction management activities for the following restoration projects: Flights End, Enyarts/ McCarthy Creek, Bear and Mary's Creek, Ferris Creek, West Sand Island, and John Day #11.$420,0006.56%07/01/201706/30/2019
G192915175Produce DesignPROJECT DEVELOPMENT-- Surveys and Early Project DevelopmentSurvey, design, and preliminary engineering is necessary for project sites that CREST is investigating. These projects will be coordinated closely with BPA for evaluation of cost/SBU and potential for implementation. These projects are proposed for implementation in 2019-20 as approved by BPA. Design will focus on alternatives development, habitat objectives, and preliminary engineering design.$19,9420.31%07/01/201706/30/2019
H192916159Transfer/Consolidate Regionally Standardized DataParticipate in Regional Data Rollup ProjectsPre and Post Project Monitoring data will be available as a source document for other researchers as well as a stand-alone evaluation of project outcomes. Biologists’ products will be standardized and shared per industry standards.$30,0000.47%07/01/201706/30/2019
I192917132Produce Progress (Annual) ReportProvide data for estuary 2017 RME Report* Provide data to the Estuary Partnership (Matt Schwartz) for the 2017 estuary RME Report* ** 2017 RME Report submitted by Estuary Partnership$3,3450.05%12/01/201702/01/2018
J192918132Produce Progress (Annual) ReportProvide data for estuary 2018 RME Report* Provide data to the Estuary Partnership (Matt Schwartz) for the 2018 estuary RME Report* ** 2018 RME Report submitted by Estuary Partnership$3,3450.05%12/01/201802/01/2019
K192919132Produce Progress (Annual) ReportSubmit Progress Report for the period (July 2017) to (June 2018)Progress reports summarize the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, long-term planning, and monitoring outcomes and deliverables. Date range July 2017 to June 2018. For an ongoing project, a progress report covering a contract period will be submitted within contract period. Progress reports will conform to BPA guidelines.$3,3450.05%07/01/201706/30/2018
L192920132Produce Progress (Annual) ReportSubmit Progress Report for the period (July 2018) to (June 2019)Progress reports summarize the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, long-term planning, and monitoring outcomes and deliverables. Date range July 2018 to June 2019. For an ongoing project, a progress report covering a contract period will be submitted within contract period. Progress reports will conform to BPA guidelines.$3,3450.05%07/01/201806/30/2019
M19292185Remove/Breach Fish Passage BarrierFLIGHTS END - Water control structure removalAt the Flights End restoration area 3 undersized culverts and associated fill will be removed to fully reconnect the wetland habitat, and eliminate the salmon stranding danger at the site. Once removed, approximately 42 acres of floodplain wetlands will be connected to Crane Slough and the Multnomah Channel. The culvert removal designs will be detailed in the construction plan set developed by CREST and our design consultant, Wolf Water Resources. * All projects in the estuary are subject to cost benefit analysis and approval by BPA. Each of the projects CREST is proposing during this contract undergo a cost/SBU preliminary review and final scoring by ERTG. If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet costs/SBU CREST will work with BPA to address. For all construction contracts over $20,000 CREST utilizes our procurement procedures through an RFP and competitive bid process.$103,0181.61%07/01/201701/31/2018
