A | 76938 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR. | $624 | 0.26% | 04/01/2011 | 11/30/2011 |
B | 76939 | 119 | Manage and Administer Projects | Bridge Creek IMW Project Management: specific tasks include budget tracking and permitting | Assist NOAA-Fisheries and EcoLogical Research (CR-101707) in managing Bridge Creek IMW for the John Day basin. Specific tasks include project coordination (phone call scheduling) and fulfilling permitting requirements for the project. | $5,000 | 2.08% | 12/01/2010 | 10/01/2011 |
C | 76940 | 141 | Produce Other Reports | Develop Data Management Guidance Documents | Develop guidance documents describing the process, guidelines, and recommendations for utilizing data management programs to facilitate monitoring programs. | $20,000 | 8.33% | 01/01/2011 | 11/30/2011 |
D | 76941 | 189 | Coordination-Columbia Basinwide | Data management coordination for pilot basins | Participate in regional coordination meetings that facilitate ISEMP development and data management practices in PNW monitoring programs. | $17,200 | 7.17% | 12/01/2010 | 11/30/2011 |
E | 76942 | 161 | Disseminate Raw/Summary Data and Results | Tabular data support for pilot basins | Volk Consulting will provide raw data QAQC support to pilot basins as needed to supplement Data Stewards. Note that it is the primary duty of Data Stewards to provide QAQC support and Volk Consulting will assist Data Stewards only when Data Steward timelines for work completion do not meet the timeline needs of ISEMP data analysts. Volk Consulting is explicitly responsible for QA/QC checks on all datasets collected in Bridge Creek basin from 2010-2011. | $25,000 | 10.42% | 12/01/2010 | 11/30/2011 |
F | 76943 | 183 | Produce Journal Article | Data QAQC strategies for multi-agency monitoring programs | In 2010, ISEMP continued data management documentation and strategy development by creating Survey Type - specific guidelines for data QAQC. In 2011, these Survey Type specific strategies will be pulled together into a QAQC manuscript. | $26,520 | 11.05% | 12/01/2010 | 11/30/2011 |
G | 76945 | 183 | Produce Journal Article | Wenatchee Status and Trend monitoring project journal article | In 2011 we plan to write and submit a manuscript describing the Wenatchee Status and Trend Monitoring habitat dataset. | $15,000 | 6.25% | 12/01/2010 | 11/30/2011 |
H | 76946 | 161 | Disseminate Raw/Summary Data and Results | Organization and updates of spatial datasets for pilot basins | Spatial datasets collected within pilot basins will be made available via the web. Dataset availability will depend on data format and metadata. This process can require a considerable amount of effort standardizing data formats and projections unique to agency datasets and will be performed as needed. | $24,200 | 10.08% | 12/01/2010 | 11/30/2011 |
I | 76948 | 161 | Disseminate Raw/Summary Data and Results | ISEMP and STEM website development and updates | Quarterly updates of the ISEMP website are needed to ensure up to date delivery of ISEMP products through the website. The STEM website also needs updated metadata on imagery, documents, and experimental design elements for data already in STEM. Continued task from 2010. | $15,000 | 6.25% | 12/01/2010 | 11/30/2011 |
J | 76950 | 162 | Analyze/Interpret Data | Tabular data support for data analysis in pilot basins | ISEMP data analysts require spatial and database support for data analyses planned in 2010. This work element will provide technical support for analysts working on projects associated with ISEMP. | $29,000 | 12.08% | 01/01/2011 | 11/30/2011 |
K | 76951 | 174 | Produce Plan | Participate in RME planning process for pilot basins | The ISEMP requires planning and documentation support for all ISEMP basins to ensure goals and projects are aligned appropriately within ISEMP. This work elements provides for review time of ISEMP documents and participation in ISEMP coordination meetings. | $8,056 | 3.36% | 12/01/2010 | 11/30/2011 |
L | 76953 | 157 | Collect/Generate/Validate Field and Lab Data | Collect field data for monitoring beaver dam support structures in Bridge Creek | Beaver dam support structures installed in 2008 and 2009 will require monitoring. This work element provides for the narrative development of this protocol, assist in the collection of field data under this protocol as needed, and entry of field data into an electronic format according to this protocol. | $15,000 | 6.25% | 12/01/2010 | 11/30/2011 |
M | 76954 | 132 | Produce Progress (Annual) Report | Produce annual report for Volk Consulting and Bridge Ck. environmental data | The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole. Date range 12/1/10 to 11/30/11 will be agreed upon by the COTR and the contractor. This may or may not coincide with the contract period. For an ongoing project, a progress report covering a contract period may be submitted under the subsequent contract, if approved by the COTR.
Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments.
If producing a technical report for this contract, a discrete experiment, or a peer-reviewed publication, use work element 183: Produce Journal Article.
Produce annual report for Bridge Creek IMW for surface water, ground water, beaver dam food supply and discharge monitoring programs. Reports will include other environmental variables as needed for data analyses (e.g. habitat data). Produce annual report of surface water, ground water, discharge, beaver food supply and dam monitoring projects in Bridge Creek. | $7,000 | 2.92% | 09/01/2011 | 11/30/2011 |
N | 76955 | 165 | Produce Environmental Compliance Documentation | Provide Environmental Compliance Documentation for Work Element U. | The NOAA BiOp for the Bridge Creek IMW and BLM NEPA documentation will be provided as Environmental Compliance documentation. | $400 | 0.17% | | 11/30/2011 |
O | 76956 | 47 | Plant Vegetation | Plant and fence riparian stakes along Bridge Creek | Plant and fence riparian stakes along Bridge Creek. | $17,000 | 7.08% | 12/01/2010 | 11/30/2011 |
P | 80888 | 183 | Produce Journal Article | Manuscript for Bridge Creek project (riparian planting or monitoring dataset) | Volk Consulting will work with Bridge Creek coordinators and crews to draft and submit a peer-reviewed manuscript about riparian planting, beaver dam or monitoring work. | $15,000 | 6.25% | 02/01/2011 | 11/30/2011 |