N192922184Install Fish Passage StructureFLIGHTS END- Install light duty bridgeAt the Fights End project site, a fish passable bridge will be installed over 1 of the existing barriers to provide for pedestrian and land management access. The bridge has been designed to be fully fish passable and allow full connection to tidal inundation. Bridge installation designs will be detailed in the construction plan sets developed by CREST and our design consultant, Wolf Water Resources. * All projects in the estuary are subject to cost benefit analysis and approval by BPA. Each of the projects CREST is proposing during this contract undergo a cost/SBU preliminary review and final scoring by ERTG. If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet costs/SBU CREST will work with BPA to address. For all construction contracts over $20,000 CREST utilizes our procurement procedures through an RFP and competitive bid process.$147,0002.30%07/01/201701/31/2018
O192923181Create, Restore, and/or Enhance WetlandFLIGHTS END - Wetland enhancementAt the Flights End restoration site11 acres of wetland will be enhanced through marsh plain lowering. Lowering the elevation of this area will convert the existing low quality, wetland dominated by reed canary grass into wet prairie habitat. Additionally, 2 new channel connections will be created to restore connection between the wetlands and the slough, and 3 beaver dam analogues will be installed to emulate natural ponding and induce additional in-water complexity. Wetland treatment designs will be detailed in construction plan set developed by CREST and our design consultant, Wolf Water Resources. * All projects in the estuary are subject to cost benefit analysis and approval by BPA. Each of the projects CREST is proposing during this contract undergo a cost/SBU preliminary review and final scoring by ERTG. If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet costs/SBU CREST will work with BPA to address.$142,6002.23%07/01/201701/31/2018
P19292447Plant VegetationFLIGHTS END - RevegetationAt the Flights End Restoration site a total of11 acres of native plant revegetation will be installed within the lowered marshplain area. Once completed, revegetated habitat will be fully exposed to tidal inundation from Crane Slough and the Multnomah Channel. Revegetation treatment designs will be detailed in construction plan set developed by CREST and our design consultants. Revegetation involves native wetland emergent and wet prairie plants. * All projects in the estuary are subject to cost benefit analysis and approval by BPA. Each of the projects CREST is proposing during this contract undergo a cost/SBU preliminary review and final scoring by ERTG. If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet costs/SBU CREST will work with BPA to address.$19,8070.31%07/01/201701/31/2018
Q19292585Remove/Breach Fish Passage BarrierENYARTS/MCCARTHY CREEK- Fish passage barrier removalAt the Enyarts/McCarthy Creek restoration area 2 undersized culverts and associated fill will be removed to connect 71 acres of floodplain wetlands and backwater sloughs. The culvert removal designs will be detailed in the construction plan set developed by CREST and our design consultant, Wolf Water Resources. * All projects in the estuary are subject to cost benefit analysis and approval by BPA. Each of the projects CREST is proposing during this contract undergo a cost/SBU preliminary review and final scoring by ERTG. If at any time during the scientific review and ERTG process it is determined that proposed restoration projects do not meet costs/SBU CREST will work with BPA to address. For all construction contracts over $20,000 CREST utilizes our procurement procedures through an RFP and competitive bid process.$22,6370.35%07/01/201701/31/2018
      
$6,399,776
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain and provide BPA with Environmental Compliance Documentation B: 165. Produce EC for projects 06/30/2019 06/30/2019
CREST Administrative Oversight of BPA Contract C: 119. Manage and Administer Projects 06/30/2019 06/30/2019
Public Outreach via Newsletters, Presentations, Educational Materials D: 99. Meetings, Newsletters, and Education 06/30/2019 06/30/2019
Three to five ERTG Templates/Project Proposals Per Year E: 114. Systematically Identify, Prioritize, and Select Projects 06/30/2019 06/30/2019
Complete Construction Management F: 100. CREST oversight of purchasing, contracting, permit compliance of active projects 06/30/2019 06/30/2019
Surveys and Early Project Development G: 175. PROJECT DEVELOPMENT-- Surveys and Early Project Development 06/30/2019 06/30/2019
Input/Share Data H: 159. Participate in Regional Data Rollup Projects 06/30/2019 06/30/2019
Annual Report of Restoration Accomplishments K: 132. Submit Progress Report for the period (July 2017) to (June 2018) 06/30/2018 06/30/2018
Annual Report of Restoration Accomplishments L: 132. Submit Progress Report for the period (July 2018) to (June 2019) 06/30/2019 06/30/2019
Flights End - Culvert Removal M: 85. FLIGHTS END - Water control structure removal 01/31/2018 09/15/2017
Flights End- Light Duty Bridge Installation N: 184. FLIGHTS END- Install light duty bridge 01/31/2018 09/22/2017
Flights End- Wetland Enhancement O: 181. FLIGHTS END - Wetland enhancement 01/31/2018 09/29/2017
Flights End - Native Plant Revegetation P: 47. FLIGHTS END - Revegetation 01/31/2018 12/31/2017
Enyarts/McCarthy Creek- Culvert Removal Q: 85. ENYARTS/MCCARTHY CREEK- Fish passage barrier removal 01/31/2018 08/03/2017
Enyarts/McCarthy Creek- Wetland Enhancement R: 181. ENYARTS/MCCARTHY CREEK- PHASE 2--Marsh plain lowering 06/30/2019
Enyarts/McCarthy Creek - Native Plant Revegetation S: 47. ENYARTS/MCCARTHY CREEK - Revegetation 06/30/2019
Bear and Mary's Creeks- Designs T: 175. BEAR AND MARY'S CREEKS - Design 07/16/2018 07/16/2018
Bear and Mary's Creeks - Levee Removal U: 180. BEAR AND MARY'S CREEKS - Breach levee 01/31/2019 09/14/2018
Bear and Mary's Creek- Pilot Channel Creation V: 30. BEAR AND MARY'S CREEKS - Pilot channel creation 01/31/2019 09/14/2018
Bear and Mary's Creek- Culvert Removal W: 85. BEAR AND MARY'S CREEKS - Fish passage barrier removal 01/31/2019 09/14/2018
Bear and Mary's Creek- Revegetation X: 47. BEAR AND MARY'S CREEKS - Revegetation 01/31/2019 02/28/2019
Ferris Creek- Designs Y: 175. FERRIS CREEK - Design 07/13/2018 07/16/2018
Ferris Creek- Levee Removal Z: 180. FERRIS CREEK - Breach Levee 01/31/2019 09/14/2018
Ferris Creek - Channel Creation AA: 30. FERRIS CREEK - Channel creation 01/31/2019 09/14/2018
Ferris Creek - Native Plant Revegetation AB: 47. FERRIS CREEK - Revegetation 01/31/2019 02/28/2019
West Sand Island- Design AC: 175. WEST SAND ISLAND - Design 06/30/2019
***CCR-41986 MODIFY: West Sand Island- Berm Removal AD: 180. ***CCR-41986 MODIFY: WEST SAND ISLAND - Remove berm 06/30/2019
***CCR-41986 MODIFY: West Sand Island - Channel Creation AE: 30. ***CCR-41986 MODIFY: WEST SAND ISLAND- Channel creation 06/30/2019
West Sand Island- Invasive Plant Treatment AF: 199. WEST SAND ISLAND- Invasive plant treatment 06/30/2019
***CCR-41986 MODIFY: West Sand Island- Native Plant Revegetation AG: 47. ***CCR-41986 MODIFY: WEST SAND ISLAND - Revegetation 06/30/2019
John Day #11 - Design AH: 175. JOHN DAY #11 - Design 06/30/2019 06/30/2019
Palensky Wildlife Area- Design AK: 175. PALENSKY WILDLIFE AREA - Design 06/30/2019
Government Island - Design AL: 175. GOVERNMENT ISLAND - Design 06/30/2019 06/17/2019
Aldrich Point Railroad Crossing- Design AM: 175. ALDRICH POINT RAILROAD CROSSING - Design 06/30/2019
Wolf Bay Railroad Crossing- Design AN: 175. WOLF BAY RAILROAD CROSSING - Design 06/30/2019
Dairy Creek- Design AO: 175. DAIRY CREEK - Design 03/31/2018 02/15/2018
Sauvie Island Planning- PC Trask Project Assistance AP: 175. SAUVIE ISLAND PLANNING- PC Trask project assistance 06/30/2019 06/30/2019
Analyze and Record AEMR Level 3 Data AQ: 162. Analyze Level 3 AEMR Data 06/30/2019 06/30/2019
Level 3 AEMR data- Pre-construction AR: 157. AEMR (Level 3): Collect PRE-Construction AEMR Level 3 data 06/30/2019 06/30/2019
Level 3 AEMR data--Post-construction AS: 157. AEMR (Level 3): Collect POST-Construction AEMR Level 3 data 06/30/2019 06/30/2019
Level 3 AEMR data- Pre and Post- Construction AT: 157. AEMR (Level 3): Collect PRE and POST-Construction AEMR Level 3 data 06/30/2019 06/30/2019
Enyarts/McCarthy Creek-- Phase II 100% Designs AU: 175. *CCR-40186: ENYARTS/MCCARTHY CREEK- PHASE 2 DESIGN 06/30/2019 05/17/2019
Dairy Creek-- Fish Passage Barrier Removal AV: 85. *CCR-40186: DAIRY CREEK-- CONSTRUCTION-- Culvert Removal 10/31/2018 10/31/2018
Dairy Creek--- Install Bridge AW: 184. *CCR-40186: DAIRY CREEK- CONSTRUCTION-- Bridge Installation 10/31/2018 10/31/2018
Dairy Creek-- Channel Enhancement AX: 30. *CCR-40186: DAIRY CREEK- CONSTRUCTION-- Channel enhancement 10/31/2018 10/31/2018
Dairy Creek-- Plant Riparian Vegetation AY: 47. *CCR-40186: DAIRY CREEK CONSTRUCTION-- Revegetation 02/28/2019 02/28/2019
Provide ACOE with survey and preliminary design work necessary for 408 deauthorization AZ: 175. **CCR-40786--TOAHEEDLIINI/NOVAK-- Surveys & Preliminary Design for 408 deauthorization process 06/30/2019 10/23/2018
Plant Vegetation BA: 47. ***CCR-41986-- South Bachelor Island - Phase I 06/30/2019

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 199 Remove Vegetation
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 7 instances of WE 47 Plant Vegetation
  • 3 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 5 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 13 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
  • 1 instance of WE 162 Analyze/Interpret Data
  • 1 instance of WE 100 Construction Management
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 7 instances of WE 47 Plant Vegetation
  • 3 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 5 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 13 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
  • 1 instance of WE 162 Analyze/Interpret Data
  • 1 instance of WE 100 Construction Management
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 6 instances of WE 47 Plant Vegetation
  • 3 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 5 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 3 instances of WE 184 Install Fish Passage Structure
  • 13 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
  • 1 instance of WE 100 Construction Management
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 47 Plant Vegetation
Cutthroat Trout, Coastal (Oncorhynchus clarkii clarkii) - All Anadromous Populations
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 5 instances of WE 47 Plant Vegetation
  • 2 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 4 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 2 instances of WE 184 Install Fish Passage Structure
  • 6 instances of WE 175 Produce Design
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 199 Remove Vegetation
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 6 instances of WE 47 Plant Vegetation
  • 2 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 5 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 3 instances of WE 184 Install Fish Passage Structure
  • 13 instances of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 07/01/2017
B 165 Produce EC for projects 07/01/2017
C 119 Manage and Administer Projects 07/01/2017
D 99 Meetings, Newsletters, and Education 07/01/2017
E 114 Systematically Identify, Prioritize, and Select Projects 07/01/2017
F 100 CREST oversight of purchasing, contracting, permit compliance of active projects 07/01/2017
G 175 PROJECT DEVELOPMENT-- Surveys and Early Project Development 07/01/2017
H 159 Participate in Regional Data Rollup Projects 07/01/2017
I 132 Provide data for estuary 2017 RME Report 07/01/2017
J 132 Provide data for estuary 2018 RME Report 07/01/2017
K 132 Submit Progress Report for the period (July 2017) to (June 2018) 07/01/2017
L 132 Submit Progress Report for the period (July 2018) to (June 2019) 07/01/2017
M 85 FLIGHTS END - Water control structure removal 08/07/2017
N 184 FLIGHTS END- Install light duty bridge 08/07/2017
O 181 FLIGHTS END - Wetland enhancement 08/07/2017
P 47 FLIGHTS END - Revegetation 08/07/2017
Q 85 ENYARTS/MCCARTHY CREEK- Fish passage barrier removal 07/01/2017
R 181 ENYARTS/MCCARTHY CREEK- PHASE 2--Marsh plain lowering 07/01/2017
S 47 ENYARTS/MCCARTHY CREEK - Revegetation 07/01/2017
T 175 BEAR AND MARY'S CREEKS - Design 06/29/2018
U 180 BEAR AND MARY'S CREEKS - Breach levee 06/29/2018
V 30 BEAR AND MARY'S CREEKS - Pilot channel creation 06/29/2018
W 85 BEAR AND MARY'S CREEKS - Fish passage barrier removal 06/29/2018
X 47 BEAR AND MARY'S CREEKS - Revegetation 06/29/2018
Y 175 FERRIS CREEK - Design 06/29/2018
Z 180 FERRIS CREEK - Breach Levee 06/29/2018
AA 30 FERRIS CREEK - Channel creation 06/29/2018
AB 47 FERRIS CREEK - Revegetation 06/29/2018
AC 175 WEST SAND ISLAND - Design
AD 180 ***CCR-41986 MODIFY: WEST SAND ISLAND - Remove berm
AE 30 ***CCR-41986 MODIFY: WEST SAND ISLAND- Channel creation
AF 199 WEST SAND ISLAND- Invasive plant treatment
AG 47 ***CCR-41986 MODIFY: WEST SAND ISLAND - Revegetation
AH 175 JOHN DAY #11 - Design
AI 85 **CCR-40786-CANCELLED: JOHN DAY #11- Fish passage barrier removal
AJ 184 **CCR-40786-CANCELLED: JOHN DAY #11- Install Bridge
AK 175 PALENSKY WILDLIFE AREA - Design 07/01/2017
AL 175 GOVERNMENT ISLAND - Design 07/01/2017
AM 175 ALDRICH POINT RAILROAD CROSSING - Design 07/01/2017
AN 175 WOLF BAY RAILROAD CROSSING - Design 07/01/2017
AO 175 DAIRY CREEK - Design
AP 175 SAUVIE ISLAND PLANNING- PC Trask project assistance 07/01/2017
AQ 162 Analyze Level 3 AEMR Data 07/01/2017
AR 157 AEMR (Level 3): Collect PRE-Construction AEMR Level 3 data 07/01/2017
AS 157 AEMR (Level 3): Collect POST-Construction AEMR Level 3 data 07/01/2017
AT 157 AEMR (Level 3): Collect PRE and POST-Construction AEMR Level 3 data 07/01/2017
AU 175 *CCR-40186: ENYARTS/MCCARTHY CREEK- PHASE 2 DESIGN 03/05/2019
AV 85 *CCR-40186: DAIRY CREEK-- CONSTRUCTION-- Culvert Removal 06/26/2018
AW 184 *CCR-40186: DAIRY CREEK- CONSTRUCTION-- Bridge Installation 06/26/2018
AX 30 *CCR-40186: DAIRY CREEK- CONSTRUCTION-- Channel enhancement 06/26/2018
AY 47 *CCR-40186: DAIRY CREEK CONSTRUCTION-- Revegetation 06/26/2018
AZ 175 **CCR-40786--TOAHEEDLIINI/NOVAK-- Surveys & Preliminary Design for 408 deauthorization process
BA 47 ***CCR-41986-- South Bachelor Island - Phase I